P. J. Construction Co. v. Roller
This text of 340 S.E.2d 564 (P. J. Construction Co. v. Roller) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Appellants Wilbert Roller, Jr., Betty V. Roller and Edgar C. Wiggins, Jr. were the defendants in separate, virtually identical mechanic’s lien foreclosure actions commenced by respondent P. J. Construction Co. These actions have been consolidated for trial and for appeal. The trial judge denied the Rollers’ and Wiggins’ separate motions for summary judgment and granted P. J. Construction’s motions to strike the Rollers’ and Wiggins’ defenses of res judicata and waiver. We affirm and remand for trial.
An order striking a portion of a pleading is immediately appealable. See Harbert v. Atlanta & Charlotte Air Line Railway, 74 S. C. 13, 16, 53 S. E. 1001, 1002 (1906). The sole issue on appeal is whether the trial judge abused his discretion in striking the defenses of res judicata and waiver.
In 1980, P. J. Construction brought two actions for foreclosure of mechanic’s liens. The Rollers and Wiggins answered the complaints and asserted counterclaims for breach of contract and negligence. Prior to trial, P. J. Construction moved to strike the counterclaims on the ground that the mechanic’s liens foreclosure proceedings were in re to actions in which in personam counterclaims could not be asserted. The trial judge granted the motion.
During trial at the close of P. J. Construction’s case, the Rollers and Wiggins moved for an involuntary nonsuit based on P. J. Construction’s failure to plead and prove that lis pendens had been filed as required by Section 29-5-120,1976 Code of Laws of South Carolina, as amended. After P. J. Construction stipulated that no lis pendens had been filed, the trial judge dismissed the mechanic’s lien actions with prejudice and issued two orders which provide in part:
[NJothing in this Order shall be interpreted as indicating that a decision has been reached as to the right of plaintiff to bring another action on the same set of facts and circumstances, since that question was not appropriately before the Court within the confines of this action.
[634]*634The record does not reflect that any party appealed from these orders.
Thereafter, P. J. Construction instituted these breach of contract actions. The Rollers and Wiggins answered, alleging the affirmative defenses of res judicata, waiver and laches and asserting counterclaims for breach of contract. Their waiver argument is that by bringing the mechanic’s lien foreclosure actions, P. J. Construction elected that remedy, thereby waiving its right to seek recovery on any other theory available at that time. Their res judicata argument is based upon the belief that the orders granting the involuntary nonsuits in the mechanic’s lien actions bar the maintenance of another action between the same parties seeking the same damages.
Thereafter, P. J. Construction moved to strike the Rollers’ and Wiggins’ res judicata and waiver defenses. The trial judge granted the motions. His rulings were correct.
I.
Res Judicata
The doctrine of res judicata requires “proof of three basic elements: (a) identity of parties; (b) identity of the subject matter; and (c) adjudication in the former suit.” Eichman v. Eichman, 285 S. C. 378, 329 S. E. (2d) 764, 766 (1985). Under this doctrine “[a] litigant is barred from raising any issues which were adjudicated in the former suit and any issues which might have been raised in the former suit.” Id. The doctrine of res judicata bars relitigation of the same cause of action. Liberty Mutual Insurance Co. v. Employers Insurance of Wausau, 284 S. C. 234, 237, 325 S. E. (2d) 566, 568 (Ct. App. 1985).
Here, no valid res judicata defense can be raised because the first actions between the parties concerned foreclosure of mechanic’s liens while the actions here raise breach of contract claims which could not have been raised in the mechanic’s lien foreclosure actions.
II.
Waiver
The Rollers’ and Wiggins’ argument is threefold: one, P. J. Construction knew or should have known that the mechanic’s lien actions would fail because of the [635]*635failure to file lis pendens
The Rollers and Wiggins also argue that P. J. Construction gained a benefit by bringing the mechanic’s lien foreclosure actions before bringing the breach of contract actions. They further argue that they suffered a substantial detriment. We disagree. The election of one remedy will not prevent a matter from being litigated on another theory “unless the suit upon the remedy first invoked shall reach the state of final adjudication, * * * or unless by the invocation of the remedy first sought to be enforced, the plaintiff shall have gained an advantage thereby or caused detriment or change of situation to the other.” Jones v. South Carolina Power Co., 198 S. C. 380, 387, 18 S. E. (2d) 336, 339 (1941).
The Rollers and Wiggins have not demonstrated that P. J. Construction received any benefit from initiating four actions involving two theories to adjudicate its claims. They claim a “substantial detriment” in being “forced to trial in 1980 without the full benefit of all claims that they were entitled to assert.” We see no such detriment. Their motions for involuntary nonsuit were granted prior to the presentation of their cases.
The Rollers and Wiggins also claim that they have suffered a detriment by defending “a multiplicity of suits on the same facts.” We disagree. If the prior suit [636]*636resulted in a final adjudication of the issues involved here, we might hold otherwise. However, “[a]n order of involuntary nonsuit is not a final determination of the case oh its merits.” Jones, 198 S. C. at 387, 18 S. E. (2d) at 339.
Affirmed and remanded.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
340 S.E.2d 564, 287 S.C. 632, 1986 S.C. App. LEXIS 288, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-j-construction-co-v-roller-scctapp-1986.