Pacific Gas and Electric Co. v. Hart High-Voltage etc.

CourtCalifornia Court of Appeal
DecidedDecember 12, 2017
DocketF072904
StatusPublished

This text of Pacific Gas and Electric Co. v. Hart High-Voltage etc. (Pacific Gas and Electric Co. v. Hart High-Voltage etc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Gas and Electric Co. v. Hart High-Voltage etc., (Cal. Ct. App. 2017).

Opinion

Filed 12/12/17

CERTIFIED FOR PARTIAL PUBLICATION*

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIFTH APPELLATE DISTRICT

PACIFIC GAS AND ELECTRIC COMPANY, F072904 Plaintiff and Appellant, (Super. Ct. Nos. CV003013, v. CVM013599)

HART HIGH-VOLTAGE APPARATUS REPAIR AND TESTING CO., INC., OPINION Defendant and Respondent.

APPEAL from a judgment of the Superior Court of Merced County. Donald J. Proietti, Judge. Urrabazo Law, Donald Urrabazo, Arturo Padilla and Joon Song for Plaintiff and Appellant. Michel & Fackler, Michael D. Michel, Kate Morrow and Jeff M. Fackler for Defendant and for Respondent. -ooOoo-

* Pursuant to California Rules of Court, rules 8.1105(b) and 8.1110, this opinion is certified for publication with the exception of part I.C. and part II. of the Discussion. Plaintiff Pacific Gas and Electric Company (PG&E) sued defendant HART High- Voltage Apparatus Repair and Testing Co., Inc. (HART) for negligently servicing a large transformer at a hydroelectric power plant and for damages under Public Utilities Code1 section 7952. PG&E alleged it incurred dirct and indirect costs of approximately $8.1 million. HART filed a motion for summary adjudication that challenged all of PG&E’s causes of action.2 The trial court determined the evidence showed MID owned the power plant and the transformer allegedly damaged by HART. The court concluded that because PG&E did not own the transformer, PG&E could not prove essential elements of its causes of action for negligence and damages under section 7952. In the unpublished parts of this opinion addressing PG&E’s negligence cause of action, we conclude (1) PG&E has standing to sue if it is a “real party in interest” pursuant to Code of Civil Procedure section 367 and (2) the evidence presented shows PG&E held sufficient interests in the transformer and the electricity it delivered to qualify as a real party in interest. Using the “bundle of sticks” metaphor in which each stick represents a legally recognized property interest, we conclude PG&E held sufficient sticks to qualify as a real party in interest. Therefore, PG&E may pursue its negligence cause of action against HART.

1 All unlabeled statutory references are to the Public Utilities Code. 2 The same motion for summary adjudication was before this court in Merced Irrigation District v. Superior Court (2017) 7 Cal.App.5th 916, where we concluded another plaintiff, Merced Irrigation District (MID), was not a “municipal corporation” for purposes of section 10251 and, therefore, not entitled to recover damages under section 10251. Based on that statutory interpretation, we upheld the grant of summary adjudication eliminating MID’s cause of action under section 10251.

2. In the published parts of this opinion addressing PG&E’s claim for damages under section 7952,3 we reach the following conclusions. First, the transformer was “necessary or useful … equipment” as that phrase is used in section 7952. Second, PG&E is an “electrical corporation” for purposes of section 7952. Third, the preposition “of” in the phrase “equipment of any … electrical … corporation” is used in the proprietary sense— that is, it refers to the corporation’s ownership of property interests in the equipment. Fourth, the ownership of property interests in the equipment need not be complete ownership because the phrase “equipment of any … electrical … corporation” also encompasses equipment in which the corporation is a partial owner—that is, holds some of the sticks in the bundle that represent the property interests in the equipment. Fifth, the evidence presented shows PG&E holds multiple property interests in the transformer and, thus, PG&E might be regarded as a partial owner of the transformer entitled to recover the measure of damages set forth in section 7952. Therefore, HART has not carried its burden of demonstrating PG&E’s cause of action for damages under section 7952 lacks merit. We therefore reverse the judgment and remand for further proceedings. FACTS PG&E, a California corporation, is a public utility regulated by the California Public Utilities Commission, and its stock is publicly traded under the symbol “PCG.” PG&E provides gas and electrical service to about 15 million end users in northern and central California.4 The other plaintiff in this lawsuit, MID, is an irrigation district

3 The first sentence of section 7952 states: “Any person who injures or destroys, through want of proper care, any necessary or useful facility or equipment of any … electrical … corporation, is liable to the corporation for all damages sustained thereby.” (Italics added.) The second sentence specifies a broad measure of damages, which includes indirect or overhead expenses. Thus, the damages recoverable under section 7952 might be much broader than those recoverable under the negligence cause of action. 4 Panoche Energy Center, LLC v. Pacific Gas & Electric Co. (2016) 1 Cal.App.5th 68, 72.

3. organized under the laws of the State of California with its principal place of business in Merced County. PG&E and MID alleged they were “the owners and operators of a transformer located at the Exchequer Dam on the Merced River” in Merced County. The transformer was an Allis-Chalmers 100 MVA Auto Transformer and was part of the power plant at the Exchequer reservoir. The transformer was large, measuring almost nine feet wide, 23 feet long, and 12 feet high. When operational, the transformer contained approximately 6,800 gallons of oil and weighed 243,000 pounds. The transformer had been custom built to take the 13.8 kilovolt electricity generated at the Exchequer dam and transform it into voltages (i.e., 70 kilovolt and 115 kilovolt) that were fed into two separate transmission systems owned by PG&E. The relationship between PG&E and MID as it pertains to the power plant and equipment located at the Exchequer reservoir is defined by their June 25, 1964, power purchase contract. The power purchase contract stated MID “shall construct at its own risk and expense, and shall be the sole owner (under Federal Power Commission License) of, the project” and set forth the requirements and specifications for its design and construction.5 The specifications addressed the project’s turbines, generators, and the transformer that is the subject of this litigation. PG&E contends the power purchase contract (1) entitled it to all electricity generated by the project; (2) made it responsible for all costs associated with maintaining and operating the Exchequer power plant; and (3) granted it the right to enter upon,

5 The contract defined the term “project” as “[a] development using the waters of Merced River and including Exchequer Reservoir, McSwain Reservoir, Exchequer Power Plant, McSwain Power Plant, dams, project communication facilities, project headquarters and project roads, tools, operation and maintenance equipment, including motor vehicles, and all necessary appurtenances for each of the foregoing.” The term “Exchequer Power Plant” was defined as “[a] hydroelectric generating facility to be constructed on Merced River at the reconstructed Exchequer Dam, including an intake structure, a penstock, a power house, and appurtenant facilities.”

4. operate and maintain any part of the power plant in the event that MID failed to operate and maintain the project in accordance with the power purchase contract. In July 2009, HART submitted a quote to MID for servicing the transformer. The work involved draining the transformer of insulating fluid, performing an internal inspection, removing and replacing five electro coolers, replacing a variety of gaskets, replacing other parts, refilling the transformer and performing tests. HART estimated the total price for this work at $122,415.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dixon v. TSE International Inc.
330 F.3d 396 (Fifth Circuit, 2003)
Poe v. Seaborn
282 U.S. 101 (Supreme Court, 1930)
Dickman v. Commissioner
465 U.S. 330 (Supreme Court, 1984)
Honchariw v. County of Stanislaus
218 Cal. App. 4th 1019 (California Court of Appeal, 2013)
Flores v. Arroyo
364 P.2d 263 (California Supreme Court, 1961)
Lungren v. Deukmejian
755 P.2d 299 (California Supreme Court, 1988)
Biakanja v. Irving
320 P.2d 16 (California Supreme Court, 1958)
Miller v. Dyer
127 P.2d 901 (California Supreme Court, 1942)
Wolfsen v. Hathaway
198 P.2d 1 (California Supreme Court, 1948)
People v. Hallner
277 P.2d 393 (California Supreme Court, 1954)
Horwich v. Superior Court
980 P.2d 927 (California Supreme Court, 1999)
Orange Grove Terrace Owners Ass'n v. Bryant Properties, Inc.
176 Cal. App. 3d 1217 (California Court of Appeal, 1986)
Pacific Gas & Electric Co. v. Alexander
90 Cal. App. 3d 253 (California Court of Appeal, 1979)
Pacific Gas & Electric Co. v. Mounteer
66 Cal. App. 3d 809 (California Court of Appeal, 1977)
Friendly Village Community Ass'n v. Silva & Hill Construction Co.
31 Cal. App. 3d 220 (California Court of Appeal, 1973)
Parkmerced Co. v. City and Cty. of San Francisco
149 Cal. App. 3d 1091 (California Court of Appeal, 1983)
Vaughn v. Dame Construction Co.
223 Cal. App. 3d 144 (California Court of Appeal, 1990)
Martin v. Bridgeport Community Assn., Inc.
173 Cal. App. 4th 1024 (California Court of Appeal, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
Pacific Gas and Electric Co. v. Hart High-Voltage etc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-gas-and-electric-co-v-hart-high-voltage-etc-calctapp-2017.