Pacific Gas and Electric Company v. Howard P. Foley Company, Inc.

79 F.3d 1154, 1996 U.S. App. LEXIS 17255
Court of Appeals for the Ninth Circuit·Decided March 6, 1996·No. 94-16162·Unpublished

Opinion

79 F.3d 1154

1996-1 Trade Cases P 71,340, RICO Bus.Disp.Guide 9004

NOTICE: Ninth Circuit Rule 36-3 provides that dispositions other than opinions or orders designated for publication are not precedential and should not be cited except when relevant under the doctrines of law of the case, res judicata, or collateral estoppel.
PACIFIC GAS AND ELECTRIC COMPANY, Plaintiff-Appellant,
v.
HOWARD P. FOLEY COMPANY, INC., et al., Defendants-Appellees.

No. 94-16162.

United States Court of Appeals, Ninth Circuit.

Argued and Submitted Dec. 5, 1995.
Decided March 6, 1996.

Before: GOODWIN and REINHARDT, Circuit Judges, and KING,* District Judge.

MEMORANDUM**

Plaintiff, Pacific Gas & Electric Company ("PG & E" or "Plaintiff" or "Appellant"), sought treble damages for the period 1972-1977 during which it paid Defendant Howard P. Foley Company, Inc. ("Foley") contracting company cost-plus 15%, a rate which PG & E alleges was possible only as a result of bid-rigging in violation of either the Sherman Act or RICO or both. PG & E alleges that a competitive fee during that time period would have been between cost-plus 4% and cost-plus 8%. PG & E calculates the excess fees as between $3.5 million and $4.6 million. PG & E also sought to recover as damages, to be trebled, the cost of financing these excess charges and calculates these financing costs as between $17.5 million and $22.4 million.

After a long jury trial in which the jury was unable to agree on a verdict, the court declared a mistrial. The court then considered Fischbach & Moore's motions for judgment as a matter of law, pursuant to Rule 50(a) at the close of PG & E's case and pursuant to Rule 50(b) after the parties had rested, and granted both motions. PG & E argues that a new trial should have been ordered.1

I.

The excess charges alleged by PG & E were incurred in the course of the construction for PG & E of a two-unit nuclear power plant called Diablo Canyon. The plant was built over a period of more than 17 years from the issuance of initial regulatory approvals on November 7, 1967, using independent contractors in many trade disciplines under PG & E's direct supervision.

The final cost of constructing Diablo Canyon, including financing costs, was approximately $5.6 billion. The largest single contractor at the plant was the Howard P. Foley Co., Inc., which performed most of the required electrical work. PG & E paid Foley at least $425 million for its work at Diablo Canyon.

PG & E let three contracts for electrical work at Diablo Canyon, designated as Contract 8807, Contract 8802, and Contract 8808, which are relevant to this case. Any electrical contractor interested in bidding for work at Diablo Canyon had to qualify itself as competent.

In March 1969, PG & E invited a number of electrical contractors, including Fischbach, to qualify. Subsequently, PG & E invited the qualified bidders to submit competitive bids for Contract 8807 in three distinct parts--a "lump sum" or "fixed" price, a "cost-plus" price, and several "unit" prices. Fischbach, Foley, and others submitted bids which were evaluated by PG & E. In February 1970, PG & E awarded Contract 8807 to the low bidder, Foley, an original defendant in the suit filed by PG & E.

Some time later, PG & E issued plans and specifications for Contract 8808 and received seven bids, in the same tripartite format as for Contract 8807, including one from Fischbach. In July 1971, Contract 8808 was awarded to Wismer & Becker Contracting Engineers, Inc. ("Wismer & Becker"), another original defendant in the suit filed by PG & E.

On July 29, 1971, shortly after awarding Contract 8808, PG & E invited Foley, Wismer & Becker, and L.K. Comstock & Company, Inc. ("Comstock") to submit bids for Contract 8802. Wismer & Becker did not bid. The contract was awarded to Foley as the lower bidder.

Once Foley was on-site performing Contracts 8807 and 8802, PG & E decided to consolidate those contracts into one. Effective September 1, 1972, the remaining work under Contract 8807 was "rolled into" Contract 8802 and under the price terms of Contract 8802.

On December 17, 1973, PG & E and Foley agreed to modify the price terms of Contract 8802. The parties agreed that work performed at Diablo Canyon by Foley retroactively from February 24, 1972 and thereafter would be paid for on a cost-plus 15% fee basis instead of the cost-plus 25% fee in Foley's bid. This fee change was effective through the end of 1976 and into early 1977.

In February 1977, as construction of Diablo Canyon was thought to be nearing completion, PG & E invited Foley and several non-electrical contractors to bid for finishing up all remaining work on a variety of construction tasks which PG & E referred to generally as "clean-up" work. Foley submitted a low bid and also promised in its bid that, if chosen, it would change its cost-plus 15% fee for Contract 8802 work to a sliding fee starting at 7.5% and moving down to 5%. PG & E awarded the clean-up work to Foley and modified the price terms of Contract 8802 to reflect Foley's proposal. Accordingly, all of the electrical work performed by Foley at Diablo Canyon for the next eight years (1977-1985), amounting to hundreds of millions of dollars, was performed at an average price of about cost-plus 5%.

As set forth earlier, PG & E seeks damages only for the five-year period 1972-1977 during which Foley charged PG & E cost-plus 15%, a rate which PG & E alleges would have been between cost-plus 4% and cost-plus 8% if the bidding had not been rigged in violation of the Sherman Act or RICO or both. Although not set forth more specifically in any of the pleadings or briefs, this period would presumably be from February 24, 1972, to the date in 1977 when the 15% fee under Contract 8802 was modified to a sliding scale.

II.

A district court's decision to grant judgment as a matter of law pursuant to Federal Rule of Civil Procedure 50 is reviewed de novo. Montiel v. City of Los Angeles, 2 F.3d 335, 342 (9th Cir.1993). The standard for reviewing the district court's grant of a directed verdict is de novo. Berry v. Bunnell, 39 F.3d 1056, 1057 (9th Cir.1994); Zamalloa v. Hart, 31 F.3d 911, 913 (9th Cir.1994).

A directed verdict (or judgment as a matter of law) is proper when the evidence permits only one reasonable conclusion. Berry, 39 F.3d at 1057. The motion should be granted only if the facts and inferences point so strongly in favor of the moving party that reasonable persons could not arrive at a contrary verdict, i.e., that the jury acted unreasonably in coming to its verdict. Jeanery, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Pacific Gas and Electric Company v. Howard P. Foley Company, Inc., 79 F.3d 1154, 1996 U.S. App. LEXIS 17255 (9th Cir. 1996).

79 F.3d 1154 (Pacific Gas and Electric Company v. Howard P. Foley Company, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Trenton Potteries Co.
273 U.S. 392 (Supreme Court, 1927)
United States v. Turkette
452 U.S. 576 (Supreme Court, 1981)
H. J. Inc. v. Northwestern Bell Telephone Co.
492 U.S. 229 (Supreme Court, 1989)
Waymon M. Berry v. William J. Bunnell
39 F.3d 1056 (Ninth Circuit, 1994)
Montiel v. City of Los Angeles
2 F.3d 335 (Ninth Circuit, 1993)
Zamalloa v. Hart
31 F.3d 911 (Ninth Circuit, 1994)
Ikuno v. Yip
912 F.2d 306 (Ninth Circuit, 1990)
River City Markets, Inc. v. Fleming Foods West, Inc.
960 F.2d 1458 (Ninth Circuit, 1992)
Monsanto Co. v. Spray-Rite Service Corp.
465 U.S. 752 (Supreme Court, 1984)