P. & W.F., Inc. v. C.S.U. Pizza, Inc.

633 N.E.2d 606, 91 Ohio App. 3d 724, 1993 Ohio App. LEXIS 5552
CourtOhio Court of Appeals
DecidedNovember 29, 1993
DocketNo. 63834.
StatusPublished
Cited by18 cases

This text of 633 N.E.2d 606 (P. & W.F., Inc. v. C.S.U. Pizza, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P. & W.F., Inc. v. C.S.U. Pizza, Inc., 633 N.E.2d 606, 91 Ohio App. 3d 724, 1993 Ohio App. LEXIS 5552 (Ohio Ct. App. 1993).

Opinion

Patton, Judge.

Plaintiff-appellant P. & W.F., Inc. (“plaintiff-lessor”) appeals from the trial court’s grant of defendants-appellees’ motion for a directed verdict at the close of plaintiff-lessor’s case during trial. The co-defendants, lessees and/or guarantors, confessed judgment for unpaid obligations in the sum of $5,132.36 plus interest at the rate of ten percent.

Plaintiff-lessor and record title holder of the subject property brought suit against co-defendants 1910, Inc., Frank Wagner and Frances Wagner (collectively “1910, Inc.”) as original lessees and guarantors of the assigned subject lease and C.S.U. Pizza, Inc., Harvey Sussel and Genevieve Lechner (collectively “C.S.U. Pizza”) as assignees for back rent and unpaid utilities.

The relevant facts are as follows: Plaintiff-lessor entered into a five-year lease agreement on or about February 23,1987 whereby plaintiff-lessor agreed to lease the ground floor of 1910 Euclid Avenue to operate a bar and restaurant. *727 Approximately five months later, on or about September 23, 1987, 1910, Inc. assigned the lease to C.S.U. Pizza. In November 1989, just over two years after the lease assignment, a fire in the kitchen shut down the bar and restaurant and rendered it untenantable. At the time of the fire, C.S.U. Pizza was in arrears on the rent. After the fire, however, pursuant to the terms of the lease agreement, rent was abated for several months, which extended into 1990.

In January 1990, two months after the fire, plaintiff-lessor contracted with the Cleveland Repair Company, Stan Marszal, to repair the fire-damaged structure.

On or about March 9,1990, Harvey Sussel of C.S.U. Pizza was asked to remove his personal property from the premises in order that repair work could begin. The record reflects that plaintiff-lessor told Sussel and Genevieve Lechner, both of C.S.U. Pizza, that the premises would be returned to “pre-fire condition.”

During the months after the fire and through the repair work, disputes arose regarding insurance coverage. It was not until April 5, 1990 that a final agreement regarding coverage was reached between plaintiff-lessor’s contractor and the insurance company. By the time the dispute had been resolved, little repair work had been done save for boarding up the windows to secure the building.

However, in May 1990 and again in July 1990, the premises fell victim to vandalism. First, the storage area was robbed of equipment. Second, vandals removed the copper plumbing. By this time, Sussel and Lechner began to look for buyers for their business, as it became obvious to them that they could no longer hope to operate their business.

After plaintiff-lessor learned of the vandalism, John Price, president of P. & W.F., Inc., refused to make the necessary repairs, as it was his belief that the repairs were the responsibility of Sussel pursuant to the terms of the lease agreement.

By the fall of 1990, Sussel had already contacted one Robert Cefrey to work on blueprints for Price in order to effectuate the repairs which still had not been completed. When it became apparent to Sussel that the repair work was not proceeding, Sussel told Cefrey to cease work on the blueprints.

By February 1991, Sussel realized that Price and P. & W.F., Inc. had no intention of repairing and restoring the subject premises to pre-fire condition. Therefore, pursuant to the provisions of Paragraph 10 of the lease, Sussel and Lechner gave written notification to terminate the lease, as the premises had been made, and indeed remained, unfit for occupancy. The notification of termination was sent to Price on February 26, 1991.

Paragraph 10, the subject of the dispute, reads as follows:

*728 “10. UNTENANTABILITY: If the premises or the building are made unfit for occupancy by the elements or other cause, the Lessor may elect (a) to terminate this lease, as of the time when the premises or building are made unfit for occupancy, by notice to the Lessee within thirty days after that date, or (b) to repair, restore or rehabilitate the building or the premises at the Lessor’s expense within ninety days after the Lessor is enabled to take possession of the damaged premises and undertake reconstruction or repairs, in which latter event the lease shall not terminate but rent shall be abated on a per diem basis while the premises are unfit for occupancy. If the Lessor elects so to repair, restore or rehabilitate the building or the premises and does not substantially complete the work within the ninety day period, excluding from said period loss of time caused by delays beyond the control of the Lessor, either party can terminate this lease, as of the time when the premises or the building were made unfit for occupancy, by notice to the other party not later than ten days after the expiration of said ninety day period, as so computed. In the event of termination of the lease pursuant to this Section 10, rent shall be apportioned on a per diem basis and be paid to the date of such termination.” (Emphasis added.)

Plaintiff-lessor avers that C.S.U. Pizza breached the terms of the lease by wrongfully terminating its lease. It is the contention of C.S.U. Pizza, through Sussel and Lechner, that as plaintiff-lessor elected to repair and restore the subject premises and did not substantially complete the work within the ninety-day period, even excluding from said period the loss of time beyond plaintiff-lessor’s control, it rightfully terminated the lease by written notification.

The trial court agreed with C.S.U. Pizza and granted its motion for a directed verdict at the close of plaintiff-lessor’s case. C.S.U. Pizza confessed judgment in the sum of $5,132.36 plus interest for back rent which accrued before the fire. The trial court ordered interest at the rate of ten percent per annum. The lease set the interest rate at twelve percent per annum.

Plaintiff-lessor appeals the judgment of the trial court and assigns the following errors for our review:

“I. The trial court committed prejudicial error when in its amended memorandum of opinion and judgment entry nunc pro tunc it granted plaintiff a judgment which included only ten percent (10%) interest from November, 1989 on a principal amount which was confessed.

“II. The trial court committed prejudicial error in granting the defendants’ motion to dismiss by finding that the defendant-tenant had properly terminated the subject lease in February, 1991.

“HI. The trial court’s granting of the defendants’ motion to dismiss made upon the conclusion of the plaintiffs case was erroneous as a matter of law and *729 against the manifest weight of the evidence, and accordingly plaintiff suffered prejudicial error.

“IV. The trial court committed prejudicial error by prematurely granting defendants’ motion to dismiss without the defendants having sustained their burden of proof on the affirmative defense of termination of the lease.

“V. The trial court committed prejudicial error by not making sufficient findings of fact and conclusions of law as required by Civil Rule 52.”

I

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Citibank, N.A. v. Hine
2019 Ohio 464 (Ohio Court of Appeals, 2019)
Buchenroth v. Adkins
2014 Ohio 257 (Ohio Court of Appeals, 2014)
Marion Plaza, Inc. v. D & L Ents., Inc.
2010 Ohio 6267 (Ohio Court of Appeals, 2010)
Marion Plaza, Inc. v. 700 Block L.L.C.
2010 Ohio 1539 (Ohio Court of Appeals, 2010)
Terminal Tower Spe. v. Kaufman, 91332 (10-16-2008)
2008 Ohio 5353 (Ohio Court of Appeals, 2008)
Heffner Invests. v. Piper, 10-07-09 (5-27-2008)
2008 Ohio 2495 (Ohio Court of Appeals, 2008)
Citifinancial v. Barrett, L-07-1058 (3-31-2008)
2008 Ohio 1558 (Ohio Court of Appeals, 2008)
First Bank of Ohio v. Wigfield, 07ap-561 (3-20-2008)
2008 Ohio 1278 (Ohio Court of Appeals, 2008)
Whitestone Co. v. Stittsworth, Unpublished Decision (1-23-2007)
2007 Ohio 233 (Ohio Court of Appeals, 2007)
Wc Milling, LLC v. Grooms
841 N.E.2d 324 (Ohio Court of Appeals, 2005)
Meck v. Burger, Unpublished Decision (5-19-2005)
2005 Ohio 2446 (Ohio Court of Appeals, 2005)
Capital Fund Leasing, L.L.C. v. Garfield
735 N.E.2d 23 (Ohio Court of Appeals, 1999)
Ohio Valley Mall Co. v. Fashion Gallery, Inc.
719 N.E.2d 8 (Ohio Court of Appeals, 1998)
Cafaro Northwest Partnership v. White
707 N.E.2d 4 (Ohio Court of Appeals, 1997)
Yager Materials, Inc. v. Marietta Industrial Enterprises, Inc.
687 N.E.2d 505 (Ohio Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
633 N.E.2d 606, 91 Ohio App. 3d 724, 1993 Ohio App. LEXIS 5552, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-wf-inc-v-csu-pizza-inc-ohioctapp-1993.