Pacific Power & Light Co. v. Bonneville Power Administration

795 F.2d 810
CourtCourt of Appeals for the Ninth Circuit
DecidedJuly 28, 1986
DocketNo. 84-4072
StatusPublished
Cited by5 cases

This text of 795 F.2d 810 (Pacific Power & Light Co. v. Bonneville Power Administration) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Power & Light Co. v. Bonneville Power Administration, 795 F.2d 810 (9th Cir. 1986).

Opinion

GOODWIN, Circuit Judge.

This direct action was filed in district court against the Bonneville Power Administration (BPA) raising' issues within the scope of the Pacific Northwest Electric Power Planning and Conservation Act, 16 U.S.C. § 839 et seq. Appellants electric utilities appeal the district court’s dismissal of their action for want of jurisdiction. Because exclusive jurisdiction lies in this court under 16 U.S.C. § 839f(e)(5), we affirm the dismissal.

This appeal is limited to the question of district court jurisdiction. Some factual background will place the question in perspective. One purpose of the Pacific Northwest Electric Power Planning and Conservation Act was to reduce the disparity in electric rates between customers of investor-owned utilities and preference customers of BPA. See generally Blumm, The Northwest’s Hydroelectric Heritage: Prologue to the Pacific Northwest Electric Power Planning and Conservation Act, 58 Wash.L.Rev. 175, 228 (1983). To that end, the Act requires BPA to enter into agreements with investor-owned utilities to enable those utilities to exchange their own, higher-priced power for an equivalent amount of lower-priced BPA power. 16 U.S.C. § 839c(c). While these agreements are called residential energy exchange agreements, there is not, in fact, any exchange of energy at all, but merely an accounting transaction in which BPA credits a subsidy to investor-owned utilities based upon each utility’s average system cost. The Act authorizes the BPA to determine average system cost. 16 U.S.C. § 839c(c)(7). The methodology for calculating average cost is subject to review and approval by the Federal Energy Regulatory Commission (FERC). Id. See 18 C.F.R. Part 300 (1984). In this case, the investor-owned utilities challenge that methodology.

Following the statutorily required consultation process, 16 U.S.C. § 839c(c)(7), BPA adopted an average cost methodology in August 1981. BPA implemented the methodology when FERC approved it on an interim basis, cf. 18 C.F.R. § 300.20 (1984), in October 1981, 46 Fed.Reg. 50,517 (Oct. 14, 1981), corrected, 46 Fed.Reg. 55,952 (Nov. 13, 1981), codified at 18 C.F.R. § 35.13a (1982). FERC gave final approval without substantive changes in October 1983. 48 Fed.Reg. 46,970 (Oct. 17, 1983); 18 C.F.R. Part 301 (1984).

Even before interim or final FERC approval of the methodology, BPA entered into exchange agreements with investor-owned utilities which incorporated the average cost methodology it had adopted. Those agreements restrict the manner in which BPA may change the methodology. The agreements allow BPA to change the methodology during the course of the agreements, but only after consultation with the affected utilities and the Northwest Power Planning Council, and not within one year of FERC approval of the immediately previous methodology.1

[813]*813Two years after BPA adoption and interim FERC approval of the average cost methodology (but only days after final FERC approval), BPA began a consultation process for changing the methodology. See 48 Fed.Reg. 45,829 (Oct. 7,1983). BPA issued a proposed new methodology in February 1984, 49 Fed.Reg. 4230 (Feb. 3, 1984) which it adopted in June 1984. 49 Fed.Reg. 25,208 (June 19, 1984). FERC considered, 49 Fed.Reg. 24,146 (June 8, 1984), and approved the new methodology in October 1984, 49 Fed.Reg. 39,293 (Oct. 5, 1984), revising 18 C.F.R. § 301.1 (1984). FERC denied a petition for rehearing on the merits. 50 Fed.Reg. 4970 (Feb. 5, 1985). BPA has implemented the new average cost methodology.

The utilities allege that BPA’s consideration and approval of the new average cost methodology was a breach of its contractual obligations to the investor-owned utilities because the agency initiated the new consultation process less than one year after final FERC approval of the first average cost methodology. While the utilities’ complaint sought declaratory relief, the district court reached only the jurisdiction question. Pacific Power & Light Co. v. BPA, 589 F.Supp. 539, 543-44 (D.Or.1984).2 It concluded that “[although [the utilities] seek to characterize their ... claim as a pure contract issue unentangled with the merits or procedure of BPA’s ratemaking proceeding, my exercise of jurisdiction would necessarily impact the course of the [pending] rate case,” because the “issues are interwoven.” Id. at 545. The utilities claims presented a “rate matter in a more general sense,” subject to exclusive Ninth Circuit jurisdiction because the suit challenged the timing of BPA’s ratemaking proceeding. Id. In holding that it had no jurisdiction, the court noted that “Congress has already specified a procedure for review of plaintiffs’ claim” by the Ninth Circuit. The district court concluded that it would have jurisdiction only if there were an affirmative basis for jurisdiction which was not precluded by the Act. Id. at 543. Because it held that the Act precluded review by any court other than the Ninth Circuit, the court did not decide whether there was an affirmative basis for jurisdiction. Id. at 543-44. See also Public Power Council v. Johnson, 589 F.Supp. 198, 203-04 (D.Or.1984) (companion case also dismissed for lack of jurisdiction); Public [814]*814Utility Comm’r of Oregon v. BPA, 583 F.Supp. 752, 755-57 (D.Or.1984) (same).

The Act creates a scheme for judicial review with exclusive jurisdiction in either this court or the district court depending upon the nature of the agency-action being challenged. When a statute establishes a specific scheme for obtaining review, that scheme may be presumed to be exclusive. Central Lincoln Peoples’ Util. Dist. v. Johnson, 735 F.2d 1101, 1109 (9th Cir.1984) citing Nader v. Volpe, 466 F.2d 261, 266 (D.C.Cir.1972). See UMC Industries v. Seaborg, 439 F.2d 953, 955 (9th Cir.1971) (if Congress designates forum for judicial review of administrative action, that forum is exclusive even if statute does not specifically so indicate). Congress may freely choose the court in which judicial review may occur. City of Tacoma v. Taxpayers of Tacoma, 357 U.S. 320, 336, 78 S.Ct. 1209, 1218, 2 L.Ed.2d 1345 (1958).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
795 F.2d 810, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-power-light-co-v-bonneville-power-administration-ca9-1986.