Pace Construction Services L L C v. Federal Insurance Co

CourtDistrict Court, W.D. Louisiana
DecidedSeptember 27, 2024
Docket2:23-cv-00197
StatusUnknown

This text of Pace Construction Services L L C v. Federal Insurance Co (Pace Construction Services L L C v. Federal Insurance Co) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pace Construction Services L L C v. Federal Insurance Co, (W.D. La. 2024).

Opinion

UNITED STATES DISTRICT COURT WESTERN DISTRICT OF LOUISIANA LAKE CHARLES DIVISION

PACE CONSTRUCTION SERVICES L L C : CASE NO. 2:23-CV-00197

VERSUS : JUDGE JAMES D. CAIN, JR.

FEDERAL INSURANCE CO : MAGISTRATE JUDGE LEBLANC

MEMORANDUM ORDER Before the Court is a Motion to Stay, or in the Alternative, for Extension of Time, filed by defendant Federal Insurance Company. Doc. 8. For the reasons that follow, IT IS ORDERED that the Motion to Stay [doc. 8] is GRANTED and that the litigation is stayed until the earlier of the completion of the contractual dispute resolution procedures described in Section 11.1.2 of the Subcontract or entry of an order by this Court lifting the stay; provided, however, that notwithstanding the stay discovery may proceed as described below. IT IS FURTHER ORDERED that plaintiff Pace Construction Services (“Pace”) is authorized to conduct limited discovery concerning facts relevant to the stay request, including without limitation whether and the extent to which non-party Sauer Incorporated intends to pursue claims on Pace’s behalf with the Owner, the progress made toward resolution of those claims between Sauer Incorporated and the Owner, and whether any claims raised by Pace in this litigation have completed the contractual claims resolution process. IT IS FURTHER ORDERED that the undersigned will conduct a telephone status conference with the parties on December 11, 2024, at 11:00 a.m. to discuss progress toward resolution of the claims necessitating the stay. To participate in the conference, counsel are to call the Chambers Teleconference Line at 877-336-1274, Access Code 7066014. I. BACKGROUND This Miller Act litigation arises from a construction project to renovate barracks at the U.S. Army Base at Fort Johnson (formerly Fort Polk) in Vernon Parish, Louisiana. Doc. 1, pp. 1-2. Plaintiff Pace is a subcontractor who performed work on the project. Id. Pace’s work was governed by a Subcontract between itself and Sauer Incorporated (“Sauer”), the Design-Builder for the project. Sauer contracted directly with the owner of Fort Johnson, the Department of the Army-Fort Worth Division (the “Owner”). As required by the Miller Act, 40 U.S.C. § 3131 et

seq., Sauer’s surety, Federal Insurance Company (“FIC”), executed a payment bond in the amount of the prime contract.1 Id. at 1-3. Pace initiated this Miller Act lawsuit against FIC for delay damages and remaining amounts owed under the Subcontract. Doc. 1. The Complaint alleges that, “per change orders authorized by the Subcontract and executed by Sauer,” the contract price was increased over the course of the project due to factors outside of Pace’s control, including the discovery of asbestos, Sauer’s unilateral work stoppages, the COVID pandemic, unusually bad weather, and “Sauer’s discovery

1 The Miller Act provides a contractor on a government construction project with a remedy analogous to a state-law lien. “The general contractor on most government projects must give the United States a payment bond, and subcontractors or others who provide goods and services on the project may sue on the bond for amounts that the contractor does not pay.” Hicks Elec. Co. v. Pac. Tech-Sauer, Inc., No. 15-CV-1059, 2016 WL 5173583, at *2 (W.D. La. Aug. 25, 2016), report and recommendation adopted, No. CV 15-1059, 2016 WL 5210577 (W.D. La. Sept. 21, 2016) (citing 40 U.S.C. §§ 3131, 3133)). that the parapet walls were not structurally connected to the roof deck and Sauer’s directive to Pace to perform extra work to fix the issue before proceeding.” Id. at ¶¶ 9-11. In its Motion to Stay, or, in the Alternative, for Extension of Time [doc. 8], FIC argues that the Subcontract requires Pace to stay this litigation while Sauer pursues contractually-required dispute resolution vis-à-vis the Owner. The issue before the court is whether Section 11.1.2 of the

Subcontract (the “Stay Provision”) requires this litigation to be stayed. The Stay Provision states: It is expressly agreed that if Subcontractor files a Miller Act lawsuit which includes any claim(s) involving the correlative rights or duties of Owner, and such claim(s) is/are not otherwise dismissed by the Court, the Subcontractor shall stay the lawsuit for such time as necessary to pursue such claim(s) against the Owner pursuant to the terms of this paragraph.

Doc. 10, att. 1, p. 28. Section 11.1.2 requires, inter alia, that the “Subcontractor shall submit all claims for extra costs for which the Owner is or may be liable through Design-Builder for transmittal to the Owner [ . . . ]” and prescribes procedures governing the transmittal of those claims. Since the initial round of briefing on this motion [docs. 8, 10, 12], the Parties have submitted supplemental briefing [docs. 20-21], and have come before this Court for hearing [doc. 22]. As of the date of the motion hearing, FIC identifies the following issues that remain outstanding and warrant a stay of the proceedings under the Stay Provision: Sauer submitted requests for equitable adjustment (“REAs”) to the Owner “seeking millions of dollars in costs and time impacts allegedly owed by the owner[,]” and “at least one,” REA001, includes claims on behalf of Pace and is not yet resolved.2 Doc. 21, p. 2. FIC also confirmed at hearing its understanding that delay damages related to the parapet wall change order (“Change Order No.

2 REA001 concerns costs associated with unforeseen conditions of non-structural Chase infills, and it includes a claim for $8,500 submitted on Pace’s behalf, Doc. 21, att. 1, p. 2. 6”) are still pending within the REAs. 3 Additionally, the Owner assessed Sauer approximately $3 million in liquidated damages, but the Owner is “reconsidering” that figure because of the pending REAs.4 II. THE PARTIES’ ARGUMENTS Defendant FIC argues that the Stay Provision requires this litigation to be stayed pending the contractual dispute resolution because the Owner may be liable for some of the claims that are the subject of Pace’s lawsuit and the issues described above remain unresolved. Doc. 8. Pace urges that Sauer has long maintained that it owes no further amounts to Pace for its work and “there is no reasonable basis for expecting that any of the amounts claimed by Pace in

this litigation will be paid to Pace if Sauer obtains additional funds (for work Pace performed) [ . . . ]” from the Owner. Doc. 10, p. 9. Pace also raises arguments relating to the purpose of the Miller Act and the policies effected by it. Pace argues that the stay provision amounts to a waiver of its right under the Miller Act to immediately claim reimbursement from FIC, and any such waiver must be clear and unequivocal. Doc. 10, p. 13-14.

3 The initial briefing on this motion devoted significant attention to Change Order No. 6. The Complaint specifically discusses the work performed pursuant to Change Order No. 6, i.e., extra work related to the discovery that parapet walls were not structurally connected to the roof deck. Doc. 1, p. 3, ¶ 10. On its face Change Order No. 6 implicates the Owner’s correlative rights and duties because it establishes that the Owner may bear responsibility for the costs required to remedy the condition of the parapet wall, triggering the Stay Provision. Doc. 8, att. 2. At hearing, FIC confirmed its understanding that Sauer submitted a claim for Change Order No. 6 to the Owner, and that the Owner has paid Sauer the direct costs associated with Change Order No. 6, but that delay claims relating to Change Order No. 6 are still pending within the REAs. FIC declined to confirm, however, that Pace stands to benefit from the resolution of those delay claims, citing contract-based defenses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Pace Construction Services L L C v. Federal Insurance Co, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pace-construction-services-l-l-c-v-federal-insurance-co-lawd-2024.