Orr v. United States

486 F.2d 270, 1973 U.S. App. LEXIS 7885
CourtCourt of Appeals for the Third Circuit
DecidedSeptember 14, 1973
Docket72-3229
StatusPublished

This text of 486 F.2d 270 (Orr v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orr v. United States, 486 F.2d 270, 1973 U.S. App. LEXIS 7885 (3d Cir. 1973).

Opinion

486 F.2d 270

George ORR, Plaintiff-Appellant-Cross Appellee,
v.
UNITED STATES of America, Defendant-Third-Party
Plaintiff-Appellee-Cross Appellant, Meador
Contracting Company, Inc., Third-Party Defendant.

No. 72-3229.

United States Court of Appeals,
Fifth Circuit.

Sept. 14, 1973.

David R. Lewis, Jacksonville, Fla., William M. Ford, Alexandria, La., for George Orr.

Richard L. Robison, Orlando, Fla., for Meador Contr. Co., Inc.

John L. Briggs, U. S. Atty., Robert A. leventhal, Asst. U. S. Atty., Jacksonville, Fla., James P. Klapps, Trial Atty., Ronald R. Glancz, Morton Hollander, Walter Fleischer, Greer S. Goldman, James C. Hair, Jr., Dept. of Justice, Washington, D. C., for the United States.

Before WISDOM, GEWIN and CLARK, Circuit Judges.

WISDOM, Circuit Judge:

George Orr was severely injured while working on electrical power lines on a federal installation in Florida. He brought suit against the United States under the Federal Tort Claims Act, 28 U.S.C. Secs. 2671-2680, and the Government in turn filed a third party claim against the contractor and the subcontractor, Orr's employer. After a nonjury trial, the district court found that Orr's injuries were the result of the combined negligence of the Government, Orr, and the subcontractor: the Government was 30-percent responsible, and Orr and the subcontractor were each 35-percent responsible. Apportioning damages under the comparative negligence standard of Florida's Hazardous Occupations Statute, Fla.Stat.Ann. Secs. 769.01-769.05, the court ordered the Government to pay Orr damages representing 30 percent of the total. From this judgment both Orr and the United States appeal. We affirm.

* On February 5, 1968, the United States entered into a construction contract with Meador Contracting Company, Inc. (Meador I) for the replacement of an overhead electrical circuit at Patrick Air Force Base, Florida. That same day Meador I subcontracted for the performance of the contract with Meador Contracting Company of Louisiana, Inc. (Meador II). The work, to be performed in compliance with Government safety requirements and subject to inspection and supervision by Government personnel,1 involved the replacement of a "critical circuit" carrying electricity generated by the Government and distributed throughout the Base. The Government generated its own electricity because some of its equipment, such as radar, was too sensitive to endure the fluctuations of commercially supplied electricity. For other Base needs, the Government purchased current from the Florida Power & Light Company.

* * *

By early July 1968 the work required under the contract had been substantially completed, and preparations were made to splice the new circuit into the remaining lines. Employees of Meador II arranged with a Mr. Bell, the Government inspector responsible for supervising Meador's performance, to cut the flow of current on the lines to be worked on. This "outage" was accomplished on Saturday and Sunday, July 13 and 14. Orr testified that on July 13 he overheard Bell advise another Meador employee that "the line was dead."

Orr ascended pole 14 on Sunday, July 14. He was not an experienced lineman.2 For example, he neither "buzzed" the lines, to find out if they were "hot", nor employed safety equipment, such as rubber gloves or a rubber blanket. Indeed, he took no precautions at all against the possibility that one of the lines was energized.

Pole 14 held a number of wires. The top wire carried 13,000 volts purchased by the Government from the Florida Power & Light Company and distributed through Government lines on Government poles. A fellow employee had advised Orr that this line was hot. Beneath the hot wire were the critical circuit lines on which Orr was to work; these lines were not energized. Closest to the ground were other lines which Orr assumed were also dead. These lines, however, were connected to the top wire by "stringers" or "jumpers", and thus current flowed from the top to the bottom wires. Consequently, the bottom wires were energized. When he climbed the pole, Orr came into contact with one of these energized lower wires and suffered severe injuries. As a result of the accident, Orr lost both legs and a substantial portion of his vision.

Before filing this action, Orr settled a suit brought in state court against Meador I, Meador II, certain of their officers, and their insurance carriers. For $52,0003 Orr released the defendants in that suit from any further liability for claims arising from his accident, and he agreed to "indemnify and hold harmless and defend all the parties herein released". On April 1, 1971, Orr sued the United States. The United States joined both Meador I and Meador II as third party defendants, relying on a clause in the construction contract holding Meador I "responsible for all damages to persons or property that occur as a result of [the contractor's] fault or negligence", and on a clause in the subcontract providing that Meador II agreed "that all terms and conditions of the Prime Contract are binding on this agreement, whether incorporated herein or not."

The district court found that Orr had suffered damages of $328,322, resulting from the combined negligence of the Government, Meador II, and Orr. The United States was negligent in allowing dead lines to be sandwiched between live ones on pole 14. Moreover, government inspector Bell knew, or should have known, that work would be performed on pole 14, and he should have ensured that the outage included disconnecting the stringers so that no current flowed through the bottom wires. Meador II's negligence consisted of failing to follow the safety procedures required in its contract.4 Orr was himself negligent in not taking precautions for his own safety.

As earlier stated, the court found the Government's negligence 30-percent responsible for the accident; Meador II and Orr were each 35-percent responsible. Taking 30 percent of the total award, the court ordered judgment against the United States in the sum of $98,496.60.

II

Under the Federal Tort Claims Act the United States waives its sovereign immunity for claims resulting from the negligent acts of its agents and accepts liability "in the same manner and to the same extent as a private individual under like circumstances". 28 U.S.C. Sec. 2674.5 What constitutes a legal duty and when such a duty has been breached are questions to be settled in accordance with "the law of the place where the act or omission occurred". 28 U.S.C. Sec. 1346(b). See United States v. Muniz, 1963, 374 U.S. 150, 83 S.Ct. 1850, 10 L.Ed.2d 805. And the choice of law is not affected by the fact that the claim in question arises on federal property, such as a military installation, within a state. See Ford v. United States, 10 Cir. 1952, 200 F.2d 272.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. County of Allegheny
322 U.S. 174 (Supreme Court, 1944)
Dalehite v. United States
346 U.S. 15 (Supreme Court, 1953)
McAllister v. United States
348 U.S. 19 (Supreme Court, 1954)
United States v. Muniz
374 U.S. 150 (Supreme Court, 1963)
United States v. Seckinger
397 U.S. 203 (Supreme Court, 1970)
Ford v. United States
200 F.2d 272 (Tenth Circuit, 1952)
Donald Feeley v. United States
337 F.2d 924 (Third Circuit, 1964)
Market Insurance Company v. United States
415 F.2d 459 (Fifth Circuit, 1969)
Florida Power & Light Co. v. Brinson
67 So. 2d 407 (Supreme Court of Florida, 1953)
Florida Power & Light Co. v. Robinson
68 So. 2d 406 (Supreme Court of Florida, 1953)
Florida Power and Light Co. v. Price
170 So. 2d 293 (Supreme Court of Florida, 1964)
Hoffman v. Jones
280 So. 2d 431 (Supreme Court of Florida, 1973)
Ahearn v. Florida Power and Light Company
129 So. 2d 457 (District Court of Appeal of Florida, 1961)
Jones v. Hoffman
272 So. 2d 529 (District Court of Appeal of Florida, 1973)
Vanlandingham v. Florida Power & Light Co.
18 So. 2d 678 (Supreme Court of Florida, 1944)
Kirkland v. City of Gainesville
166 So. 460 (Supreme Court of Florida, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
486 F.2d 270, 1973 U.S. App. LEXIS 7885, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orr-v-united-states-ca3-1973.