Otto Haug, T/a Southeastern Floor Company v. Gersten Construction Company, Cross-Claimant and Third-Party-Plaintiff v. United States Fidelity and Guaranty Company, Third-Party-Defendant and Cross-Claimant

289 F.2d 616, 1961 U.S. App. LEXIS 4555
CourtCourt of Appeals for the Third Circuit
DecidedMay 9, 1961
Docket8290
StatusPublished

This text of 289 F.2d 616 (Otto Haug, T/a Southeastern Floor Company v. Gersten Construction Company, Cross-Claimant and Third-Party-Plaintiff v. United States Fidelity and Guaranty Company, Third-Party-Defendant and Cross-Claimant) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Otto Haug, T/a Southeastern Floor Company v. Gersten Construction Company, Cross-Claimant and Third-Party-Plaintiff v. United States Fidelity and Guaranty Company, Third-Party-Defendant and Cross-Claimant, 289 F.2d 616, 1961 U.S. App. LEXIS 4555 (3d Cir. 1961).

Opinion

289 F.2d 616

Otto HAUG, T/A Southeastern Floor Company, Plaintiff, Appellee,
v.
GERSTEN CONSTRUCTION COMPANY, Defendant, Cross-Claimant and Third-Party-Plaintiff, Appellant,
v.
UNITED STATES FIDELITY AND GUARANTY COMPANY, Third-Party-Defendant and Cross-Claimant, Appellee.

No. 8290.

United States Court of Appeals Fourth Circuit.

Argued April 4, 1961.

Decided May 9, 1961.

Jacob Shearer, Beverly Hills, Cal., and John Thorpe Richards, Alexandria, Va. (Clarke, Richard, Moncure & Whitehead, Alexandria, Va., Shearer & Fields, Beverly Hills, Cal., and Bernard Shearer, Beverly Hills, Cal., on brief), for defendant-appellant, Gersten Construction Co.

Benj. W. Dulany, Washington, D. C. (Douglas, Obear & Campbell, Washington, D. C., on brief), for plaintiff-appellee, Otto Haug.

Jackson, Gray & Jackson, and John W. Jackson, Washington, D. C., on brief for third-party defendant-appellee, U. S. Fidelity and Guaranty Co.

Before SOPER and HAYNSWORTH, Circuit Judges, and HARRY E. WATKINS, District Judge.

HARRY E. WATKINS, District Judge.

This is an appeal from a judgment on a jury verdict in a contract action brought by Appellee Otto Haug, as a flooring subcontractor, against Appellant Gersten Construction Company, the general contractor, for breach of the flooring subcontract. Gersten's answer alleged that Haug had failed to comply with the terms of the subcontract and that the termination was therefore proper under the subcontract. Gersten also counter-claimed for damages suffered in recontracting the job. Gersten, in connection with the counterclaim, named Appellee United States Fidelity and Guaranty Company as a cross-defendant as surety on Haug's obligation. The jury awarded Haug $40,000 and judgment was entered on the verdict. After denial of its motions to set aside the verdict and for a new trial, Gersten effected this appeal.

The only question before this court on appeal is whether it was proper for the trial judge to submit to the jury the issue of whether Haug agreed to a work schedule furnished by Gersten. Gersten contends that a reasonable person must conclude from the evidence that Haug did so agree and that the court should not have submitted this issue to the jury. We disagree with this contention, and hold that the issue of agreement was properly submitted to the jury.

Gersten is a California corporation engaged in the general contracting business. Gersten entered into a contract with the Department of the Army for the construction of 309 duplex houses containing 618 apartment units in the vicinity of Fort Belvoir, Virginia. Pursuant to this contract, Gersten, on August 8, 1958, entered into a subcontract with Haug, doing business as Southeastern Floors, under which Haug agreed to install the flooring in the houses for a price of $248,000.

The record shows that some difficulties were experienced between the general contractor and the subcontractor from the time of inception of work under the contract. Issues arose as to whether baseboards should be installed prior to the flooring, whether weather stripping, front and back stoops, sidewalks, and grading should be completed prior to the flooring installation, and whether the flooring work was progressing at the proper speed. The mutual dissatisfaction of the parties (Gersten because of what it considered lack of satisfactory progress, and Haug because of purported onerous requirements of performance) led to a meeting between the two parties on May 27, 1959. It was at this meeting that the work schedule was discussed, and either imposed by Gersten or agreed to by Haug. Haug concedes that the schedule was never complied with.

On June 23, 1959, the contract was terminated by Gersten, seven reasons being listed in the termination letter. The only reason material here is "Failure to make progress required and failure to comply with time schedules provided for plaintiff's performance." Thus, if it could be found as a matter of law that Haug agreed to the work schedule, his failure to comply with the schedule would be a breach of contract, justifying Gersten in writing the letter of termination.

The trial judge instructed the jury that they must determine whether the work schedule was reasonable or arbitrary, and that if Haug voluntarily agreed to it, this would be conclusive evidence of the reasonableness of the schedule. Thus, the issue of agreement was left to the jury.

It would appear from the record that Gersten relied at the trial upon the theory that the written contract provided that any work schedule required by Gersten was binding on Haug. Consequently, very little was said by anyone about any separate and subsequent oral agreement by Haug that he would comply with such work schedule. The counterclaim of Gersten avers that "plaintiff failed to make the progress required of the plaintiff by the defendant and further that plaintiff failed to comply with the time schedule provided for the plaintiff's performance." (Emphasis added.) Nothing is said about any subsequent oral agreement.

Counsel for appellant, in his opening statement to the trial court, stated that Gersten gave Haug "written directions to proceed with doing so many buildings per day * * *," and that "He never approached the four or six (houses per day) which was required of him * * *." (Emphasis added.)

Most of the evidence at the trial related to the terms of the work schedule "required" of Haug in the written contract, and whether such terms were reasonable. The reasonableness of such required work schedule was appropriately submitted to the jury under proper instructions. Upon appeal Gersten now concedes that there was sufficient evidence to go to the jury as to the reasonableness of the work schedule and all other issues, except the single issue as to whether Haug agreed to the work schedule.

Appellant Gersten relies for reversal upon the testimony of John F. Keogan, project manager for Gersten, because no other witness mentions any such agreement. His testimony relates to the meeting of the two parties on May 27, 1959, and a letter sent by him to Haug on May 28, 1959. The pertinent part of the letter is as follows:

"Gentlemen:

"As a result of our meeting Thursday, May 28, we list the following: * * *

"Number Three. As per our conversation we expect, starting Monday, June 1st, that you will install floors at the rate of four (4) buildings per day and will build this installation to six (6) buildings per day by Friday, June 5th."

Due to the importance attached to Keogan's testimony by appellant, it may be well to set out his testimony relating to the meeting and letter:

"Q. Now do you recall any conversations at that meeting with regard to the schedule? A. Yes. The conversation set up that we were not getting enough production and all of our problems were brought to the Southeastern's attention. And at that time a promise was made verbally, as it had been on previous occasions, that they would step up their production.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haug v. Gersten Construction Co.
289 F.2d 616 (Fourth Circuit, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
289 F.2d 616, 1961 U.S. App. LEXIS 4555, Counsel Stack Legal Research, https://law.counselstack.com/opinion/otto-haug-ta-southeastern-floor-company-v-gersten-construction-company-ca3-1961.