Ortmeyer Lumber Co. v. Central Surety & Insurance

98 P.2d 97, 151 Kan. 226, 1940 Kan. LEXIS 95
CourtSupreme Court of Kansas
DecidedJanuary 27, 1940
DocketNo. 34,528
StatusPublished
Cited by2 cases

This text of 98 P.2d 97 (Ortmeyer Lumber Co. v. Central Surety & Insurance) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ortmeyer Lumber Co. v. Central Surety & Insurance, 98 P.2d 97, 151 Kan. 226, 1940 Kan. LEXIS 95 (kan 1940).

Opinions

The opinion of the court was delivered by

Allen, J.;

This was an action by a lumber company to recover from a contractor and the surety on his bond for materials furnished in the construction of a schoolhouse. Plaintiff sued for the balance due on the contract, $1,777.50, plus interest and costs. The court rendered judgment against the contractor, Carpenter, for $1,833.80 and against the surety company for $633.80 — the total recovery against both defendants not to exceed $1,833.80. From this judgment plaintiff appealed and the defendants have filed a cross-appeal.

On June 14, 1937, the defendant, Carpenter, entered into a contract for the construction of a school building at a stipulated contract price of .$18,135. The contractor, with the defendant surety company as surety, executed a bond to the state of Kansas for the [227]*227benefit of the persons entitled thereto in the sum of $18,135, the condition of the obligation being that if the contractor should well and truly pay all indebtedness incurred for supplies, materials, or labor furnished or consumed in connection with the construction of the public building in question, then the obligation was to be null and void, otherwise in full force and effect.

In the answer of the defendant, Carpenter, it was alleged that under the agreement between the plaintiff and Carpenter the plaintiff was to assist Carpenter to secure the job by making up the bid for the contract, and would back him with money to carry on the job and protect him against loss, that defendant was to buy all lumber and material from plaintiff, that plaintiff was to have the profits from the lumber, and the defendant Carpenter was to have the profits from the labor and work and the usual contractor’s profits.

The defendant surety company in its answer stated:

“Further answering herein this defendant adopts and makes a part of its answer herein the answer of its eodefendant, C. F. Carpenter, as fully as though said allegations were set out in this answer and alleges that by reason of facts therein set out this plaintiff was a partner or joint adventurer of the said Carpenter and under the facts therein states this defendant is not liable to the said plaintiff.
“Plaintiff further says that on the letting of said contract to the said Carpenter a surety bond was required of the said defendant Carpenter and he applied to the agents of this defendant, the Long-Sherman Agency in the city of Hutchinson to furnish such bond. That the said agent informed said Carpenter that his financial statement did not show sufficient assets to enable the defendant, Carpenter, to carry on said work and take care' of any loss or shortage which might be on said job, and that on such showing it would be impossible to write the bond in the amount required, and thereupon the said Carpenter informed said agent that the plaintiff herein was interested in said contract and would stand back of him to enable him to carry out and complete said contract. That the said agent of this defendant went with the said Carpenter to the office of the said plaintiff and informed the general manager thereof, J. L. Powell, that the defendant could not write the bond as the said Carpenter did not ha-ve sufficient assets to carry on said contract and protect against any possible loss therein and thereupon the said J. L. Powell informed the said agent that they were backing Carpenter and would see him through. That they were willing to place to his credit a sufficient sum to enable him to carry on with said contract and to protect him against any loss on the bond that Carpenter was required to give, and after some discussion it was agreed that the sum of $1,200 would be a sufficient amount. That the said agent required that some written statement be made so that he would know that the bank would advance said amount on demand, and the said plaintiff executed and delivered to this defendant for use to the Central State Bank [228]*228a written statement, a copy of which is hereto attached, marked “exhibit A,” and made a part hereof. That it was agreed and understood that said credit was to be available to the said Carpenter during all of said time to pay said bills and protect this defendant against any loss on said bond.
“That thereupon and on the strength of the said agreement to stand back of the said Carpenter and the furnishing of said amount of credit to the said Carpenter, this defendant executed said bond.
“Defendant further alleges that the said bank did furnish certain credit to the said Carpenter on notes signed by the said Carpenter and said plaintiff and that the said Carpenter by the direction of said plaintiff used the money paid to him by said school district to pay said notes instead of paying debts that might become a liability on said bond.”

It was alleged that by reason of the premises that as between the defendant surety company and the plaintiff, the plaintiff is primarily liable for any unpaid debt incurred by Carpenter in the performance of his contract.

The plaintiff lumber company owned five yards, the main office being at Wichita. Powell was the manager of the Hutchinson yard. A school district in Reno county advertised for bids for a new schoolhouse. The defendant Carpenter entered into a verbal agreement with Powell to buy the lumber and other building materials from the plaintiff company, if Powell would assist Carpenter in getting the contract. Employees of the lumber company assisted him in figuring the estimates upon which his bid was based, secured a check of $1,000 to accompany the bid, and Carpenter, being the low bidder at the letting, was awarded the contract. Before the contract could be entered into it was necessary that Carpenter furnish faithful performance and statutory lien bonds for its completion. The plaintiff had arranged a credit of $500 at the bank for Carpenter. The circumstances under which the bond was executed by the surety company is shown by the following excerpts from the testimony.

Long, local agent for the defendant surety company, testified:

“A. Down at Mr. Powell’s office, I told Mr. Powell that $500 wouldn’t be enough to bond this job, and he said, ‘What do we need to get a bond written on it?’ I said, ‘You will need at least $1,200:
“I told Powell $500 cash in the bank would not be enough to write a bond on Carpenter for this job.
“Q. Did Mr. Powell make any statement to you about backing Mr. Carpenter or he was going to see him through or anything of the kind, in your presence? A. No, sir.
“Q. What did you tell him? A. I told him it would be necessary to file [229]*229a line of credit giving the firm of the Carpenter Construction Company the necessary working capital to enable them to get their operations started.”

Powell, local agent for plaintiff, testified:

“Long said at that time that he did not think that the bond could be .written with just $500 shown as working capital; that he did not believe that the bonding company would feel that this big an operation could be commenced, started and then go along with -(¡hat amount of capital, and that that would be an insufficient amount — and Long said that he thought if it could be arranged whereby Carpenter could have $1,200, that he felt sure the bonding company would go ahead and bond him for the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stevens v. Farmers Elevator Mutual Insurance
415 P.2d 236 (Supreme Court of Kansas, 1966)
State ex rel. Hedrick v. Hartford Accident & Indemnity Co.
114 P.2d 812 (Supreme Court of Kansas, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
98 P.2d 97, 151 Kan. 226, 1940 Kan. LEXIS 95, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ortmeyer-lumber-co-v-central-surety-insurance-kan-1940.