Pacific Sheet Metal Works v. Californian Canneries Co.

164 F. 980, 1908 U.S. App. LEXIS 4706
CourtCourt of Appeals for the Ninth Circuit
DecidedOctober 12, 1908
DocketNo. 1,531
StatusPublished
Cited by3 cases

This text of 164 F. 980 (Pacific Sheet Metal Works v. Californian Canneries Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Sheet Metal Works v. Californian Canneries Co., 164 F. 980, 1908 U.S. App. LEXIS 4706 (9th Cir. 1908).

Opinion

DE PIA VEN, District Judge.

This action was brought by the Californian Canneries Company, Limited, a corporation, to recover damages from the Pacific Sheet Metal Works, a corporation, for alleged breach of contract.

The complaint charges that plaintiff and defendant entered into a contract by which the plaintiff agreed to purchase, and defendant agreed to sell and deliver to plaintiff, between July 13 and December 31, 1899, as and when ordered, all the tin cans which should be used in plaintiff’s cannery at San Francisco during the packing season of 1899, not exceeding 100,000 cans in any one day; that at the time of the execution of the contract defendant knew that plaintiff was engaged in the business of canning green fruit and vegetables, and, in reliance upon the performance of said contract by defendant, would purchase large quantities of green fruits and vegetables, and would enter into contracts for the sale and delivery thereof when canned, and that unless said cans were promptly delivered, as ordered, the plaintiff would be unable to pack all of the fruit and vegetables purchased for canning, or comply with its contracts for the sale and delivery of such canned products, and would lose the profit which it would otherwise make from the sale of the same. The complaint further alleges that defendant did not deliver the number or variety of cans ordered by plaintiff under said agreement; that plaintiff thereby sustained damage in the sum of $28,578, on account of fruit which it was compelled to throw away, loss of profit which it would have made if such fruit had been canned, and for wages paid its employes during times when they were idle, waiting for defendant to make delivery of the cans contracted for.

The answer of defendant denies all of the material allegations of the complaint, and then alleges that the only contract made between the plaintiff and defendant is the one fully set out in .the answer, the material parts of which are as follows:

“This agreement executed in duplicate by and between the Pacific Sheet Metal Works, hereinafter called seller, and Californian Canneries Company, Ltd., of Newcastle on Tyne, England, hereinafter called buyer, witnesseth:
“1. The seller agrees to sell and deliver to the buyer, and the buyer agrees to purchase and receive of and from the seller, all the tin cans which shall be used in its or their cannery at San Francisco, during the packing season of 1899, not exceeding, however,' 100,000 cans in any one day.”
“4. Place of delivery f. o. b. San Francisco, at its cannery.
* * & -J* * *
“8. If the seller shall be unable to perform any of its obligations under this contract, by reason of strike or of damage by the elements, or of any unavoidable casualty, such obligations shall at once terminate and cease.”

The answer also alleges, as matters of defense:

“(1) That a strike was inaugurated in defendant’s factory on August 24, 1899, by its workmen, whereby it was released from performing its contract
[982]*982■ “(2) That, at the date of the contract between plaintiff and defendant, defendant had on board the ship Ancois, then on her way from Liverpool to San Francisco, enough tin plate for the manufacture of 5,000,000 tin cans. That said ship, with said tin plate on board, sailed from Liverpool, England, on January 28, 1809. That the usual time required for a voyage for such a ship from Liverpool to the port of San Francisco is from 115 days to 140 days; but she did not arrive in San Francisco until July 80, 1809, having been 182 days on her voyage; that the Ancois was in all respects seaworthy and fit for the voyage in which she was engaged, and that the delay in arriving at San Francisco was caused by damage done to her by the storms and high winds which she encountered in making the voyage.”

The case was tried by the court without a jury, and the court found:

That the contract between plaintiff and defendant is correctly set forth in the answer; that—

“the defendant between August. 8. 1899, and September 13, 1899, failed to deliver to plaintiff 143,000 cans, under and in accordance with the terms of the contract of April 12, 1899.
“That on the 24th and 2oth days of August, 1899, there was a strike in defendant's factory, which released the defendant from the necessity of complying with the orders of plaintiff for those two days, and that plaintiff was not entitled to demand cans from defendant on Sundays and other legal holidays, during the period of the said contract, but that the said defendant failed to deliver to plaintiff 143,000 cans under the terms of said contract, exclusive of those cans from which it was released by reason of the said strike, and cans ordered on Sundays and holidays.”

The court further found that the defendants purchased in England, and shipped on board the Ancois, enough tin plate for the manufacture of 5,000,000 tin cans; that said ship sailed from Liverpool, England, for San Francisco on January 28, 1899, that the usual time required for such a voyage, by a vessel like the Ancois, is from 115 to 140 days; that she did not arrive at the port of San Francisco until July 30, 1899, 182 days after leaving Liverpool; that this delay was caused by heavy storms and calms encountered by the ship.

Upon these and other findings as to the loss of fruit which plaintiff was compelled to throw away because of nondelivery of cans, and loss of profit upon fruit which would have been canned had defendant furnished the cans which plaintiff was entitled to receive under the contract, and wages paid by plaintiff to its employes during times when they were idle because cans were not delivered when ordered, the court found that plaintiff had sustained damage, by reason of defendant’s breach of contract, in the sum of $7,264.75, with interest thereon at 7 per cent, per annum from December 22, 1900, and after deducting therefrom $1,640.72, with interest at the rate of 6 per cent, per annum from January 1, 1900, which it allowed defendant as a set-off, the court further found that plain-tiff was entitled to recover from defendant $8,084.57. Judgment was thereupon entered in favor of the plaintiff for that sum with costs. Th& case is brought here by the defendant on a writ of error.

1. The plaintiff in error insists that the Circuit Court erred in finding that there was a failure on its part to deliver 143,000 or any number of cans, required or needed by the defendant in error at its cannery. Whether there was such failure or not is a pure question of fact, and this being an action at law, and before us on writ of error, [983]*983the finding of the Circuit Court as to the fact, if there was any evidence upon which to base the finding, is conclusive here. King v. Smith, 110 Fed. 95, 49 C. C. A. 46, 54 L. R. A. 708; Eureka County Bank v. Clarke, 130 Fed. 326, 64 C. C. A. 571; Dooley v. Pease, 180 U. S. 126, 21 Sup. Ct. 329, 45 L. Ed. 457; Stanley v. Supervisors, 121 U. S. 547, 7 Sup. Ct. 1234, 30 L. Ed. 1000; Runkle v. Burnham, 153 U. S. 216, 14. Sup. Ct. 837, 38 L. Ed. 694; Hathaway v. Bank, 134 U. S. 494, 10 Sup. Ct. 608, 33 L. Ed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mitchell Canneries, Inc. v. United States
77 F. Supp. 498 (Court of Claims, 1948)
Eddy v. National Union Indemnity Co.
78 F.2d 545 (Ninth Circuit, 1935)
McFarland v. Savannah River Sales Co.
247 F. 652 (Third Circuit, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
164 F. 980, 1908 U.S. App. LEXIS 4706, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-sheet-metal-works-v-californian-canneries-co-ca9-1908.