Owen v. Thompson

224 P. 405, 29 N.M. 517
CourtNew Mexico Supreme Court
DecidedFebruary 28, 1924
DocketNo. 2752
StatusPublished
Cited by6 cases

This text of 224 P. 405 (Owen v. Thompson) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Owen v. Thompson, 224 P. 405, 29 N.M. 517 (N.M. 1924).

Opinion

OPINION OP THE COURT.

BRATTON, J.

We shall refer to the parties as plaintiff and defendants, as they were denominated in the court below.

This action was instituted by Robert L. Owen against the Thompson Sheep Company, a copartnership composed of L. E. Thompson, John Gilillour, Juan Er-rasmuspe, Jean Gonzales, and Miguel Nalda, to recover the sum of $10,000, with certain interest thereon, for labor performed by the plaintiff in drilling a certain well upon the premises of the defendants in accordance with a certain written agreement entered into between them on January 28, 1919, by wbicb it was expressly provided that the plaintiff should continue to drill said well, wbicb was then down to about 600 • feet in depth. the price to be paid, according to the terms of said contract, was to be determined by the flow of water obtained. If it tested 5 gallons or more per minute, the price should be $10,000; if 4 gallons or more, and less than 5 gallons, $9,000; if 3 gallons or more, and less than 4 gallons, $8,000; if 2 gallons or more, and less than 3 gallons $7,000; and if l/2 gallons or more, and less than 2 gallons per minute, $5,000. the sums so found to be due was to be settled by a note due November 10, 1923, to be secured by a lien on such well and the premises adjacent thereto. It was further provided that the plaintiff should have until August 31, 1920, within wbicb to perform bis part of the contract, if that length of time was required. And it was further provided that, should the well then in progress fail to produce from l]/2 to 5 gallons of water per minute, the plaintiff should have the privilege of sinking another well or other wells on some other part of the premises belonging to the defendants and situated adjacent to the location of said well then being drilled. Plaintiff charged that he had performed all of the conditions required of him under the terms of such contract; that he continued to drill and sink said well, and that before August 31, 1920, be obtained water which afterwards tested in excéss of 5 gallons per minute; that the defendants failed to perform their part of said contract by failing and refusing to accept said well and execute the note provided in the contract, and had advised the plaintiff they would refuse to execute said note or otherwise pay the plaintiff as required by such contract. Judgment for $10,000, with interest and costs of suit, together with the establishment and foreclosure of a lien upon said well and the adjacent premises was prayed.

The defendants filed a motion to make more definite and certain, wherein they sought to have the court require the plaintiff to make his complaint more definite and. certain, by setting forth, the exact date on which the well in question was completed and ready to be tested with a proper pumping machine; that he state whether or not said well was finished and in condition to be tested on or before August 31, 1920; that he state when and to whom he gave notice that it was complete and ready to be tested, and when the actual test was made. After permitting the plaintiff to amend his complaint by interlineation, this motion was denied. On April 25, 1921, a demurrer was lodged against said amended complaint, upon the grounds that it failed to affirmatively show that the plaintiff had fully performed all of the conditions required of him by said contract, in that it failed to show that said well was completed and produced, or was capable of producing, any quantity of water prior to August 31, 1920, and that it affirmatively appeared from the face of the said complaint that the well was tested subsequent to said date, and that it failed to show that the defendants were notified that said w^ell was completed and ready for a test prior to August 31, 1920. At the same time this demurrer was filed, a motion was interposed, renewing and asking the court to reconsider the motion' to make more definite- and certain. The demurrer and motion were denied by an order duly made on April 25th, and the defendants were ordered to answer the amended complaint on or before May 2d, and the case wras set for trial at the opening of the regular term of court to begin on May 6th; to all of which the defendants duly excepted.

The defendants filed their answer on May 2d, in which they admitted the execution of the contract sued upon and denied the remaining allegations contained in the complaint. They further pleaded that on August 31, 1918, they purchased from the plaintiff certain sheep grazing outfit, and leases upon certain lands situated in Lincoln county, near to and surrounding the location of the well referred to; that they were to and did receive the sheep during January, 1919, and thereby completed their original contract, except tbat portion which referred to the plaintiff completing the well in question, and that they thereupon executed the subsequent agreement, being the one sued upon by the plaintiff; that at all of said times the country surrounding said well was without living water other than that produced from wells, and that the only other source of water for grazing live stock was lakes or tanks which caught and held surface water; that it was unsafe to rely upon such lakes or tanks exclusively, and it was therefore necessary to provide water from wells drilled to a depth of about 800 feet in order to make such ranges safe for grazing live stock and particularly sheep; that the plaintiff did not proceed diligently with drilling said well, but carelessly and negligently proceeded in a desultory manner, abandoning such work for periods of time, and did not complete said well within the time specified, or within any reason - able time thereafter; that he first advised the defendants on October 20, 1920, that he claimed said well was completed; that in the meantime the drought existing in said country became so acute that it was necessary for the defendants to, and they did, purchase a half interest in another well in order to provide water for their herds of sheep.

By way of counterclaim, the defendants pleaded most of the facts hereinbefore set forth, and further that, in order to induce the defendants to enter into the original contract for the purchase of said ranch and sheep, the plaintiff told and represented to them that he controlled the entire range in question; that no other persons had water thereon which would enable them to use such range for grazing purposes, and'that, if defendants purchased said lands and water, together with the well then being drilled, they would secure control of all of such range; that such statements and representations were false and were known by the plaintiff to be so; that at said time there was another well owned by other persons in the midst of said range, known as the Waller and Billings well, which would give to the owners thereof equal rights with 'defendants to graze thereon; that the defendants did not know of such facts, but relied and acted upon the false and fraudulent representations of the plaintiff. They prayed damages in the sum of $14,000.

On May 2d, at 'the time said answer was filed, the defendants filed an unverified motion to vacate the previous order setting the case for trial on May 6th, and to continue the case for the term. Several grounds were put forward in such motion. These were that the case was not at issue upon the affirmative matters and counterclaims set forth by the defendants; that the defendants L. E.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brink v. Hayes Branch Drainage District
376 N.E.2d 78 (Appellate Court of Illinois, 1978)
Rudy v. Newman
220 P.2d 489 (New Mexico Supreme Court, 1950)
State v. Gallegos
129 P.2d 634 (New Mexico Supreme Court, 1942)
Owen's Estate v. Prichard
281 P. 463 (New Mexico Supreme Court, 1929)
Baca v. Board of Com'rs of Socorro County
231 P. 637 (New Mexico Supreme Court, 1924)
Brown v. Heller
227 P. 594 (New Mexico Supreme Court, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
224 P. 405, 29 N.M. 517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/owen-v-thompson-nm-1924.