P & K Heating & Air Conditioning, Inc. v. Tusten Townhomes Redevelopment Corp.

877 S.W.2d 121, 1994 Mo. App. LEXIS 569, 1994 WL 109274
CourtMissouri Court of Appeals
DecidedApril 5, 1994
Docket62649
StatusPublished
Cited by16 cases

This text of 877 S.W.2d 121 (P & K Heating & Air Conditioning, Inc. v. Tusten Townhomes Redevelopment Corp.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P & K Heating & Air Conditioning, Inc. v. Tusten Townhomes Redevelopment Corp., 877 S.W.2d 121, 1994 Mo. App. LEXIS 569, 1994 WL 109274 (Mo. Ct. App. 1994).

Opinion

CRANE, Presiding Judge.

Tusten Townhomes Redevelopment Corporation (Owner) appeals a judgment in favor of P & K Heating and Air Conditioning, Inc. (Subcontractor) enforcing a mechanics’ hen in the amount of $16,222.00. On appeal Owner contends that the trial court erred in entering judgment in favor of Subcontractor because Subcontractor signed and issued hen waivers in an amount greater than it was owed, that a $2,300.00 hen waiver signed July 1,1987 waived hens on ah work through July 1,1987, and that Subcontractor failed to file a just and true account of its hen. Owner further contends that Subcontractor failed to join and timely serve the general contractor. We affirm.

Owner owned and developed a condominium redevelopment project (Project) at 4561-63 Laclede in St. Louis, Missouri. Owner hired Raymond Burchard, d/b/a Radal Construction Company (Contractor) as the general contractor on the Project. In October, 1985 Contractor contracted with Subcontractor to provide the heating, ventilating and air conditioning work for the Project. Contractor also hired Subcontractor to do some facade work. Mark Twain Mortgage Company (Mark Twain) served as an escrow agent to disburse the proceeds of the construction loan for the development of the Project.

Subcontractor furnished labor and materials to the Project in the amount of $30,-584.36. It was paid $19,090.00. Subcontractor served Owner with the ten day notice and recorded its Statement of Mechanics’ Lien within the statutory limitations period. Subcontractor filed its original Petition to enforce its mechanics’ hen on June 10, 1988.

This case was tried before the Honorable Timothy J. Wilson. The court entered a Judgment and Order in the amount of $11,-494.36 plus 9% statutory interest from July *123 20, 1987, for a total judgment of $16,222.00. The judgment was imposed as a mechanics’ lien against the Project. Owner appeals from the mechanics’ lien judgment. 1

In a court-tried case we sustain the judgment of the trial court unless there is no substantial evidence to support it, it is against the weight of evidence, or it erroneously applies or declare the law. Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976); Commercial Openings, Inc. v. Mathews, 819 S.W.2d 347, 349 (Mo. banc 1991). We accept all evidence and inferences favorable to the judgment, and disregard all contrary inferences. Behen v. Elliott, 791 S.W.2d 475, 476 (Mo.App.1990). We are bound by the trial court’s factual findings if supported by substantial evidence in the record.. Dave Kolb Grading, Inc. v. Lieberman Corp., 837 S.W.2d 924, 930 (Mo.App.1992).

I.

For its first point Owner asserts that the trial court erred in establishing a lien against its property because Subcontractor executed lien waivers in an amount greater than it was owed. At trial Owner offered into evidence the following lien waivers which it had received from Subcontractor:

Amount Date Trial Exhibit No.
$11,733.33 (10/25/85) (Owner’s Exh. 1)
$ 4,943.00 (10/25/85) (Owner’s Exh. 1)
$ 1,556.67 (1/8/86) (Owner’s Exh. 2)
$11,733.33 (11/11/85) (Owner’s Exh. 3)
$ 3,500.00 (7/16/86) (Owner’s Exh. 4)
$ 2,300.00 (7/1/87) (Owner’s Exh. 5)
$35,766.33 Total 2

Owner contends that it paid either Contractor or Subcontractor the amounts equal to the face amount of all the lien waivers provided to Mark Twain. Owner’s argument under this point does not detail any of these payments or specify the amount or date of any payment on which it relies. There is no dispute that Subcontractor, alone or jointly with Contractor, was paid the amounts shown on the lien waivers contained in Exhibits 2-5. Subcontractor testified it received payments in the following amounts which were substantiated by payment vouchers:

Amount Payable to Date Exhibit No.
$ 1,556.67 Contractor and 1/7/86 Owner’s Exh. 2 Subcontractor
$11,733.33 Contractor and 1/13/86 Owner’s Exh. 3 Subcontractor
$ 3,500.00 Subcontractor 7/16/86 Owner’s Exh. 4
$ 2,300.00 Subcontractor 7/6/87 Owner’s Exh. 5
$19,090.00

We assume Owner is including a $60,229.00 disbursement to Contractor on October 10, 1985, contained in its trial Exhibit 1, when it argues it paid out the face amounts of each of Subcontractor’s lien waivers. The trial court found that Subcontractor was not paid the sums of $11,733.33 and $4,943.00 (the face amounts of the October 25,1985 lien waivers) from this disbursement. This finding is supported by substantial evidence including Subcontractor’s testimony and business records.

To be valid a lien waiver must be supported by consideration or must have induced the party receiving it to have detrimentally changed its position in reliance upon the waiver. Herbert & Brooner Construction Co. v. Golden, 499 S.W.2d 541, 545 (Mo.App.1973). Where a lien claimant has not received consideration, it may successfully assert the invalidity of a lien waiver if the owner or other interested person has not paid out money or otherwise changed its position to his detriment in reliance on the waiver. St. Louis Flexicore, Inc. v. Lintzenich, 414 S.W.2d 787, 790-91 (Mo.App.1967).

Owner argues that it detrimentally relied on the waivers by signing payment vouchers in the face amount of each waiver. *124 The evidence at trial does not support owner’s reliance claim with respect to the October 25, 1985 waivers. A representative of Mark Twain Bank, who was loan coordinator and records custodian, testified that Mark Twain had copies of the $11,733.33 and $4,943.00 lien waivers, both dated October 25, 1985, in its file. The representative testified that Mark Twain’s practice was that it would not have authorized the initial $60,229.00 disbursement to Contractor unless it had received the lien waivers. However, she was not the loan coordinator at the time the disbursement was processed. She testified to this transaction as records custodian, not from personal knowledge.

Further, the dates and contents of the documents in Mark Twain’s file, which Owner packaged as its Exhibit 1, are evidence from which the trial court could have found Mark Twain did not issue the $60,229.00 disbursement in reliance on Subcontractor’s lien waivers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.W. ex rel. A.W. v. St. Louis Public Schools
Missouri Court of Appeals, 2022
Johnson v. DELMAR GARDENS WEST, INC.
335 S.W.3d 83 (Missouri Court of Appeals, 2011)
Glenstone Block Co. v. Pebworth
264 S.W.3d 703 (Missouri Court of Appeals, 2008)
Deane v. S.F. Pizza, Inc.
229 S.W.3d 223 (Missouri Court of Appeals, 2007)
TBF Financial, L.L.C. v. Stone
213 S.W.3d 231 (Missouri Court of Appeals, 2007)
Woods Ex Rel. Woods v. Cory
192 S.W.3d 450 (Missouri Court of Appeals, 2006)
Stromberg v. Moore
170 S.W.3d 26 (Missouri Court of Appeals, 2005)
American Property Maintenance v. Monia
59 S.W.3d 640 (Missouri Court of Appeals, 2001)
Landvatter Ready Mix, Inc. v. Buckey
963 S.W.2d 298 (Missouri Court of Appeals, 1997)
Gibson v. Adams
946 S.W.2d 796 (Missouri Court of Appeals, 1997)
Tharp v. Keeter/Schaefer Investments, L.P.
943 S.W.2d 811 (Missouri Court of Appeals, 1997)
Pagano v. Director of Revenue, State
927 S.W.2d 948 (Missouri Court of Appeals, 1996)
Berry v. State
908 S.W.2d 682 (Supreme Court of Missouri, 1995)
Schnucks Carrollton Corp. v. Bridgeton Health & Fitness Inc.
884 S.W.2d 733 (Missouri Court of Appeals, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
877 S.W.2d 121, 1994 Mo. App. LEXIS 569, 1994 WL 109274, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-k-heating-air-conditioning-inc-v-tusten-townhomes-redevelopment-moctapp-1994.