Owners Insurance Co. v. Jim Carr Homebuilder, LLC

157 So. 3d 148, 2014 WL 1270629, 2014 Ala. LEXIS 44
CourtSupreme Court of Alabama
DecidedMarch 28, 2014
Docket1120764
StatusPublished
Cited by16 cases

This text of 157 So. 3d 148 (Owners Insurance Co. v. Jim Carr Homebuilder, LLC) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Owners Insurance Co. v. Jim Carr Homebuilder, LLC, 157 So. 3d 148, 2014 WL 1270629, 2014 Ala. LEXIS 44 (Ala. 2014).

Opinions

PER CURIAM.

The opinion of September 20, 2018, is withdrawn, and the following is substituted therefor.

Owners Insurance Company (“Owners”) appeals a judgment entered by the Shelby Circuit Court declaring that Owners was obligated to pay an arbitration award entered against Jim Carr Homebuilder, LLC (“JCH”X under the terms of a commercial general-liability (“CGL”) insurance policy Owners had issued JCH. We affirm.

I.

In January 2006, Thomas Johnson and Pat Johnson contracted with JCH, a licensed homebuilder, for the construction of a new house on Lay Lake in Wilson-ville.1 The Johnsons paid approximately $1.2 million for the design and construction of the house and took possession of the substantially finished house in early February 2007. Within a year, the Johnsons noted several problems with the house related to water leaking through the roof, walls, and floors, resulting in water damage to those and other areas of the house. The Johnsons notified JCH of the problems, and JCH apparently made some efforts to remedy them; however, the John-sons were not satisfied with those efforts, and, on May 13, 2008, the Johnsons sued JCH, alleging breach of contract, fraud, and negligence and wantonness.2

The Johnsons’ contract with JCH required JCH to maintain general-liability insurance, and, during the relevant period, JCH held a CGL policy issued by Owners (“the Owners policy”). After receiving notice of the Johnsons’ lawsuit, JCH filed a claim with Owners requesting that it provide a defense and indemnification for the Johnsons’ claims. On July 21, 2008, Owners hired counsel to defend JCH while reserving its right to withdraw the defense if it later determined that the Johnsons’ claims were not covered under the Owners policy. Subsequently, on September 12, 2008, Owners moved the trial court to allow it to intervene in the case for the limited purpose of determining whether there was in fact coverage for the John-sons’ claims.

On December 19, 2008, the trial court issued an order declining to rule on Owners’ motion to intervene at that time but inviting Owners to reapply to intervene at “the appropriate time.” On March 23, 2009, Owners instead filed the instant declaratory-judgment action asking the trial court to determine whether Owners had a duty to defend and indemnify JCH with regard to the Johnsons’ claims. This action was assigned to the same trial judge presiding over the Johnsons’ action against [151]*151JCH, and JCH and the Johnsons thereafter filed separate answers to Owners’ complaint, asserting their own counterclaims and taking the position that Owners was required to defend and indemnify JCH for the Johnsons’ claims.3

During this same time, the Johnsons’ underlying action against JCH proceeded. On July 80, 2008, JCH, through its Owners-provided counsel, moved the trial court to compel arbitration of the Johnsons’ claims pursuant to an arbitration provision in the construction contract entered into by the parties. The trial court granted that motion in the same December 19, 2008, order in which it had declined to grant Owners’ petition to intervene. The Johnsons thereafter moved the trial court to reconsider its order compelling arbitration, and there was thereafter some delay, presumably related to the parties’ reaching an agreement on the mechanics of arbitration. On September 24, 2010, the trial court entered an order noting that the parties had reached an agreement regarding arbitration and staying the case pending completion of the arbitration proceedings. On August 22, 2011, the trial court also stayed the instant case until the underlying case resolving the Johnsons’ claims against JCH was completed.

The Johnsons’ case against JCH proceeded to a final arbitration hearing on March 6, 2012, and, on March 13, 2012, the arbitrator entered an award in favor of the Johnsons in the amount of $600,000 based on the following findings:

“a. That flashing was either not installed or was improperly installed by [JCH’s] subcontractor in certain areas and has subjected other parts of the completed house to leaks, moisture, water intrusion, and damage resulting therefrom;
“b. That the mortar and brick used on the house was not defective, but rather the brick was improperly prepared for installation by [JCH’s] subcontractor, which resulted in excessive absorption of water from the mortar which thereby damaged the completed mortar and requires its replacement;
“c. That the damaged mortar has subjected other parts of the completed house to leaks, moisture, water intrusion, and damage resulting therefrom;
“d. That sufficient weep holes were not installed in the brick or else were covered by mortar by [JCH’s] subcontractor, which has subjected other parts of the completed house to leaks, moisture, water intrusion, and damage resulting therefrom;
“e. That certain windows and doors were not properly installed by [JCH’s] subcontractor and have subjected other parts of the completed house to leaks, moisture, water intrusion, and damage resulting therefrom;
“f. That certain windows and doors either were not caulked or were not properly caulked by [JCH’s] subcontractor, which has subjected other parts of the completed house to leaks, moisture, water intrusion, and damage resulting therefrom;
“g. That the exposed upper porches on the house were not properly installed and waterproofed by [JCH’s] subcontractor, subjecting the completed porch ceilings and areas of the completed dining room to damage from leaks, moisture and water intrusion ...;
[152]*152“h. That part of the roofing was not properly installed by [JCH’s] subcontractor, resulting in a small hole in the attic through which daylight is visible and in water damage to the completed roof decking;
“i. That the completed window sill on the large ‘great room’ window has suffered visible water damage from water leaks;
“j. That certain areas of the completed hardwood floors have suffered visible water damage from water leaks (to quote [JCH’s] expert, even a ‘blind monkey’ could see this);
“k. That a downstairs bathtub was not properly installed by [JCH’s] subcontractor, resulting in leaks and resulting water damage to the completed wood subfloor below .... ”

The arbitrator also found that the John-sons had suffered “significant mental anguish.” The trial court thereafter entered a judgment in the underlying case consistent with the arbitrator’s award. That judgment was not appealed.

On March 14, 2012, the day after the arbitrator returned its award in the underlying case, the Johnsons moved for a summary judgment in Owners’ declaratory-judgment action, asking the trial court to enter a judgment declaring that the Owners policy did in fact cover the award entered against JCH. JCH thereafter filed its own summary-judgment motion seeking the same relief. On April 6, 2012, Owners filed its response to the summary-judgment motions filed by the Johnsons and JCH and simultaneously moved the trial court to enter a summary judgment in its favor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
157 So. 3d 148, 2014 WL 1270629, 2014 Ala. LEXIS 44, Counsel Stack Legal Research, https://law.counselstack.com/opinion/owners-insurance-co-v-jim-carr-homebuilder-llc-ala-2014.