Pacific Hardware Co. v. Lincoln

12 Haw. 358, 1900 Haw. LEXIS 39
CourtHawaii Supreme Court
DecidedMay 4, 1900
StatusPublished
Cited by1 cases

This text of 12 Haw. 358 (Pacific Hardware Co. v. Lincoln) is published on Counsel Stack Legal Research, covering Hawaii Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Hardware Co. v. Lincoln, 12 Haw. 358, 1900 Haw. LEXIS 39 (haw 1900).

Opinion

OPINION OF THE COURT BY

FREAR, J.

This is an action for $101 against defendant Lincoln, a contractor, personally and to enforce a materialman’s lien for this amount against a dwelling house and cottage owned by defendant Cooper. The jury found against Lincoln for the amount claimed and for the enforcement of the lien for $99.44,- — -a portion of the materials furnished,- valued at $1.56, having been shown not to have gone into the building. The case comes here on exceptions taken by defendant Cooper.

The exception chiefly relied on was taken to the refusal of the trial judge to allow defendant Cooper to show that the contract for the dwelling house was abandoned by the contractor and the building taken over by the defendant on the 26th of May and [359]*359that the latter thereafter completed the building himself by day labor. The object stated at the time was to show that the notice of the lien was' not filed within ninety days after the completion of the building.

The statute provides (Civ. L. Sec. 1742) that, “The lien shall continue for three months, and no longer, after the completion of the construction * * * of the building * * * unless the same shall have been satisfied, or proceedings commenced to collect the amount due thereon by enforcing the same” and (Sec. 1744) that, “The lien herein provided shall have force only from the date of filing.” The contract was abandoned May 26, the notice of lien filed August 26, and the action commenced August 30. It is evident that the lien, to be effective, must have been filed not later than three months after the completion of the building, but it was so filed even if the building must be deemed to have been completed, within the meaning of the statute, as defendant contends1, on May 26. Defendant seems to have assumed that the time limited by the statute was ninety days, in which case, of course, the lien would not have been filed in time, if the building was completed on May 26. But since the statute prescribes three months, and not ninety days, as the limit, the lien was filed in time. Bowler v. McIntyre, 9 Haw. 306. In re Martin, 4 Fed. Rep. 208. But since the lien was filed the last day allowed by the statute, if the building was completed on May 26, it would not continue in force thereafter unless the action were brought on the same day. It was not brought until four days later. Let us therefore consider whether the building was completed, within the meaning of the statute, on May 26, although, strictly speaking, this question is not before us.'

It is often a nice question to determine when a building is completed within the meaning of a statute of this kind. No hard and fast rule can be laid down. The practice in other jurisdictions has been to decide each case by itself fairly and equitably under its own peculiar circumstances: It is held that after a building is substantially completed the contractor cannot [360]*360extend the time or keep alive his lien by performing further work of his own accord and merely for that purpose, but if such, further work is performed at the request of the owner, even though it is small in amount and is performed after a considerable interval of time, the building is regarded as completed, for the purposes of the lien, when such additional work is performed. But even then the completion is not deemed to have been postponed by the performance of such additional work as against rights acquired meanwhile by third parties on the supposition that the building had been completed previously and that the time limited by the statute had expired. Woodruff v. Hovey, 91 Me. 116, 424; Nichols v. Culver, 51 Conn. 177; Cole v. Uhl, 46 Conn. 296; Minn. Tr. Co. v. Great N. Ry. Co. 76 N. W. (Minn.) 953. If the work is suspended through the fault of the contractor, he might forfeit his right to a lien altogether, but if the contractor abandons the work in consequence of the owner’s fault, the building may be regarded as completed then. Catlin v. Douglass, 33 Fed. R. 569; Canal Co. v. Gordon, 6 Wall. 561; Knight v. Norris, 13 Minn. 473. If a change is made in the plans, the date of completion, as to labor performed or materials furnished before the change, may be the date of the completion or cessation of the work under the old plans or the date of the completion under the new plans according to whether there is substantially a new or different plan or work or merely a modification of the old. Diller v. Barger, 68 Pa. St. 432. In Catlin v. Douglass, supra, the court said: “It is apparent that parties intending to assert liens rather than rely upon the personal credit of the debtor, must be vigilant to ascertain when the work is completed or abandoned, and not be too early or too late in filing their statements. It is also apparent that there may arise perplexing questions as to when a work is completed, or abandoned, and, in determining such questions, the court should not take a technical and narrow view, but should save to parties entitled to liens any rights they may justly have, under a fair and equitable construction of the facts and the law applicable thereto.”

[361]*361In the present case, as we understand, the owner took the work from the contractor on the ground that the latter was not faithfully carrying out the terms of his contract, and then completed the building himself on substantially the original plans by employing the same contractor and paying for the labor by the day. The contention seems to be that this change of itself fixed the date of the completion of the building at that time, as to materials furnished prior thereto. Under the circumstances the materialmen would naturally suppose, in the absence of any notice to the contrary, that the work was being continued under the original contract. Whether they had such notice we do not know and need not consider. The statute provides that the lien shall continue three months from the “completion of the construction of the building,” not from the completion or abandonment of the contract. In McIntyre v. Trautner, 63 Cal. 429, the statute allowed the original contractor sixty days from the completion of the contract and the subcontractor thirty days from the completion of the building. The completion of the contract is not synonymous with the completion of the building. The subcontractor or materialman under our statute is not merely subrogated to the rights of the original contractor. Allen & Robinson v. Redward, supra. An abandonment of the contract by the contractor without just cause might work a forfeiture of his own right to a lien without working a forfeiture of the materialman’s right. Although, if the work had been suspended at the time of the abandonment of the contract and had not afterwards been continued or completed, the material-man might have regarded the building as then completed for the purposes of the lien, yet it was not obliged to do so under the circumstances of this case. The owner having gone on and completed the building, .the materialman could under the statute wait until it was completed and then have three months in which to file notice of the lien and bring suit. If the entire building had been constructed by day labor, the materialman would not be obliged to file his notice and bring suit for the value of each article within three months after it was fur[362]*362nished.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Honolulu Roofing Co. v. Felix
426 P.2d 298 (Hawaii Supreme Court, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
12 Haw. 358, 1900 Haw. LEXIS 39, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-hardware-co-v-lincoln-haw-1900.