P. J. Carlin & Co. v. United States

53 Ct. Cl. 376, 1918 U.S. Ct. Cl. LEXIS 130, 1918 WL 1039
CourtUnited States Court of Claims
DecidedApril 22, 1918
DocketNo. 24757
StatusPublished

This text of 53 Ct. Cl. 376 (P. J. Carlin & Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P. J. Carlin & Co. v. United States, 53 Ct. Cl. 376, 1918 U.S. Ct. Cl. LEXIS 130, 1918 WL 1039 (cc 1918).

Opinion

Campbell, Chief Justice,

delivered the opinion of the court.

The matters involved herein were referred to this court by the Secretary of the Navy under the provisions of section 148 of the Judicial Code, the reference having been made upon the application of plaintiffs. Under the provisions of the contract involved in the case it is probable that all of the questions could have been decided by the Secretary. He appointed a board, which took a large amount of testimony and made an investigation required by his order, consuming more that a year’s time, and reported their recommendations. Without taking further action than to tender to the plaintiffs the difference between the amount found by the board to be the value of the work done, with the value of certain materials added, and the amount which had already been paid the plaintiffs, the entire controversy was referred to this court.

Thereafter the plaintiffs appeared and filed their petition in this court.

The rules of the Supereme Court provide that this court shall find the ultimate facts, and also provide that the parties may make requests for findings of fact deemed by them to be material for the due presentation of the case. The rules of this court, established to carry into effect the rules of the [397]*397Supreme Court, require a statement, in the form of distinct number propositions, of the facts which the party desires to have found, so arranged as to present a concise statement in orderly and logical sequence of the whole case as the party desires it to appear in the findings of fact, and that subjoined to each proposition so requested there shall be references to the pages of the record or to the unprinted evidence relied on in its support. The rule also requires that where a party objects to requested findings of fact by the other party the objection shall be pointed out specifically, with appropriate references to the record relied upon to support them. Either party is allowed to make requests for findings of fact. The rule does not contemplate or authorize in the requested findings of fact arguments or conclusions of fact or of law. We call attention to these rules because in the instant case they have not been ful-ly observed.

In 1899 the plaintiffs entered into a contract with the United States for the construction of certain sections of a sea wall near the Naval Academy and agreed to deliver the same complete in all respects as required by the drawings, plans, and specifications to the Superintendent of the Naval Academy, or to such person as he might direct to receive the same. A copy of the contract and specifications is attached to the petition. By the specifications, made a part of the contract, it was provided that the contractors should guarantee and maintain the stability of all work and material and keep same in perfect repair and condition for a period of one year after the issuance of the final certificate and would make good any defects appearing during that period when called upon to do so. The obligation of the plaintiffs therefore extended not only to the building of the sea wall but to its maintenance for the period stated, and having entered into that obligation, strict as it was, it became their duty to perform it.

It was said by the Supreme Court in Dermott v. Jones, 2 Wall., 1:

“ It is a well-settled rule of law that if a party by his contract charge himself with an obligation possible to be per[398]*398formed he must make it good, unless its performance is rendered impossible by the act of God, the law, or the other party. Unforseen difficulties, however great, will not excuse him.”

Under the rules laid down in that case the plaintiffs would have no standing in this court, because they did not perform their contract, were it not for the fact that their contract was annulled and the controversy subsequently transferred to this court.

During the time of the prosecution of the work under this contract the plaintiffs were also prosecuting other work at the Naval Academy under contracts involving much larger sums than was involved under this contract. The work under the several contracts was carried along simultaneously. The original contract with which we have to do was made in February, 1899, and provided for the completion of the work upon the sea wall in 270 days. Several extensions of time were granted at the request of the plaintiffs, and considerable delays,, shown in the findings, were occasioned by the agents of the defendants.

A large part of the contention of plaintiffs is devoted to an attack upon the architect and upon the plans and specifications, and, strangely enough, it is alleged in the petition that the plaintiffs performed all that was required by their contract. It must be presumed that the contractors, who were experienced in their line of work, understood something of the nature of the work they undertook to perform. It is too ■late, after a contract is made and its obligations have been assumed, to complain of features that should have been considered before the contractors agreed to do the work. Dermott v. Jones, supra. They not only charge incompetency upon the architect but also bad faith on the part of the officers having supervision of the work, and they in substance charge that fraud was perpetrated upon them in the matter of certain borings which were made prior to the time of the contract. These charges are not sustained. The said borings were made to ascertain the character of the soil into which the piles were to be driven, and were by what is called the wash-boring method. The charge that these borings [399]*399were improperly made is not sustained by the evidence. A correct record of the borings was kept, and it was accessible to all contractors when they made their bids. In addition thereto notations were made upon some of the plans calling attention to the location of the wall asnd the result of the borings. A prudent contractor was thus sufficiently put upon notice of the uncertainties of the soil into which piles were to be driven and the uncertainties of the foundation upon which they were to rest to sustain the sea wall. That difficulties were encountered which had not been anticipated by the contractors and which were unexpected by the Government’s agents, appears certain, and it also appears that the contractors were not left entirely free and at times were not left reasonably free to cope with the situation as it developed. On the contrary, the defendants’ superintendent in many instances took what may be characterized as a practical direction of the work. It was the right and duty of the contractors to build the sea wall according to their contract and without undue interference on the part of the Goverment’s agents.

As shown by the findings of fact, the wall sank in places and went somewhat out of alinement. The producing cause of these conditions is not definitely shown. If it was the duty of the contractors to prevent or remedy such conditions it was their right to be allowed to do so within the terms of their contract without undue interference or delays caused by the agents of the defendants.

The contractors were engaged on the work in September, 1902, more than three years after it had begun. On or about September 17, 1902, pursuant to direction by the Assistant Secretary of the Navy work was discontinued. In December thereafter a board was appointed by the Assistant Secretary of the Navy to examine into the status of the work and report thereon, as shown in Finding XVIII.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dermott v. Jones
69 U.S. 1 (Supreme Court, 1865)

Cite This Page — Counsel Stack

Bluebook (online)
53 Ct. Cl. 376, 1918 U.S. Ct. Cl. LEXIS 130, 1918 WL 1039, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-j-carlin-co-v-united-states-cc-1918.