Pacific Sash and Door Co. v. Elderton

140 P. 247, 167 Cal. 563, 1914 Cal. LEXIS 500
CourtCalifornia Supreme Court
DecidedMarch 31, 1914
DocketL.A. No. 3227.
StatusPublished

This text of 140 P. 247 (Pacific Sash and Door Co. v. Elderton) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Sash and Door Co. v. Elderton, 140 P. 247, 167 Cal. 563, 1914 Cal. LEXIS 500 (Cal. 1914).

Opinion

SLOSS, J.

A number of actions for the foreclosure of mechanics’ liens having been consolidated, a judgment of *564 foreclosure was entered. The defendant Elderton, owner of the land and building involved, appeals from the judgment and from an order denying his motion for a new trial. The contract was made, and the building erected, prior to the amendments of 1911 to the code sections governing mechanics’ liens and the questions presented must therefore be decided according to the law in force at the time of the transactions giving rise to this controversy.

Elderton, as owner, made a contract with one Saffell, as contractor, for the construction of a building, which was thereafter duly completed. The contract price was sixteen thousand three hundred dollars payable in installments. Six progress payments of one thousand dollars each were provided for, then a completion payment of $6,225, and finally, a payment of $4,075, or twenty-five per cent of the total contract price, thirty-five days after the building, should be completed and accepted. The contract complied in all respects with the code requirements for the making and filing of a valid building contract.

The claims of the various plaintiffs in the consolidated actions aggregated - $9,129.30. The defendant Elderton answered, alleging that he had paid the contractor at the times when they were payable, respectively, the first seven installments of the contract price, including the completion payment of $6,225, and that he held the amount of the final payment, $4,075, in his hands, applicable to the payment of liens. . In his answer he offered to pay said sum of $4,075 into court for distribution among such persons as might be determined to be entitled thereto. The court found that the owner had paid to the contractor pursuant to the terms of the contract only $10,225 (instead of $12,225, as stated in the answer), and that $6,075 remained unpaid and applicable to the liens of the plaintiffs. It found, further, that it was not true that all payments had been made when due. Judgment was rendered accordingly.

The various plaintiffs filed, within the proper time after the filing of notice of completion, their claims of lien in regular form. It was stipulated that “no notice under section 1184 of the Code of Civil Procedure . . . was ever served on the owner of said premises by any lien claimant requiring said owner to withhold any money from the contractor.” *565 That the various plaintiffs had furnished labor and material to the amounts claimed by them was not, and is not now, in controversy.

It was shown beyond dispute that, at the time of the filing of the various liens, the contractor had been paid by the owner all of the progress payments, including the completion payment of $6,225. All that then remained due, as between the owner and the contractor, was the thirty-five day payment of twenty-five per cent. There was, however, evidence tending to prove that on two or three occasions during the progress of the work, the owner had made to the contractor advances aggregating two thousand dollars, before the amounts so advanced were payable under the contract. Such amounts were then deducted out of the succeeding payments as they became due.

The question of law to be decided is whether lien claimants who have not served notices to withhold may, in case of a valid contract, compel the owner to pay them, in addition to the twenty-five per cent, amounts of prior payments actually earned by the contractor on or before completion, but advanced by the owner before the date when such payments were due under the contract. The question is not a new one in this court. In Sweeney v. Meyer, 124 Cal. 512, [57 Pac. 479 ], the court held against the contention made by the appellant here, viz., that, as the only fund available to the lien claimant who has served no notice is the thirty-five day payment of twenty-five per cent, such claimant is not affected by, and cannot take advantage of, the fact that other payments were prematurely made. The provisions of section 1184 that “no payment made prior to the time when the same is due, under the terms and conditions of the contract, shall be valid for the purpose of defeating, diminishing, or discharging any lien in favor of any person except the contractor, but as to such lien such payment shall be deemed as if not made, and shall be applicable to such liens, ’ ’ was quoted, and it was said that this provision “is not made dependent upon the giving or the failure to give notice.” Sweeney v. Meyer was decided in Department Two and a petition for a hearing in Bank was denied, the Chief Justice dissenting. In Ganahl v. Weir, 130 Cal. 237, [62 Pac. 512] which followed shortly *566 after, the same conclusion was announced by Department One of this court.

The question was again under consideration in Valley Lumber Co. v. Struck, 146 Cal. 266, [80 Pac. 405]. In this case the contract provided that a certain sum should be paid when the building was completed and accepted by the architect. The payment was made upon the completion of the building, but two days before the acceptance by the architect. Upon the first submission of the case, which was in Bank, a judgment holding the owner liable to lien claimants for such payment (which was treated as premature) was affirmed on the authority of Sweeney v. Meyer, 124 Cal. 512, [57 Pac. 479].) The opinion, prepared by Mr. Justice Shaw, was concurred in by four members of the court. The Chief Justice dissented, filing an opinion in which he gave his reasons for thinking the decision in Sweeney v. Meyer erroneous. Mr. Justice Angellotti dissented on another ground, but added the statement that, if the question had been new, he would have agreed with the views of the Chief Justice. A rehearing was granted, and the appeal again came before the court in Bank. On the second submission, the judgment was reversed, a majority of the court talcing the position that, as the clause requiring approval by the architect was for the benefit of the owner solely, it might be waived by him, and a payment made in advance of such approval was not to be regarded as premature so far as the plaintiff’s rights were concerned. It thus became unnecessary to decide the question of the effect of a premature payment, if one had been made. Mr. Justice Shaw concurred, taking the position that the payment was premature, but that, for the reasons stated in the dissenting opinion of the Chief Justice on the former submission, the rights of the lien claimants were not affected by such payment. In this opinion the Chief Justice concurred, and Mr. Justice Angellotti concurred in a separate opinion in which he, for like reasons, expressed the view that Sweeney v. Meyer should be overruled.

In view of the judicial history just recited, the question of law here presented cannot be said to be finally settled by our decisions. It is true that the contention of the respondents has been twice upheld in Department. But at a later date, a Bank decision to the same effect was set aside. Upon re *567 submission the appeal was disposed of upon other grounds.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ganahl v. Weir
62 P. 512 (California Supreme Court, 1900)
Valley Lumber Co. v. Struck
80 P. 405 (California Supreme Court, 1905)
Hampton v. Christensen
84 P. 200 (California Supreme Court, 1906)
West Coast Lumber Co. v. Knapp
54 P. 533 (California Supreme Court, 1898)
Sweeney v. Meyer
57 P. 479 (California Supreme Court, 1899)

Cite This Page — Counsel Stack

Bluebook (online)
140 P. 247, 167 Cal. 563, 1914 Cal. LEXIS 500, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-sash-and-door-co-v-elderton-cal-1914.