Otis Eastern Service, Inc. v. Raytheon Engineers & Constructors, Inc.

15 F. Supp. 2d 318, 1998 U.S. Dist. LEXIS 20617, 1998 WL 695017
CourtDistrict Court, W.D. New York
DecidedJuly 30, 1998
Docket6:98-cv-06019
StatusPublished
Cited by1 cases

This text of 15 F. Supp. 2d 318 (Otis Eastern Service, Inc. v. Raytheon Engineers & Constructors, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Otis Eastern Service, Inc. v. Raytheon Engineers & Constructors, Inc., 15 F. Supp. 2d 318, 1998 U.S. Dist. LEXIS 20617, 1998 WL 695017 (W.D.N.Y. 1998).

Opinion

DECISION AND ORDER

SIRAGUSA, District Judge.

This is a diversity action in which the plaintiff is suing to collect monies allegedly owed under a construction subcontract. Before the Court is a motion by the plaintiff for partial summary judgment. For the reasons stated below, this application is denied.

BACKGROUND

This action involves a dispute between a general contractor and a subcontractor on a project to construct a natural gas storage facility near Avoca, New York. On or about May 7, 1996, the parties entered into a subcontract agreement which required the plaintiff, as subcontractor, to install a gas pipeline at the aforesaid gas storage facility. The subcontract agreement consists of a primary agreement and eighteen other “subcontract documents.” The total amount due to the plaintiff upon completion of the project was to be 2.5 million dollars 1 , with the defendant agreeing “to make monthly progress payments on account hereof as provided in Article 10 of the Subcontract General Conditions.” That article states in relevant part:

INVOICING AND PAYMENT
Unless otherwise stated in the Agreement, Subcontractor shall:
10.1 Submit a monthly invoice by the third working day of the month covering progress on the Work during the previous calendar month, subject to approval by Contractor.
10.2 Be paid ninety (90%) of the approved amount of the monthly invoice within thirty (30) days of Contractor’s receipt of payment therefore. The remaining ten percent (10%) of each approved monthly invoice shall be withheld as re-tainage and paid to Subcontractor within thirty (30) days of Contractor’s receipt of final payment from Owner less funds withheld by Owner, if any. (Emphasis added).

To effectuate this provision, the plaintiff submitted to the defendant a detailed price breakdown setting forth a schedule of the amounts it would charge the defendant for each particular task to be performed. The defendant then agreed to make progress payments based on the scheduled amounts set forth in the price breakdown and the percentage of work completed as reported by the plaintiff in its invoices. Pursuant to Article 10.2 above, these progress payments were to be for ninety percent of the invoice amount, with the defendant holding back ten percent of each invoice amount as retainage.

The subcontract also contains the following provisions:

Article 8, Waiver of Liens
SUBCONTRACTOR, for itself, its lower-tier subcontractors, materialmen, laborers, and for all other persons performing any labor or furnishing any services, labor or materials for any of the work covered by this SUBCONTRACT, hereby waives, to the full extent permitted by law, all right to have filed or maintained any mechanics’ or other liens or claims for or on account of the services, labor or materials to be furnished hereunder.
SUBCONTRACTOR (1) shall indemnify, and save harmless OWNER (and it’s Partners, Plant Operator, etc.) and CONTRACTOR (and their employees) from all laborers’, materialmen’s, and mechanics’ liens upon the real property upon which the Work is located arising out of the services and materials furnished by SUBCONTRACTOR, its lower tier subcontrac *320 tors and others in connection with the Work, and (2) shall keep said property free and clear of all liens, claims, and encumbrances arising from the performance of this SUBCONTRACT by SUBCONTRACTOR, its lower tier subcontractors and others.
Final payment will not be made by CONTRACTOR until a properly executed SUBCONTRACTOR’S Release and Certificate, Form 4-003 has been received by CONTRACTOR., Said form should accompany the final invoice to ensure no delay in payment to SUBCONTRACTOR.

(Emphasis added). 2 This Subcontractor’s Release and Certificate form, Form 4003, was attached to and incorporated into the subcontract agreement. Although the contract provision relating to this release form is found under the heading “Waiver of Liens,” the actual release pertains to much more than the release of any liens. The release form states that the subcontractor acknowledges that the contractor has fully performed and complied with the agreement, and that the subcontractor

[f]orever releases and discharges the Owner and Contractor of and from all claims, demands or causes of action, suits, debts, liabilities, controversies, damages and demands, whether in law or equity, contract or tort, which the Subcontractor, its successors and assigns, may now or hereafter have by reason of any matter, causes or thing whatsoever against the Owner or Contractor, their successors, or assigns, including, but not limited to. any and all claims and demands arising out of the Contract, or any changes therein or amendments thereto, or otherwise, in connection therewith.

In short, the release operates to release the Contractor and Owner not just from liability, for liens, but from any and all liability they may have to the subcontractor.

The subcontract agreement further states, in relevant part:

DEFAULT, TERMINATION, AND SUSPENSION
* * * * H: *
13.5 Contractor shall have the night to suspend the Work upon advance, written notice to Subcontractor In the event of suspension: ... The duration of any such suspension shall not exceed one (1) year.

On or about May 7, 1996, the plaintiff began work on the gas pipeline. By letter dated August 9,1996, the defendant informed the plaintiff that it was “temporarily suspending all project Work at the close of business on Friday, August 09, 1996.” As of August 9, 1996, pursuant to Article 10 of the Subcontract General Conditions, the plaintiff had already sent three invoices to the defendant which the defendant paid, less the ten percent retainage. After work on the project was suspended, the plaintiff sent another invoice to the defendant, dated August 23, 1996. The defendant approved and paid this invoice, less the ten percent retainage. Then on January 13, 1997, the parties met to discuss further payments. Following that meeting, the plaintiff submitted its fifth invoice, dated January 15, 1997. The defendant approved and paid this invoice, less the ten percent retainage. It is undisputed that the total amount retained from the five invoices is $148,993.73. To date, the defendant has not paid any of this retained amount to the plaintiff.

Following payment of the fifth invoice, the plaintiff demanded payment from the defendant for additional amounts allegedly owed under the contract. The plaintiff alleges that it systematically understated the amount of work it had completed on the earlier five invoices at the insistence of the defendant, as a condition of being paid. The plaintiff contends that both sides were aware that the invoices were not accurate, and that because the defendant would not agree to pay the full amounts claimed to be due, the plaintiff submitted invoices for the amounts that the defendant would agree to pay at that time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J & K Plumbing & Heating Co. v. Lane
13 A.D.3d 856 (Appellate Division of the Supreme Court of New York, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
15 F. Supp. 2d 318, 1998 U.S. Dist. LEXIS 20617, 1998 WL 695017, Counsel Stack Legal Research, https://law.counselstack.com/opinion/otis-eastern-service-inc-v-raytheon-engineers-constructors-inc-nywd-1998.