Oxbow Land Holdings, LLC v. ARCO/Murray National Construction Company, Inc.

CourtDistrict Court, D. Montana
DecidedDecember 4, 2024
Docket2:24-cv-00093
StatusUnknown

This text of Oxbow Land Holdings, LLC v. ARCO/Murray National Construction Company, Inc. (Oxbow Land Holdings, LLC v. ARCO/Murray National Construction Company, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Montana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oxbow Land Holdings, LLC v. ARCO/Murray National Construction Company, Inc., (D. Mont. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MONTANA BUTTE DIVISION

OXBOW LAND HOLDINGS, LLC, a

Delaware limited liability company, CV 24-93-BU-JTJ

Plaintiff,

MEMORANDUM

AND ORDER ARCO/MURRAY NATIONAL CONSTRUCTION COMPANY, INC., a Delaware corporation,

Defendant.

I. INTRODUCTION Plaintiff Oxbow Land Holdings, LLC, (Oxbow) has filed a Complaint against ARCO/Murray National Construction, Inc., (ARCO) seeking damages based upon the following causes of action: Count I: Breach of Contract; Count II: Breach of Covenant of Good Faith and Fair Dealing; Count III: Fraud; Count IV: Constructive Fraud; and Count V: Declaratory Judgment. (Doc. 1) The Complaint centers around a Construction Agreement (Agreement) whereby Oxbow contracted with ARCO to construct a large apartment complex in Bozeman, Montana. ARCO filed an Answer and Counterclaim that includes the following counterclaims: Count One: Arbitration; Count Two: Breach of Covenant of Good Faith and Fair Dealing; Count Three: Foreclosure of Lien; Count Four: Unjust Enrichment/Quantum Meruit; and Count Five: Breach of Montana Prompt Pay Act.

(Doc. 6) ARCO filed the present motion to compel arbitration and stay proceedings contending that Section 17.8 of the Agreement requires the parties to engage in

arbitration regarding the Oxbow’s payment obligations to ARCO. (Doc. 8) Oxbow opposes the motion contending the dispute involves the application of the Agreement’s liquidated damages provision (Article 8) and the application and calculation of liquidated damages is not a payment dispute requiring arbitration as

contemplated by the Agreement. (Doc. 11) II. LEGAL STANDARD The Federal Arbitration Act (FAA) governs arbitration agreements related to

interstate commerce. 9 U.S.C. § 2; Southland Corp. v. Keating, 465 U.S. 1, 10-17 (1984); Zigrang v. U.S. Bancorp Piper Jaffray, Inc., 123 P.3d 237 (Mont. 2005). The Montana Uniform Arbitration Act (MUAA) governs arbitration agreements subject to Montana law but not subject to the FAA. Mont. Code Ann. §§ 27-5-111

and 114(1). Under both Acts, a written contract or contract provision by which the parties agree to resolve a future controversy by arbitration is valid and enforceable except upon grounds as exist at law or in equity for the revocation of contracts. 9

U.S.C. § 2; Mont. Code Ann. § 27-5-114(2). In determining the threshold question of whether a dispute is subject to arbitration, state and federal courts distinguish between two types of arbitrability

— substantive arbitrability and procedural arbitrability. John Wiley & Sons, Inc., v. Livingston, 376 U.S. 543, 557-59 (1964). Substantive arbitrability is the gateway question of whether a party agreed to arbitrate a particular dispute or type of

dispute. Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79, 84 (2002). Substantive arbitrability involves two distinct considerations — whether the parties formed a valid and enforceable agreement to arbitrate and whether the terms of the arbitration agreement require arbitration of the particular matter or type of matter

at issue. Id. Except as clearly and unequivocally otherwise provided by contract, the question of whether an issue is substantively arbitrable is a threshold question for judicial determination. Id.

III. DISCUSSION A. Arbitration Oxbow does not dispute that the parties agreed to arbitrate certain matters governed by the Agreement in accordance with the MUAA. Therefore, the only issue

before the Court is whether the Agreement requires arbitration of the claims set forth in Oxbow’s Complaint. ARCO contends that Oxbow’s withholding of liquidated damages, thereby failing to “pay” them for the work they completed, clearly constitutes a dispute subject to arbitration as contemplated by Section 17.8 which provides:

If Contractor believes that Owner has breached Owner’s payment obligations to Contractor under this Agreement, or if any other dispute that this Agreement expressly states may be resolved by arbitration pursuant this Section 17.8, then Owner and Contractor agree that the Claim will be resolved by an individual arbitration conducted in accordance with Montana’s Uniform Arbitration Act (Title 27, Chapter 5 Montana Code) (the “Arbitration Act”); provided that (1) there will be only one arbitrator, (2) any in-person hearings will be held in Bozeman, Montana, (3) parties and witnesses may appear telephonically or by video technology, and (4) the arbitrator’s fees and costs will be shared between Owner and Contractor equally. Unless Owner and Contractor agree on an arbitrator, the arbitrator will be as appointed under the Arbitration Act at the request of either party.

(Doc. 1, Ex. A) (emphasis added)

Oxbow contends that the application and calculation of liquidated damages is subject to Section 8 of the Agreement and that the Owner’s payment obligation is distinct from its contractual right to liquidated damages for ARCO’s failure to timely deliver a Project. (Doc. 11, p. 8) Oxbow contends that a payment dispute is a dispute regarding the “performance of an obligation by the delivery of money or some other valuable thing.” Thus, Oxbow contends, while both arise out of contractual disagreements, liquidated damages and payment disputes address fundamentally different issues: one being stipulated damages for breach, while the other being the timing, sufficiency, or mechanism of payment under the Agreement. (Id.) ARCO counters that Oxbow admits it is withholding payments from ARCO based upon its claim of liquidated damages and that ARCO has filed a counterclaim

demanding payment. (Doc. 14, p. 2). Therefore, ARCO argues that the current dispute does directly concern Oxbow’s payment obligations, which ARCO believes Oxbow has breached by improperly alleging a claim to liquidated damages.

Accordingly, there can be no question the dispute falls within Section 17.8’s arbitration requirement. (Id.) In resolving the question of whether a dispute between the parties is subject

to arbitration pursuant to the terms of an agreement, the Court looks to the following general principles of contract construction: When interpreting a contract according to principles of federal common law, the courts look to “general principles for interpreting contracts.” Under the general principles of contract interpretation, “[c]ontract terms are to be given their ordinary meaning, and when the terms of a contract are clear, the intent of the parties must be ascertained from the contract itself.”

A written contract must be read as a whole and every part interpreted with reference to the whole. Preference must be given to reasonable interpretations as opposed to those that are unreasonable, or that would make the contract illusory. The fact that the parties dispute a contract's meaning does not establish that the contract is ambiguous; it is only ambiguous if reasonable people could find its terms susceptible to more than one interpretation.

Indoor Billboard Northwest Inc. v. M2 Systems Corp., 922 F.Supp.2d 1154, 1161 (D. Or. 2013) (internal citations omitted). Applying these general contract principles to the Agreement, the Court determines whether Section 17.8 requires arbitration turns on whether “[ARCO]

believes that [Oxbow] has breached [Oxbo’s] payment obligations to [ARCO] under this Agreement.” There is no doubt that ARCO holds such a belief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Wiley & Sons, Inc. v. Livingston
376 U.S. 543 (Supreme Court, 1964)
Southland Corp. v. Keating
465 U.S. 1 (Supreme Court, 1984)
Howsam v. Dean Witter Reynolds, Inc.
537 U.S. 79 (Supreme Court, 2002)
Mountain West Farm Bureau Mutual Insurance v. Brewer
2003 MT 98 (Montana Supreme Court, 2003)
Zigrang v. U.S. Bancorp Piper Jaffray, Inc.
2005 MT 282 (Montana Supreme Court, 2005)
Indoor Billboard Northwest Inc. v. M2 Systems Corp.
922 F. Supp. 2d 1154 (D. Oregon, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Oxbow Land Holdings, LLC v. ARCO/Murray National Construction Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/oxbow-land-holdings-llc-v-arcomurray-national-construction-company-inc-mtd-2024.