Pacific Gas Transmission Co. v. F.E.R.C.

CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 23, 1993
Docket92-5014
StatusPublished

This text of Pacific Gas Transmission Co. v. F.E.R.C. (Pacific Gas Transmission Co. v. F.E.R.C.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Gas Transmission Co. v. F.E.R.C., (5th Cir. 1993).

Opinion

United States Court of Appeals,

Fifth Circuit.

Nos. 92-5013, 92-5014.

PACIFIC GAS TRANSMISSION CO., Petitioner,

v.

FEDERAL ENERGY REGULATORY COMMISSION, Respondent.

Aug. 26, 1993.

Petitions for Review of an Order of the Federal Energy Regulatory Commission.

Before REYNALDO G. GARZA, SMITH, and BARKSDALE, Circuit Judges.

JERRY E. SMITH, Circuit Judge:

Pacific Gas Transmission Company ("PGT") petitions for review of t he Federal Energy

Regulatory Commission's (the "Commission's" or "FERC's") orders amending Kern River Gas

Transmission Company's ("Kern River's") and Mojave Pipeline Company's ("Mojave's") optional

certificates of public convenience and necessity and denying PGT's application for rehearing. Because

we find that the Commission's actions were neither arbitrary nor capricious and that the Commission

did not abuse its discretion in amending the certificates and denying PGT's motion for rehearing, we

affirm.

I.

On January 24, 1990, Kern River and Mojave received authorizations under the Commission's

optional certificate procedure jointly and individually to construct, own, and operate new pipeline

facilities in order to transport natural gas into south-central California.1 The certificated cost of Kern

1 In order to obtain authorization for a new pipeline venture from the Commission, a natural gas company first must obtain a certificate of public convenience and necessity from the Commission pursuant to § 7(c) of the Natural Gas Act ("NGA"), which provides in pertinent part as follows:

No natural gas company ... shall engage in the transportation or sale of natural gas, ... or undertake the construction or extension of any facilities therefor, or acquire or operate any such facilities or extensions thereof, unless there is in force with respect to such natural gas company a certificate of public convenience and necessity issued by the Commission authorizing such acts or operations.... River's facilities was $631,329,000, and the certificated cost of Mojave's facilities was $109,332,000.

The certificated cost of the common facilities was $204,010,000. Kern River's share of this cost was

$129,825,000, and Mojave's share was $74,185,000. The companies based these figures upon 1989

estimates of total costs.

Based upon these cost figures, the Commission approved maximum reservation fees for both

Kern River and Mojave, which the Commission set forth in its certificate order. 50 FERC ¶ 61,069,

1990 WL 488664 reh'g denied, 51 FERC ¶ 61,195, 1990 WL 488742 (1990).2 For the first

15 U.S.C. § 717f(c)(1)(A) (1993).

A company may elect to obtain one of two types of certificates. First, it may obtain a conventional or standard § 7 certificate. The Commission requires companies that wish to obtain a standard certificate to meet rigorous requirements, and the application process is slow and costly. An applicant must demonstrate that it has contracts and supporting market data equivalent to the total capacity of its proposed facilities and must present evidence of adequate gas supply. See NGA section 7(e), 15 U.S.C. § 717f(e) (1993) (certificate will be granted only if proposed service, sale, operation, construction, extension, or acquisition, to extent authorized by the certificate, is or will be required by present or future public convenience and necessity; otherwise, application will be denied).

Alternatively, a company may obtain an optional certificate pursuant to Part 157, Subpart E of the Commission's regulations, 18 C.F.R. §§ 157.100-.106 (1992). Under optional certificate procedures, the Commission does not require applicants to demonstrate that markets or gas supplies for their new projects exist. See 18 C.F.R. § 157.102(b)(1)(iii) (1992) (exhibits detailing total gas supply, market data and tariff rates not required in optional certificate proceedings); 18 C.F.R. § 157.104(c) (1992) (if application for optional certificate complies fully with outlined requirements, the Commission will presume that proposed new service is or will be required by present or future public convenience and necessity).

In exchange for the streamlined procedures and less burdensome requirements for optional certificates, applicants must specifically agree to assume the economic risks of the project. See 18 C.F.R. § 157.103(d)(8) (1992) (describing prohibitions against cost shifting). The Commission reasons that as long as the applicant bears the risk of a new pipeline project, the Commission may infer that the applicant will build its facilities on an efficient scale and that the project will advance the public interest. The applicant's agreement is embodied in the specific terms and conditions under which the optional certificate is offered. 2 A reservation fee applies regardless of the quantity of gas shipped to the customer, whereas a usage fee applies to each unit of gas shipped. The reservation fee therefore guarantees that the pipeline company will recover some of its costs regardless of the customer's actual use of the pipeline or the volume of gas taken. In issuing optional certificates, the Commission caps the amount of costs that a pipeline company may recover through its reservation fee but permits the company to recover the remainder of its costs through a usage fee. See 18 C.F.R. § 157.103(d)(3) (1992) (describing volumetric rates) and (d)(7) (discussing rate flexibility). fifteen-year period of service, the Commission approved a maximum monthly reservation fee of

$12.75 per Mcf for Kern River and a maximum daily reservation fee of .2022 cents per MMbtu for

Mojave. The Commission also established minimum reservation fees of zero for both companies.

The Commission authorized the companies to negotiate reservation fees with their customers within

these parameters.

Subsequently, the companies negotiated rates that complied with the terms set forth in the

Commission's certificate order, and the Commission approved the rates as incorporated into the

companies' contracts. Kern River Gas Transmission Co., 53 FERC ¶ 61,172 (1990); Mojave

Pipeline Co., 56 FERC ¶ 61,282, reh'g granted, 57 FERC ¶ 61,300 (1991). The Commission's

certificate order also provided as follows:

... [T]he Commission is requiring Kern River [and Mojave] to make ... [section 4] tariff filing[s], three years after [their] in-service date[s], either justifying [their] existing rates or proposing alternative rates to be effective no later than three years after the in-service date. This requirement will enable the Commission to examine Kern River's [and Mojave's] actual operating costs, and to make a determination at that time as to whether ... rates are in the public interest. The filing[s] must use the same or greater throughput levels on which Kern River's [and Mojave's] initial rates have been predicat ed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atlantic Refining Co. v. Public Service Commission
360 U.S. 378 (Supreme Court, 1959)
Udall v. Tallman
380 U.S. 1 (Supreme Court, 1965)
Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Pacific Gas Transmission Co. v. F.E.R.C., Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-gas-transmission-co-v-ferc-ca5-1993.