Overby v. Barnett

262 A.2d 604, 1970 D.C. App. LEXIS 231
CourtDistrict of Columbia Court of Appeals
DecidedMarch 6, 1970
DocketNo. 4900
StatusPublished
Cited by3 cases

This text of 262 A.2d 604 (Overby v. Barnett) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Overby v. Barnett, 262 A.2d 604, 1970 D.C. App. LEXIS 231 (D.C. 1970).

Opinion

NEBEKER, Associate Judge.

This breach of contract action was dismissed, sua sponte, by the trial court on the third day of trial.1 The action arose from a dispute over the adequacy of performance of a contract for construction of a residence in the District of Columbia. The builder-appellee filed the complaint asserting incomplete payment by the owners-appellants. The owners filed an answer and counterclaim asserting improper construction by the builder and damages resulting from depreciation and the necessity to make repairs. The builder denied the material allegations in the counterclaim by timely reply.

The written contract was on a form, consisting of four pages, bearing a lengthy copyright by the American Institute of Architects. Article 19 thereof contained a standard arbitration clause whereby "any disagreements” shall be submitted to arbitration under predetermined procedure of A.I.A. or the American Arbitration Association.

At the close of the second day of trial, the judge requested that the parties submit their views on the question whether the court had jurisdiction of the case in light of the arbitration provision. The builder [605]*605maintained that the provision did not apply to his suit for a fixed sum of money. The owners asserted that all rights under the provision were waived by the parties since the builder had brought suit and none of the pleadings asserted the right to arbitration as a condition precedent to litigation. The trial judge dismissed the action for want of jurisdiction and this appeal followed. We reverse and remand for a new trial. ...

We have held, consistent with established precedent,2 that a contractor’s right to arbitration of a dispute may be and is waived by answering the complaint on the merits and counterclaiming for damages. Rubewa Products Co. v. Watson’s Quality Turkey Products, Inc., D.C. App., 242 A.2d 609 (1968). These acts, amounting to active participation in a law suit,3 are inconsistent with the right to arbitrate and constitute a waiver of the right. Here the builder and the owners, through their pleadings, have clearly waived the arbitration provision by submitting the issues to a jury trial. Neither desired to use arbitration to settle their dispute and it was error to force them to do so.4

It is particularly unfortunate that the parties are forced to undergo the expense of a new trial when the case could have been submitted for jury determination. Our earlier admonition respecting the grant of a directed verdict5 applies with equal force in this case. The better practice would have been to submit the case to the jury and then, if deemed appropriate, the trial judge could rule on the effect of the arbitration clause. “Action by this court in the event of an appeal from such a judgment would not entail the trouble and expense of a new trial.” Peigh v. Baltimore & Ohio R.R., 92 U.S.App.D.C. 198, 202, 204 F.2d 391, 396, 44 A.L.R.2d 671 (1953). See also Todd v. Jackson, 109 U.S.App.D.C. 7, 283 F.2d 371 (1960).

Reversed and remanded for a new trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charlton v. MOND
987 A.2d 436 (District of Columbia Court of Appeals, 2010)
Brandon v. Hines
439 A.2d 496 (District of Columbia Court of Appeals, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
262 A.2d 604, 1970 D.C. App. LEXIS 231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/overby-v-barnett-dc-1970.