P & F Construction Corp. v. Friend Lumber Corp. of Medford

575 N.E.2d 61, 31 Mass. App. Ct. 57, 16 U.C.C. Rep. Serv. 2d (West) 377, 1991 Mass. App. LEXIS 488
CourtMassachusetts Appeals Court
DecidedJuly 17, 1991
Docket89-P-1236
StatusPublished
Cited by14 cases

This text of 575 N.E.2d 61 (P & F Construction Corp. v. Friend Lumber Corp. of Medford) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P & F Construction Corp. v. Friend Lumber Corp. of Medford, 575 N.E.2d 61, 31 Mass. App. Ct. 57, 16 U.C.C. Rep. Serv. 2d (West) 377, 1991 Mass. App. LEXIS 488 (Mass. Ct. App. 1991).

Opinion

Kass, J.

For the reason that the buyer, P&F Construction Corporation (“P&F”), failed within a reasonable time to notify the seller, Friend Lumber Corporation (“Friend”), of a claimed deficiency in goods furnished, see G. L. c. 106, § 2-607(3)(a), summary judgment was correctly entered for Friend.

On the basis of the affidavits and depositions served up with Friend’s motion for summary judgment, we 'may take it to have been established as undisputed facts that on August 4, 1985, P&F ordered 338. door units (doors with jambs) for an apartment condominium project on which P&F was the general contractor. There was an identity of interest between the contractor and the owner; i.e., Vincent C. Fantasia, the president, clerk, and a director of P&F, was also trustee of Winchester Investment Trust, the developer of the condominium project. With what Fantasia, in his role as chief executive of P&F, regarded as excessive promptness, the door units arrived on the job site on August 26, 1985. Each door unit came wrapped in clear plastic. Fantasia made the first documented complaint about the shipment on October 30, 1985, when he rejected an interest charge on a bill for the balance due on P&F’s open account with Friend. As the goods had arrived prematurely and it was a nuisance having them around the job site, Fantasia wrote in a letter to Friend, an interest charge on his balance was not warranted. Until December 15, 1985, there was no documented complaint that the door units were one-quarter inch off size, and, even then, the only grievance articulated as the basis for a back charge was “for the storage and handling of said shipment.” Cf. Nugent v. Popular Mkts., Inc., 353 Mass. 45, 48-50 (1967). During deposition, Fantasia “believed” he had notified Friend prior to December 15 of his dissatisfaction with the size of the door jambs, but “"[ejxpressions of belief and understanding fall short of such specific facts ‘as would be *59 admissible in evidence’ . . . .” Hartford Acc. & Indem. Co. v. Millis Roofing & Sheet Metal, Inc., 11 Mass. App. Ct. 998, 999 (1981). See Key Capital Corp. v. M & S Liquidating Corp., 27 Mass. App. Ct. 721, 727-728 (1989).

Lustily disputed by the parties was whether the door units in fact deviated from what P&F had ordered. Reading the record favorably to P&F, the nonmoving party, see Riley v. Presnell, 409 Mass. 239, 240-241 (1991), there was evidentiary material submitted from which one could infer that P&F had ordered door units fabricated to be installed on 2 by 4 inch stud framing and that what Friend delivered were units fabricated for 2 by 3 inch framing. Friend offered evidentiary material that it delivered what had been ordered and that what it had delivered was fully incorporated in the work. P&F asserted it had incurred costs incident to adjustments required to incorporate the door units into the work, and those costs were the basis for its claim of damages.

Specially manufactured things which are moveable at the time of identification to the contract of sale are “goods” within the meaning of the Uniform Commercial Code. G. L. c. 106, § 2-105(1). When, as occurred in this case, the tender of the goods has been accepted, “the buyer must within a reasonable time after he discovers or should have discovered any breach notify the seller of breach or be barred from any remedy . . . .” G. L. c. 106, § 2-607(3)(a), as inserted by St. 195'.’, c. 765, § 1. Generally, the timeliness of a notice of displeasure with the goods is a question to be determined by the fact finder because whether notice is sufficiently prompt is a function of what was reasonable in the commercial circumstances. Delano Growers’ Coop. Winery v. Supreme Wine Co., 393 Mass. 666, 675 (1985). City Welding & Mfg. Co. v. Gidley-Eschenheimer Corp., 16 Mass. App. Ct. 372, 373 (1983). See also G. L. c. 106, § 1-204(2). There is a category of cases, however, in which courts, on the basis of facts developed in the record, sometimes on summary judgment motions, have decided whether, as matter of law, a buyer has given timely notice of defects in the goods. See Steel & Wire Corp. v. Thyssen Inc., 20 *60 U.C.C. Rep. Serv. (Callaghan) 892, 897-898 (E.D. Mich. 1976); Atlantic Bldg. Sys., Inc. v. Alley Constr. Corp., 32 U.C.C. Rep. Serv. (Callaghan) 1414, 1420-1421 (D. Mass. 1981); Oregon Lumber Co. v. Dwyer Overseas Timber Prod. Co., 280 Or. 437, 444 (1977). See also United Cal. Bank v. Eastern Mountain Sports, Inc., 546 F. Supp. 945, 957-960 (D. Mass. 1982) (dealing with both timeliness and adequacy of notice); M.K. Associates v. Stowell Prod., Inc., 697 F. Supp. 20 (D. Me. 1988). We think this is such a case.

A principal purpose underlying the obligation imposed by § 2-607(3)(a), to make a seller aware within a reasonable time that its goods do not conform, is to prepare the ground for working out a commercial dispute through compromise. See Nugent v. Popular Mkts., Inc., 353 Mass, at 48-49; Atlantic Bldg. Sys., Inc. v. Alley Constr. Corp., supra at 1420; United Cal. Bank v. Eastern Mountain Sports, Inc., supra at 958. It is easier to accept that a claim of breach is in good faith and should be responded to in good faith when the buyer makes the claim soon after the goods arrive, rattier than when the claim is made after payment has become overdue. On this record, the first mention that the door units were in some manner flawed came three and a half months after the goods had been delivered. Section 2-607(3)(a) requires notice within a reasonable time not only of when a buyer discovers any breach but within a reasonable time of when the buyer should have discovered the breach. Although the door units arrived on the job site individually wrapped, those units were susceptible of inspection, including a check of measurements (the wrapping, it will be recalled, was clear plastic). This was not a case where the defect alleged was hidden. Compare Mastercraft Wayside Furniture Co. v. Sightmaster Corp., 332 Mass. 383, 384-387 (1955)(defect in television sets could not be detected until three and one-half months after delivery, when television broadcasting began in the area). Qualities that are apparent, such as size or color, reasonably should be inspected and complained of soon after the goods for a construction job have been delivered to the job site. We hesitate to specify the outer limits of “soon af *61 ter” but think, in the circumstances described, three and one-half months is not soon enough. Compare Fortin v. Ox-Bow Marina, Inc., 408 Mass. 310, 318-319 (1990), in which the court, construing G. L. c. 106, § 2-608, a provision analogous to § 2-607(3)(a), decided revocation four months after acceptance of a boat was timely because the buyer had immediately registered its complaint about the product with the seller.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MORRISON v. AQ TEXTILES LLC
M.D. North Carolina, 2022
Carhartt, Inc. v. Innovative Textiles, Inc.
998 F.3d 739 (Sixth Circuit, 2021)
Bev Smith, Inc. v. Atwell
301 Mich. App. 670 (Michigan Court of Appeals, 2013)
Archstone v. Tocci Building Corp. of New Jersey, Inc.
101 A.D.3d 1057 (Appellate Division of the Supreme Court of New York, 2012)
Smith v. Robertshaw Controls Co.
410 F.3d 29 (First Circuit, 2005)
Novacore Technologies, Inc. v. GST Communications Corp.
20 F. Supp. 2d 169 (D. Massachusetts, 1998)
Besicorp Group, Inc. v. Thermo Electron Corp.
981 F. Supp. 86 (N.D. New York, 1997)
Cameron v. Carelli
653 N.E.2d 595 (Massachusetts Appeals Court, 1995)
J.S.B. Industries, Inc. v. Bakery Machinery Distributors, Inc.
1995 Mass. App. Div. 2 (Mass. Dist. Ct., App. Div., 1995)
Atlantic Pipe Corp. v. R. J. Longo Construction Co.
622 N.E.2d 279 (Massachusetts Appeals Court, 1993)
Baker v. Monga
590 N.E.2d 1162 (Massachusetts Appeals Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
575 N.E.2d 61, 31 Mass. App. Ct. 57, 16 U.C.C. Rep. Serv. 2d (West) 377, 1991 Mass. App. LEXIS 488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-f-construction-corp-v-friend-lumber-corp-of-medford-massappct-1991.