Pacific Coast Engineering Co. v. Trinity Construction Co.

467 S.W.2d 635
CourtCourt of Appeals of Texas
DecidedMay 13, 1971
Docket15467
StatusPublished
Cited by6 cases

This text of 467 S.W.2d 635 (Pacific Coast Engineering Co. v. Trinity Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pacific Coast Engineering Co. v. Trinity Construction Co., 467 S.W.2d 635 (Tex. Ct. App. 1971).

Opinion

BELL, Chief Justice.

In this case in the trial court the appellant was plaintiff and cross-defendant and appellee was defendant and cross-plaintiff. Appellant, after trial to a jury, recovered judgment against appellee in the amount of $31,382.62, with interest from the date of judgment. Appellant appeals because it was denied recovery of an attorney’s fee of $18,500.00 found by the jury and because of disallowance of certain interest and some other damages sought by it. Ap-pellee- was denied any recovery on its cross-action. By cross points appellee complains of the judgment rendered against it and in favor of Pacific and because judgment should be in its favor on its cross-action.

We will, however, refer to Pacific as Pacific or appellant and Trinity as Trinity or appellee.

In 1959 Trinity entered into a contract with the United States, through the Corps of Engineers, to construct Canyon Dam in Comal County. Trinity then entered into a contract with Pacific to fabricate four hydraulically operated gates to control the flow of water from the reservoir created by the dam. The contract price for the four gates was $233,800.00. Payment on the gates was made, except for a retainage of 10%, as provided in the contract. The full contract price was to be paid on acceptance by the Corps of Engineers of the gates, or, of acceptance of the project according to appellee.

The four gates were fabricated, assembled and shop tested in California, the tests being conducted by Pacific employees in the presence of representative of the Corps of Engineers. This resulted in approval by the Corps of Engineers. In early 1960 the gates were disassembled and shipped to the jobsite. The gates were to be reassembled and installed by Trinity. Pacific offered, for a fee, to send its representatives to supervise installation, but Trinity chose to make installation. At Trinity’s request Pacific furnished written directions and procedures to be followed. After the gates were installed they were field tested on May 1, 1961. On such test damage resulted to Gate No. 1. The gate stem which is attached to the piston in the hydraulic cylinder mounted on top of the gate bonnet, and which is used to raise and lower the gate leaf in the gate frame and bonnet, did not travel freely up and down as it was designed to do. The stem was caused to bind and scrape against the stainless steel gland or bushing located at the top of the bonnet resulting in some of the monel metal cladding, or outer surface on the stem, being torn or scraped from the steel core and gland and related packing and gaskets being damaged. Pacific’s position is that the misalignment was brought about by Trinity when it set the gate preparatory to setting it in concrete. Pacific says the gate frame was not set level and plumb but was tilted when Trinity encased it in concrete. Pacific says the bottom of the assembly was tilted to the west and north and the upper portion, that is, the bonnet was tilted to the east and south. This tipping of the gate frame, Pacific contends, at an angle or “dogleg”, in view of the microscopic tolerances, caused the damage.

Trinity contends there were defects in fabrication that caused the damages. Trinity urges many defects but relies principally on the following:

1. Failure of Pacific to machine a protruding brass seal flush with the gate leaf on the south.

2. A .037 mislocation of the gate stem to one side.

3. Excessive metal left on adjacent to a bonnet guide.

*638 4.Extension of the south bonnet guide .031 of an inch to the north of the south gate frame guide.

Pacific sued on the contract for full performance to recover the unpaid retainage, plus interest, for the reasonable expense incurred in making repairs to Gate No. 1, plus interest, and for attorney’s fees, for material furnished. By a trial amendment Pacific sought recovery on the theory of substantial performance.

Trinity sought recovery of the reasonable cost and expense allegedly caused it by reason of its work made necessary because of the failure of Gate No. 1, which failure was allegedly caused by defective fabrication.

The jury found as follows in response to the following numbered special issues:

1. The hydraulic gates were fabricated and delivered by Pacific in substantial performance of the contract, plans and specifications.

2. It would reasonably cost Trinity $2900.00 to remedy the failure of Pacific to fabricate the four gates in accordance with its contract and within the contemplation of the plans and specifications.

3. Failed to find the failure of Pacific to manufacture and deliver Gate No. 1 within the contemplation of the contract, plans and specifications was a producing cause of damage to Gate 1.

4. Failed to find such failure was the sole producing cause of such damage.

5. Found the reasonable cost to Trinity to rectify, repair and recondition Gate No. 1 as a result of the damage occurring May 1, 1961 to be nothing.

6. Found the failure of Trinity to erect and install Gate No. 1 within the contemplation of the contract, plans and specifications and reasonably prudent construction practices was a producing cause of damage occurring to Gate No. 1.

6-A. Failed to find that such failure by Trinity was the sole producing cause of such damage.

7. Found that by requesting Pacific to repair, rectify and recondition the gate Trinity did not impliedly agree to pay Pacific the reasonable and customary charges for such work.

8. Found the reasonable and necessary expense incurred by Pacific in repairing, rectifying and reconditioning the gate to be $1961.05.

9. Found a reasonable attorney’s fee for Pacific for prosecution and collection of such expense to be $1000.00.

10. Found a reasonable attorney’s fee to Pacific for prosecution of its _ claim against Trinity over and above the attorney’s fee found for collecting for the repairs to be $18,500.00.

On Trinity’s motion the trial court disregarded the jury’s finding in answer to Issue No. 10 and did not allow recovery of an attorney’s fee of $18,500.00. The court refused Pacific’s motion to disregard the answer to Issue No. 8 finding $1961.05 and render judgment on that issue in the amount of $7919.00. On Pacific’s motion the court also disregarded the answer to Issue No. 7 but allowed recovery of only the amount found by the jury in answer to Issue No. 8.

The trial court denied recovery of an attorney’s fee in the amount of $18,500.00 found in answer to Issue No. 10 because it concluded that since the gates were fabricated and delivered pursuant to special contract such a fee was not within the purview of Article 2226, V.A.T.S.

We are of the view that the trial court assigned the wrong reason but correctly refused to allow recovery for another reason. The fact there is a contract for materials furnished does not preclude recovery under Article 2226. Page v. Superior Stone, 412 S.W.2d 660, Tex.Civ.App., ref., n. r. e. Though a wrong legal theory *639

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oyster Creek Financial Corp. v. Richwood Investments II, Inc.
176 S.W.3d 307 (Court of Appeals of Texas, 2004)
Aztec Corp. v. Tubular Steel, Inc.
758 S.W.2d 793 (Court of Appeals of Texas, 1988)
Missouri Pacific Railroad v. American Statesman
538 S.W.2d 229 (Court of Appeals of Texas, 1976)
Pacific Coast Engineering Co. v. Trinity Construction Co.
481 S.W.2d 406 (Texas Supreme Court, 1972)
Wilson v. Whitcher
477 S.W.2d 344 (Court of Appeals of Texas, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
467 S.W.2d 635, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pacific-coast-engineering-co-v-trinity-construction-co-texapp-1971.