Pace Builders v. Westco Trucking & Contracting, LLC

CourtLouisiana Court of Appeal
DecidedSeptember 28, 2016
DocketCA-0016-0265
StatusUnknown

This text of Pace Builders v. Westco Trucking & Contracting, LLC (Pace Builders v. Westco Trucking & Contracting, LLC) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pace Builders v. Westco Trucking & Contracting, LLC, (La. Ct. App. 2016).

Opinion

NOT DESIGNATED FOR PUBLICATION

STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT

16-265

PACE BUILDERS

VERSUS

WESTCO TRUCKING & CONTRACTING, LLC

**********

APPEAL FROM THE NINTH JUDICIAL DISTRICT COURT PARISH OF RAPIDES, NO. 241,135 HONORABLE GEORGE C. METOYER JR., DISTRICT JUDGE

BILLY HOWARD EZELL JUDGE

Court composed of Elizabeth A. Pickett, Billy Howard Ezell, and Phyllis M. Keaty, Judges.

AFFIRMED IN PART; REVERSED IN PART; AND REMANDED. Jason P. Waguespack Frederick W. Swaim III Alexander L. Williams Galloway, Johnson, Tompkins, Burr & Smith 701 Poydras St., 40th Floor New Orleans, LA 70139 (504) 525-6802 COUNSEL FOR PLAINTIFF/APPELLANT: Healtheon, Inc.

Jonathan D. Stokes Max S. Antony Gold, Weems, Bruser, Sues & Rundell P. O. Box 6118 Alexandria, LA 71307 (318) 445-6471 COUNSEL FOR DEFENDANT/APPELLEE: Westco Trucking & Contracting, LLC

Josh Pace In Proper Person 3050 Hoyt Road Boyce, LA 71409 DEFENDANT/APPELLEE EZELL, Judge.

In this matter, Healtheon, Inc., appeals the decision of the trial court denying

it attorney fees under its contract with Westco Trucking and Contracting, LLC For

the following reasons, we affirm the decision of the trial court in part, reverse in

part, and remand for further proceedings in accordance with our ruling below.

In January of 2010, Healtheon was awarded a public contract by the U.S.

Army Corps of Engineers to perform storm proofing work on pump stations in

Jefferson Parish. Healtheon entered into a subcontract with Westco to provide and

manage labor, materials, and equipment for the job. The contract included

indemnification and duty to defend provisions in favor of Healtheon. Westco then

entered into another subcontract with Pace Builders to perform work on the project.

On March 18, 2011, Pace filed a suit on an open account against both Westco and

Healtheon. Healtheon answered the suit and further filed an incidental demand

against Westco, seeking indemnification under the contract. Westco answered

both claims, denying Healtheon was entitled to indemnification in the suit.

Healtheon later filed a motion for summary judgment on its incidental

demand, which was opposed by Westco. The trial court granted Healtheon’s

motion for summary judgment, ruling that it was entitled to indemnification for all

claims asserted by Pace, including attorney fees and costs. The attorney fees were

to be determined at a later hearing. When that hearing occurred, the trial court

ruled that because Healtheon failed to properly demand a defense from Westco, it

was not entitled to recover any attorney fees for its claims. From that decision,

Healtheon appeals.

Healtheon asserts one long assignment of error containing three overlapping

assertions. Healtheon claims that the trial court erred in interpreting the contract between it and Westco; that the trial court erred in finding that Healtheon failed to

properly demand a defense from Westco against the Pace lawsuit; and that the trial

court erroneously denied it attorney fees associated with this suit.

Questions of contractual interpretation are questions of law which are subject to a de novo standard of review. Mitchell v. Patterson Ins. Co., 00-612 (La.App. 3 Cir. 12/6/00), 774 So.2d 366. Contracts have the force of law between the parties, and the courts are bound to interpret them according to the common intent of the parties. La.Civ.Code arts. 1983 and 2045. If the words of the contract are clear, unambiguous, and lead to no absurd consequences, the court need not look beyond the contract language to determine the true intent of the parties. La.Civ.Code art. 2046. “Each provision in a contract must be interpreted in light of the other provisions so that each is given the meaning suggested by the contract as a whole.” La.Civ.Code art. 2050. Whether or not a contract is ambiguous is a question of law. La. Ins. Guar. Ass’n v. Interstate Fire & Cas. Co., 93-911 (La.1/14/94), 630 So.2d 759. These general rules that govern the interpretation of most contracts apply to contracts of indemnity. Soverign Ins. Co. v. Tex. Pipe Line Co., 488 So.2d 982 (La.1986).

Boykin v. PPG Indus., Inc., 08-117, pp. 4-5 (La.App. 3 Cir. 6/18/08), 987 So.2d

838, 842, writs denied, 08-1635, 08-1640 (La. 10/31/08), 994 So.2d 537.

However, “factual findings which are pertinent to the interpretation of a

contract will not be disturbed absent manifest error.” Campbell v. Melton, 01-2578,

p. 12 (La. 5/14/02), 817 So.2d 69, 78. “In applying the manifest error rule to the

trial court’s interpretation, the Court of Appeal may not simply substitute its own

view of the evidence for the trial court’s view, nor may it disturb the trial court’s

finding of fact so long as it is reasonable.” French Quarter Realty v. Gambel, 05-

933, pp. 3-4 (La.App. 4 Cir. 12/28/05), 921 So.2d 1025, 1028.

We find that the trial court’s determination that Healtheon failed to demand

a defense from Westco to be reasonable based on the scant record before this court.

Section 15.3 of the contract deals with Westco’s duty to defend Healtheon and

provides (emphasis ours):

2 In all such cases where [Westco’s] indemnity obligation under this Subcontract Agreement apply, [Westco] shall, upon demand by Healtheon, provide a competent defense of all Claims covered by [Westco’s] indemnity and shall remain responsible for all the Costs of defense of the Claim, and any damages awarded to the claimant by settlement, mediation, arbitration, litigation or otherwise. Should [Healtheon] be required to retain an attorney to defend any Claims, [Westco] shall reimburse any reasonable Costs incurred by [Healtheon] to defend such claims.

In Healtheon’s incidental demand, it mentioned, but did not demand or pray

for a defense to be provided by Westco. Only indemnification was prayed for.

Likewise, in its subsequent demand letter to Westco seeking attorney fees,

Healtheon demanded reimbursement for costs incurred, but again did not demand

that a defense be provided by Westco. There is no other evidence in the record that

indicates that Healtheon was ever required or actually called for Westco to provide

it a defense in the suit by Pace. Therefore, we can find no manifest error in the

trial court’s factual finding that Healtheon failed to properly demand that Westco

provide it a defense. Accordingly, Healtheon is not entitled to costs associated

with its defense of the Pace claim itself.

However, after reviewing the record and the plain terms of the contract, we

find that the trial court did err in ruling that Healtheon was not entitled to any

attorney fees, as the contract clearly provided for attorney fees should any party be

forced to sue to enforce the provisions of the contract. The contract provided, in

pertinent part:

15. INDEMNIFICATION.

15.1 General. Subcontractor [Westco] hereby agrees to indemnify, save and hold harmless, and defend [Healtheon] from and against any and all liabilities, Claims, damages, including, but not limited to . . . suits and the costs and expenses incident thereto, including, without limitation, costs of defense, settlement, and attorneys’ and paralegals’ fees, arising out of or connected in any way

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Louisiana Ins. Guar. Ass'n v. Interstate Fire & Casualty Co.
630 So. 2d 759 (Supreme Court of Louisiana, 1994)
Alex v. Rayne Concrete Service
951 So. 2d 138 (Supreme Court of Louisiana, 2007)
Soverign Ins. Co. v. Texas Pipe Line Co.
488 So. 2d 982 (Supreme Court of Louisiana, 1986)
Mitchell v. Patterson Ins. Co.
774 So. 2d 366 (Louisiana Court of Appeal, 2000)
Boykin v. PPG Industries, Inc.
987 So. 2d 838 (Louisiana Court of Appeal, 2008)
Campbell v. Melton
817 So. 2d 69 (Supreme Court of Louisiana, 2002)
French Quarter Realty v. Gambel
921 So. 2d 1025 (Louisiana Court of Appeal, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Pace Builders v. Westco Trucking & Contracting, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pace-builders-v-westco-trucking-contracting-llc-lactapp-2016.