Orr Construction Co. v. State of Illinois, Department of Public Works & Buildings

30 Ill. Ct. Cl. 266, 1975 Ill. Ct. Cl. LEXIS 77
CourtCourt of Claims of Illinois
DecidedFebruary 3, 1975
DocketNo. 6777
StatusPublished
Cited by2 cases

This text of 30 Ill. Ct. Cl. 266 (Orr Construction Co. v. State of Illinois, Department of Public Works & Buildings) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orr Construction Co. v. State of Illinois, Department of Public Works & Buildings, 30 Ill. Ct. Cl. 266, 1975 Ill. Ct. Cl. LEXIS 77 (Ill. Super. Ct. 1975).

Opinion

Holderman, J.

This claim is founded upon a contract entered into by the respondent with the claimant, a general contractor, for the construction of a particular section of Illinois Route 57 Highway in Fayette County.1

The facts are not in dispute. The issues, under which claimant’s five-count complaint seeks damages in the sum of $572,408.12, arise out of a dispute in the interpretation of "Special Provisions” in-the contract entitled, "Removal and Replacement of Silty Topsoil Materials”.

This court is called upon to resolve the legal issues by making a judicial interpretation of the contract provision in dispute. Hence, without any objections from the respondent, we granted claimant’s motion to render a declaratory judgment in this cause pursuant to §57.1 of the Civil Practice Act. The parties concede that a declaration of their respective rights under the disputed provision of the contract which they request this court to construe may obviate the necessity for further litigation on the question of damages.

Both parties have informed the court that, if the legal question is decided in favor of the claimant, there is a possibility that the parties hereto in conference may reach a settlement on the amount of claimant’s damages making it unnecessary to go to trial on that factual issue. Conversely, if the ruling is favorable to the respondent, there would be no need for further proceedings in this cause.

As essential prologue to our interpretation of the disputed section of the contract, we restate the undisputed pertinent facts. On January 24,1969, the claimant submitted its sealed proposal for contract with the respondent under which claimant would construct the following: certain mainline grading and drainage for future pavement and ramps, as well as frontage roads, drainage structures, fencing, seeding, clearing and other work; a triple-barrel box culvert; and two steel bridges. This contract, as bid upon, was prepared and drafted solely by respondent. It consists of: (a) Plans, (b) Standard Specifications for Road and Bridge Construction and (c) Special Provisions (which supplement the Standard Specifications.)

The Special Provisions (on page 3 of the contract) provide, in relevant part:

REMOVAL AND REPLACEMENT OF SILTY TOPSOIL MATERIAL: Within the following station limits, and, as shown on the cross sections, the silty topsoil horizon is to be removed and replaced with suitable material.
This silty material shall be removed to a depth sufficient to provide a minimum thickness of 24 inches of suitable material between the bottom of the subbase and the remaining soil. The minimum depth of excavation shall be six (6) inches. The width of excavation shall extend beneath the pavement and the stabilized portions of the shoulders. The excavated material may be used in embankments greater than two feet in height and placed in alternate layers with suitable material. The height of embankment is to be measured from original ground to bottom of subbase. (Emphasis supplied to the keyword "may”.)
The silty material as well as material excavated from ditches or other excavations which has an A-4 classification (HRB classifications) and a silt content greater than 50% shall not be placed in embankments less than two (2) feet in height.
It is hereby understood and agreed that the final determination as to the materials to be removed and replaced will be made by the Engineer in the field and the plan quantity for Earth Excavation adjusted accordingly.
[Here the contract contains a table listing 21 areas in both the northbound and southbound pavement-, from station number to station numbers, in which the silty topsoil material was to be removed and replaced.]

Standard Specifications Section 202.03 (p. 31) in relevant part provides as follows:

"Unless otherwise provided in the plans or specifications, unstable and unsuitable material shall be disposed of by the contractor at his expense, outside the limits of the right of way.”

Claimant, in preparing its bid for the contract, understood the above quoted special provisions and standard specifications to mean: (1) that the silty topsoil material between the indicated stations was unsuitable material and was to be removed and replaced with suitable material; (2) that the unsuitable material was to be disposed of by the contractor at his expense; (3) that, at the contractor’s election, he could use the unsuitable material for fill in embankments greater than two feet in height, provided claimant placed it in alternate layers with suitable material; and (4) that, notwithstanding the quantity for such excavation shown on the plans, the determination of what was silty material to be removed and replaced would be made by the State’s Engineer and the plan quantity for excavation would be adjusted accordingly.

Claimant, relying on this understanding of the language of (3) above, determined that it could furnish a substantially lower bid by not using said unsuitable material in embankments over two feet high, but rather by disposing of it and providing and using suitable material in the embankments. Accordingly, claimant determined and submitted its bid on that basis; namely, on claimant’s election to dispose of the silty topsoil material and to use, instead, suitable borrow material in the embankments.

Thereafter, the claimant, having submitted the lowest bid, was awarded the job. Accordingly, on February 24, 1969, claimant entered into the aforesaid contract with the respondent. Except for the insertions of claimant’s bid prices, this contract is exactly the same as that drafted by respondent for submission to all contractors for bidding.

Claimant commenced work on the job. During the course of the work, respondent’s field engineer ordered claimant to use said excavated silty material in embankments of two feet or higher, contending that the election to use said materials rested with respondent. Claimant protested this interpretation of the Special Provisions; informed the respondent that the election to use said excavation in the embankments rested with the claimant; that his proposal had not been based on such re-use; and apprised respondent that its order would necessitate substantial additional expense not provided for in its bid. Respondent, nevertheless, ordered claimant to use this material. Claimant complied under protest.

The issue thus presented to the court is, whether the election to use the silty topsoil (unsuitable material) rests with the claimant contractor or with the State’s Engineer. The correct answer depends upon whether the grant of discretion by the word "may” in the following sentence from the "Special Provisions” supra, is addressed to the contractor to respondent’s field engineer:

"The excavated material may be used in embankments greater than two feet in height and placed in alternate layers with suitable material.”

The court takes notice that all of the other four sentences in the same paragraph from which the above sentence is lifted, are obviously all addressed to the contractor, and speak directly to him.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Toledo, Peoria & Western R.R. v. State
48 Ill. Ct. Cl. 25 (Court of Claims of Illinois, 1994)
Lukasik v. Riddell, Inc.
452 N.E.2d 55 (Appellate Court of Illinois, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
30 Ill. Ct. Cl. 266, 1975 Ill. Ct. Cl. LEXIS 77, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orr-construction-co-v-state-of-illinois-department-of-public-works-ilclaimsct-1975.