Ortego v. Caldwell

87 So. 2d 124, 229 La. 907, 1956 La. LEXIS 1366
CourtSupreme Court of Louisiana
DecidedMarch 26, 1956
DocketNo. 42275
StatusPublished
Cited by2 cases

This text of 87 So. 2d 124 (Ortego v. Caldwell) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ortego v. Caldwell, 87 So. 2d 124, 229 La. 907, 1956 La. LEXIS 1366 (La. 1956).

Opinion

FOURNET, Chief Justice.

We granted certiorari to review the judgment of the Court of Appeal, First Circuit, reversing the district court’s judgment and dismissing the suit of plaintiffs Laurent R. Lafleur and LeRoy Ortego to recover for damage to their crops and to the land belonging to the former by water which flooded the property because of the alleged failure of defendant to construct a levee on plaintiff’s property in accordance with his contract with the Louisiana Highway Commission to rebuild a public road bordering the said property. See La.App., 77 So.2d 151.

The record discloses that plaintiff Lafleur’s property, situated in Evangeline Parish, abuts La. Highway 119, formerly a narrow gravel road with a levee alongside, the said levee having been in existence for some sixty years and having served to prevent the water in ditches along side the highway from flooding plaintiff’s fields — presently used for the growing of cotton, potatoes, etc., with the plaintiff Ortego as a tenant on a share crop basis. A project, to be undertaken in 1952, was the blacktopping of the highway, and in order to broaden the existing road it was necessary to take in that portion of the land adjoining the highway on which the levee stood. The contract for the road construction was awarded by the Department of Highways to the defendant, E. A. Caldwell; it provided for replacement of the levee by another, to be constructed within Lafleur’s fence, and contained a special provision that the owner was to be satisfied. The levee was constructed between January 2 and January 20, 1952, and with the spring rains many breaks developed. Repairs were made by the defendant but other soft spots gave way, water broke through the levee and spread over the fields with resulting crop loss and damage to top soil — the most serious damage having taken place in May, 1952; this suit followed.

The trial judge, in a well consideied opinion, observing that while there were no specifications covering the construction of the levee on plaintiff’s property other than that the old levee was to be replaced by a single line rice levee1 parallel to the road but inside the landowner’s fence, he found after hearing all the evidence in the case that there was a provision in the contract that the levee was to be of the same efficiency and strength as the old levee and to the satisfaction of the landowner, and concluded that it was [911]*911very obvious that the new levee did not meet those requirements. The loose dirt used to construct the levee had simply been graded, without being packed or staked or otherwise made sufficiently firm and strong to withstand the pressure of water from the highway ditches; and that consequently the contractor was liable for the resulting damages, which he found to be $283.32 and $266.68, respectively, for Lafleur and Ortego, with legal interest from judicial demand.

The Court of Appeal, in reversing the judgment of the District Court, did not seriously consider plaintiffs’ contention that the contract contained a stipulation pour autrui, it being the court’s opinion that, assuming such a contention to be valid, under the holding of the Court of Appeal, Parish of Orleans, in Schott v. Ingargolia, La.App., 180 So. 462, 463,2 inasmuch as the construction of the levee had been completed and accepted by the Department of Highways on January 20, 1952, for which work defendant had been paid in full, he, the defendant contractor, was absolved of liability for faulty construction not only as to the department but as to any third persons who would have benefited under the stipulations of the contract. In so holding the court maintained the contention of counsel for the defendant, which had been considered and rejected by the trial judge whose opinion it was that the rule governing the Schott case is inapplicable to the factual situation here presented.

We agree with the trial judge that the rule applied in Schott v. Ingargolia, under the facts of this case, is inapplicable. The Court of Appeal fell into the error of concluding that the levee work had been accepted and paid for on the 20th of January, 1952, because of the Tact that on that date a payment was made to the defendant contractor, and the levee work had been performed during the previous 18 days, which were covered by the payment; but the Court failed to take into consideration that on the 20th of each month during the progress of the work, the contractor was paid a sum, representing partial payment of his rough estimate of the cost of work done during the 30 day period, with retention by the Department of Highways of 10% of such estimate for use, if necessary, in correctional work. The levee was constructed in the very beginning of the work on the project, when workmen were just starting the dirt work for the highway, after the fences had been moved, and necessarily it cannot be said that Caldwell’s work was approved until the final acceptance of the project covered by the contract — which [913]*913could not have taken place before November of 1952 because construction of the highway, according to the record, was not completed until that time. Although the defendant contractor denies that there was any complaint made to him about the unsatisfactory construction of the levee by the landowner Lafleur or by anyone on his behalf, it is nevertheless clear that Lafleur’s acceptance or approval of the work was never sought and it is equally clear that after each break occurring during this period of construction repairs were undertaken by the defendant contractor but the levee never served its purpose until it was repaired and properly packed by the landowner.

A perusal of the record reveals that the Department of Highways, in order to obtain the necessary width required to reconstruct Highway No. 119, had to acquire property from abutting owners, including the plaintiff Lafleur — who agreed to relinquish a strip along the highway and in exchange received the promise that the levee would be rebuilt to protect crops and his land from highway drainage; and in the contract for the construction of the highway, it was stipulated between the Department of Highways and the defendant Caldwell that the latter would replace the old levee to the satisfaction of the owner. Not only was such an agreement binding on the defendant Caldwell, but it could not have been revoked once Lafleur availed himself of the advantages stipulated in his favor, LSA-Civil Code, Article 1890 ;3 and consequently Lafleur and his tenant, for whose benefit the stipulation in the contract was made, have an equitable action 4 against the defendant-obligor for the damages suffered as a result of his faulty performance of his obligation, LSA-Civil Code, Articles 1930 and 2769.5

For the reasons assigned the judgment of the Court of Appeal is annulled and set aside and the judgment of the District Court is affirmed, defendant to pay all costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kendrick v. Mason
99 So. 2d 108 (Supreme Court of Louisiana, 1958)
King v. Mason
95 So. 2d 705 (Louisiana Court of Appeal, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
87 So. 2d 124, 229 La. 907, 1956 La. LEXIS 1366, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ortego-v-caldwell-la-1956.