Pacific Gas & Electric Co. v. Damé Construction Co.

191 Cal. App. 3d 233, 236 Cal. Rptr. 351, 1987 Cal. App. LEXIS 1598
CourtCalifornia Court of Appeal
DecidedApril 22, 1987
DocketA031745
StatusPublished
Cited by12 cases

This text of 191 Cal. App. 3d 233 (Pacific Gas & Electric Co. v. Damé Construction Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Gas & Electric Co. v. Damé Construction Co., 191 Cal. App. 3d 233, 236 Cal. Rptr. 351, 1987 Cal. App. LEXIS 1598 (Cal. Ct. App. 1987).

Opinion

Opinion

KLINE, P. J.

This appeal arises from a dispute between Pacific Gas and Electric Company (PG&E) and Damé Construction Company, Inc. (Damé) *235 over liability for costs incurred in the relocation of certain electrical power poles. The trial court found Damé responsible for these costs and ordered it to pay PG&E $19,542. We shall affirm the judgment.

Statement of Facts

Damé, a private land development company, owned 417 acres immediately west of and adjacent to San Ramon Valley Boulevard in Contra Costa County. Damé sought approval of a plan to subdivide its land and construct 715 homes. The Contra Costa Board of Supervisors granted its approval upon numerous conditions, one of which required Damé to widen that portion of San Ramon Valley Boulevard immediately adjacent to the site of the proposed development. PG&E owns and maintains an electric distribution line on that road. In the stipulation of facts submitted below the parties agreed that neither the board of supervisors nor any other local government agency specifically required Damé to relocate the PG&E power poles and lines.

When PG&E became aware of Damé’s development plans it notified Damé that it would move the affected electrical poles, provided that “such change [would] be made only at the expense of the person making such request.”

On July 8, 1980, the Contra Costa County Public Works Department sent a letter to PG&E requesting PG&E to “make arrangements” to relocate its power poles in accordance with the attached plans. Thereafter, on five separate occasions, PG&E sought an acknowledgement from Damé that it would reimburse PG&E for its relocation expenses. Damé refused to accept liability.

During the latter part of 1982 Damé completed the road widening, which left poles and electrical lines in the middle of the newly paved street. On or about October 1982, PG&E moved its poles at a cost of $19,542. As a result of Damé’s continued refusal to pay for this work PG&E commenced this action on January 26, 1983.

Statement of the Case

After answering PG&E’s complaint, Damé moved for summary judgment, arguing it was protected by a rule holding utilities responsible for the cost of relocating equipment due to the proper governmental use of the land on which the equipment is located. The court denied the motion.

*236 The matter was submitted for decision based on the parties’ stipulated facts, the evidence submitted in support of and in opposition to the summary judgment motion and additional declarations submitted by Damé.

The court issued written findings on the specified “ ‘controverted issues.’ ” In particular, it noted that while the general public might receive some incidental benefit from the improvements on San Ramon Valley Boulevard, the “principal beneficiary” of this work was Damé, which was permitted to develop its property only after agreeing to widen the road. The court concluded that utility relocation costs incidental to a private land improvement project should be borne by the private developer which benefited from that project. Accordingly, it entered judgment for PG&E and against Damé. Damé filed a motion for new trial, which was denied.

Discussion

Damé’s entire argument is based on the common law rule that a franchised utility must bear its own costs of relocation when requested to move its equipment by an authorized governmental agency. Damé maintains that in the absence of express statutory authority—which PG&E admits is lacking here—a utility cannot shift this obligation to others, even where a private developer undertakes the improvements that make the equipment relocation necessary. This apparently is a question never before directly addressed by the appellate courts of this state.

It is true that at common law and, in California, by statute (Pub. Util. Code, § 6297) utilities must bear the costs of relocating equipment moved at the request of a municipality. However, by its own terms, that rule does not apply to a dispute between a utility and a private developer. Moreover, if the policy behind that rule in any way applies to this situation, it militates in favor of allocating the cost of relocation to Damé.

According to the common law rule, “in the absence of a provision to the contrary, a public utility’s franchise rights in a public street are subject to an implied obligation to relocate its facilities at the utility’s own expense when necessary to make way for a proper governmental use of the street. [Citations.]” (Pacific Tel. & Tel. Co. v. Redevelopment Agency of Redlands (1977) 75 Cal.App.3d 957, 962 [142 Cal.Rptr. 584]; accord, Pacific Tel. & Tel. Co. v. Redevelopment Agency of Glendale (1978) 87 Cal.App.3d 296, 299 [151 Cal.Rptr. 68]; see also 12 McQuillin, Law of Municipal Corporations (3d ed. rev. 1986) § 34.74a [utilities must pay for relocation when changes “are required by public necessity”].) This rule has been codified in Public Utilities Code section 6297: “The grantee [of a utility franchise] shall *237 remove or relocate without expense to the municipality any facilities installed, used, and maintained under the franchise if and when made necessary by any lawful change of grade, alignment, or width of any public street, way, alley, or place, including the construction of any subway or viaduct, by the municipality.” (Italics added.)

It is apparent from the cited authorities that the utility’s obligation arises only when relocation is made necessary by a valid governmental act. This rule has been explained by the fact that “at the time of framing the franchise [agreement] there existed the possibility that an exercise of the police power could force relocation. This fact contributes to a contract construction whereby an implied term in the franchise is raised that the utility will bear the costs.” (Note, Municipal Corporations: Extraterritorial Power: Determination of Who Should Bear the Expense of Relocation of Private Utility Lines (1959) 6 UCLA L.Rev. 336, 337, fn. omitted.) The rule and the noted justification are of dubious relevance to situations in which the relocation is made necessary by private development not initiated by any governmental agency.

As section 6297 makes clear, the purpose of the rule is to insulate the government and, consequently, taxpayers, from such expenses: the statutory language explicitly provides that relocation be accomplished “without expense to the municipality.” Courts have emphasized that this rule cannot easily be avoided by judicial construction because “[i]t is for the Legislature to decide whether [relocation] expenses should be shifted to the taxpayers.” (Pacific Tel. & Tel. Co., supra, 75 Cal.App.3d at p. 968, italics added.) In the instant case analogous reasoning favors the imposition on Damé of liability for the costs to protect PG&E’s ratepayers, who are comparable to taxpayers, from having to bear the burden.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mahgerefteh v. Verizon California CA4/3
California Court of Appeal, 2015
Whisenhunt v. Southwestern Bell Telephone
573 F.3d 565 (Eighth Circuit, 2009)
Whisenhunt v. Southwestern Telephone L.P.
582 F. Supp. 2d 1103 (E.D. Arkansas, 2008)
Potomac Electric Power Co. v. Classic Community Corp.
856 A.2d 660 (Court of Appeals of Maryland, 2004)
Opinion No.
Arkansas Attorney General Reports, 1999
Sundquist Homes, Inc. v. Snohomish County Public Utility District No. 1
965 P.2d 1148 (Court of Appeals of Washington, 1998)
City of Livermore v. Pacific Gas & Electric Co.
51 Cal. App. 4th 1410 (California Court of Appeal, 1997)
Home Builders Ass'n of Greater St. Louis v. St. Louis County Water Co.
784 S.W.2d 287 (Missouri Court of Appeals, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
191 Cal. App. 3d 233, 236 Cal. Rptr. 351, 1987 Cal. App. LEXIS 1598, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-gas-electric-co-v-dame-construction-co-calctapp-1987.