Pacific Pools Construction Co. v. McClain's Concrete, Inc.

706 P.2d 849, 101 Nev. 557, 1985 Nev. LEXIS 454
CourtNevada Supreme Court
DecidedSeptember 30, 1985
Docket15191
StatusPublished
Cited by15 cases

This text of 706 P.2d 849 (Pacific Pools Construction Co. v. McClain's Concrete, Inc.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Pools Construction Co. v. McClain's Concrete, Inc., 706 P.2d 849, 101 Nev. 557, 1985 Nev. LEXIS 454 (Neb. 1985).

Opinion

*558 OPINION

Per Curiam:

This is an appeal from a summary judgment. We have determined that the grant of summary judgment was partially improper as a matter of law. Accordingly, we affirm in part, reverse in part, and remand with instructions.

The following facts are not disputed. Respondent McClain’s Concrete, Inc. (McClain) performed subcontracting work for appellant Pacific Pools Construction Company (Pacific) from 1977 to 1981. Pacific failed to compensate McClain for the work done between August and November, 1981. In March of 1982, McClain contacted the State Board of Contractors to obtain assistance in collecting the debt. With the help of the Board’s intervention, the parties reached a new agreement that provided that the debt would be paid in monthly installments of at least $500.00. Pacific made partial payment, but in August, 1982, the outstanding debt, according to McClain, was still in excess of $11,000.00. 1 Consequently, McClain commenced an action in district court to recover the unpaid balance. On June 29, 1983, the district court granted summary judgment against Pacific and awarded McClain $18,041.01 in damages. The three elements making up the damages award are as follows: (1) $7,334.81, the principal amount of the debt; (2) $3,888.31, interest at 18 percent per annum through August 16, 1982, the date of the filing of the complaint; and (3) $6,817.89, the amount of tax penalties imposed against McClain for its failure to pay its federal withholding taxes. 2 The district court also awarded McClain attorney’s fees and interest on the entire judgment at 12 percent per annum beginning on August 16, 1982, the date of the filing of the complaint. Pacific appealed.

*559 On appeal, Pacific admits that it owes McClain an outstanding debt of $7,334.81. Further, Pacific does not challenge the award of attorney’s fees or the interest charged against the judgment. Accordingly, these portions of the judgment will be affirmed. However, Pacific contends that the district court erred by awarding McClain interest on the principal debt amount at 18 percent per annum and by awarding McClain the amount of the tax penalties imposed by the Internal Revenue Service because of McClain’s failure to pay its withholding taxes. We agree.

Summary judgment is appropriate only where no genuine issue of fact remains for trial and one party is entitled to judgment as a matter of law. NRCP 56(c); see Zuni Constr. Co. v. Great Am. Ins. Co., 86 Nev. 364, 468 P.2d 980 (1970). Further, it is well established that a litigant has the right to a trial where the slightest doubt as to the facts exists. Nehls v. Leonard, 97 Nev. 325, 630 P.2d 258 (1981). In addition, in deciding whether summary judgment is appropriate, the evidence must be viewed in the light most favorable to the party against whom summary judgment is sought, and the factual allegations of that party must be presumed correct. See Oak Grove Inv. v. Bell & Gossett Co., 99 Nev. 616, 668 P.2d 1075 (1983). Finally, the burden of establishing the non-existence of any genuine issue of fact is on the party moving for summary judgment. Hoffmeister Cabinets of Nev. v. Bivins, 87 Nev. 282, 486 P.2d 57 (1971). With this standard in mind, we turn to Pacific’s contentions.

Pacific first contends that the district court could not find as a matter of law that McClain was entitled to 18 percent prejudgment interest on the outstanding debt. We note initially that the district court did not expressly award prejudgment interest at the rate of 18 percent per annum on the outstanding debt. Instead, $3,888.31 of the amount awarded as damages represents interest charged by McClain on its invoices at 1.5 percent per month from the time monies became due until August 16, 1982, the date of the filing of the complaint. The only interest award made by the district court was an award of interest at 12 percent per annum on the judgment from and after August 16, 1982. This award is not challenged by Pacific.

Pacific argues that it was improper for the damages award to include an amount which represents interest at 18 percent per annum because Pacific did not agree to an 18 percent interest charge. McClain asserts, on the other hand, that the 18 percent interest charge represents the “common custom and usage” in the construction industry, and that the district court, therefore, could find as a matter of law that McClain was entitled to 18 percent interest. NRS 99.040 provides: “When there is no express contract in writing fixing a different rate of interest, *560 interest must be allowed at the rate of 12 percent per annum. ...” (Emphasis added.) McClain admits that the written agreement of the parties does not include a provision for an 18 percent per annum interest charge. However, McClain argues that invoices sent to Pacific had included the 1.5 percent per month charge and that Pacific had acknowledged receipt of the invoices. Thus, McClain contends that these invoices evidence an agreement between the parties to the 18 percent interest charge. In his affidavit in opposition to the motion for summary judgment, however, Pacific’s president denied that Pacific had agreed to the 18 percent interest charge.

Although it may be argued, as Pacific does, that this difference of opinion is a sufficient material issue of fact to preclude the granting of summary judgment, we conclude as a matter of law that under the circumstances of this case McClain’s invoices are insufficient to satisfy the written contract requirement of NRS 99.040. Consequently, McClain is only entitled to 12 percent interest on the amounts owed from the time they became due regardless of the “custom and usage” in the industry. See NRS 99.040. Therefore, that portion of the judgment that represents prejudgment interest at the rate of 18 percent per annum must be reversed. However, because it is impossible on the record before us to determine the amount of interest due, we must remand the case to the district court for that determination.

Pacific next contends that McClain was not entitled as a matter of law to receive as damages the amount of tax penalties assessed against McClain for McClain’s failure to pay its withholding taxes. McClain asserts that because Pacific failed to pay its bills, McClain was left short of cash and could not meet its federal withholding tax obligations. As a result, penalties were imposed on McClain by the IRS.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Garcia-Lopez v. Affordable Plumbing/Vinings Insurance Co.
66 So. 3d 1024 (District Court of Appeal of Florida, 2011)
Wood v. Safeway, Inc.
121 P.3d 1026 (Nevada Supreme Court, 2005)
Nga 2 Limited Liability Co. v. Rains
946 P.2d 163 (Nevada Supreme Court, 1997)
Basile v. Union Plaza Hotel & Casino
887 P.2d 273 (Nevada Supreme Court, 1994)
Mallin v. Farmers Insurance Exchange
839 P.2d 105 (Nevada Supreme Court, 1992)
Burnett v. C.B.A. Security Service, Inc.
820 P.2d 750 (Nevada Supreme Court, 1991)
Ferreira v. P.C.H. Inc.
774 P.2d 1041 (Nevada Supreme Court, 1989)
Charles v. J. Steven Lemons & Associates
760 P.2d 118 (Nevada Supreme Court, 1988)
Hampton v. Brewer
733 P.2d 852 (Nevada Supreme Court, 1987)
Parker v. Mineral County
729 P.2d 491 (Nevada Supreme Court, 1986)
Renaud v. 200 Convention Center Ltd.
728 P.2d 445 (Nevada Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
706 P.2d 849, 101 Nev. 557, 1985 Nev. LEXIS 454, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-pools-construction-co-v-mcclains-concrete-inc-nev-1985.