Orpheus Vaudeville Co. v. Clayton Investment Co.

128 P. 575, 41 Utah 605, 1912 Utah LEXIS 95
CourtUtah Supreme Court
DecidedDecember 3, 1912
DocketNo. 2401
StatusPublished
Cited by5 cases

This text of 128 P. 575 (Orpheus Vaudeville Co. v. Clayton Investment Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orpheus Vaudeville Co. v. Clayton Investment Co., 128 P. 575, 41 Utah 605, 1912 Utah LEXIS 95 (Utah 1912).

Opinion

FRICK, C. J.

This is an appeal from a judgment dismissing appellant’s complaint. The judgment of dismissal is based upon respondent’s objection interposed at the time of trial to the introduction of any evidence in support of the allegations of the complaint, upon the ground that the facts stated therein were insufficient to constitute a cause of action. The errors assigned are that the court erred in sustaining the objection and in entering a judgment dismissing the complaint.

[607]*607In view of the foregoing, it becomes necessary to set forth, somewhat in detail, the material allegations of the complaint which are: That both parties are corporations. That on the 7th day of April, 1-905, the parties entered into an agreement in writing, whereby in consideration of the appellant’s promise to lease the building hereinafter mentioned' for a period of ten years beginning October 1, 1905, at a rental of $60,000 for said term, payable as stated in the agreement, which agreement is specifically made a part of the complaint by reference, the respondent agreed “to completely build, erect, and equip at its . . . own cost, on or before October 1, 1905, in accordance with” certain plans and specifications to be approved by appellant, a certain theater building on certain property belonging to respondent in Salt Lake City, which property is fully described. That on the 27th day. of April, 1905, the time for the completion and equipment of the building was extended, such extension being in writing and indorsed on said agreement from October 1, 1905, to the 31st day of said month, and thereafter, on the 12th day of June, 1905, the time for the completion and equipment of said building was in the manner aforesaid further extended until the 30th day of November, 1905. That no plans or specifications were ever submitted to appellant for its approval.

“That said building was not finished and completed by the 1st day of October, 1905, nor by the 30th day of November, 1905, to which date the period of the completion of the same had been extended, but that on or about the 25th day of December, 1905, defendant informed plaintiff the said building was fully completed and ready for occupancy, and that plaintiff might have possession of the same. That on or about the said last-mentioned date a written lease of said theater building, whereby the defendant leased the same to the plaintiff for a period of ten years, beginning October 1, 1905, and expiring on October 1, 1915, at the rental above, and in said agreement in writing mentioned, and in which plaintiff agreed and obligated itself to pay the same to defendant, was taken out of escrow, where it had been placed at the time of [608]*608executing said agreement by said plaintiff and defendant, and because of the delay in erecting said building the said lease by interlineation was changed, so .as to provide that the term should begin January 1, 1906, and continue for a period of ten years from that d'ate. That said lease so changed was by the defendant herein offered to the plaintiff. That at the time of the offering of said lease the plaintiff herein protested and objected to the defendant that said building was not completed according to the terms of said-contract as hereinafter specifically set forth. That defendant refused' to complete said building in the particulars hereinafter set forth, and plaintiff was, by reason of the facts hereinafter set forth, compelled to and did accept said lease, under protest as aforesaid', and not waiving any of its rights-under said agreement in writing or otherwise. That on and prior to the 25th day of December, 1905, this plaintiff was under a large forfeit amounting, to wit, to $2500, to third parties in the event it failed to open the theater for a theatrical performance on the night of December 25, 1905, which the defendant then and there well knew. That on or about said 25th day of December, 1905, and upon being notified by the defendant that said theater building was fully completed and ready for occupancy, plaintiff because and on account of said forfeiture to the third party aforesaid, and in order to avoid the same, took possession of the same from defendant under protest and after objecting to the same as ■aforesaid. That at all times plaintiff was willing and ready to perform all on its part to be performed under said agreement in writing dated April 7, 1905, and frequently demanded of defendant the preparation and submission to it of a full and complete set of plans and specifications for said building, and the building, erection, and completion of the same in accordance with said contract. That in erecting, building', and equipping said theater building in accordance with said contract it was necessary and essential, in order that the same could be used for theatrical performances, that the same should be equipped with an asbestos curtain, a ticket office, and brass rail for same, a gridiron and rigging loft, [609]*609a manager’s office, forty-eight chairs for theater boxes and stalls, and ceiling and wall decorations, all of which defendant a,t all times knew, and it became and’ was the duty of defendant herein to fully build, erect, and equip at the cost of defendant said theater building as hereinbefore set forth, but that defendant failed, neglected, and refused to perform1 said contract on its part to be performed as hereinabove set out, notwithstanding its duty so to do. That in order to complete the erection and equipment of the said building, and in order to put the building in'such condition that it would be a theater building where theatrical performances might be given, and which it becomes necessary for the plaintiff so to do, and because of the failure of the defendant to perform its duties under said contract as hereinabove set forth, the plaintiff between the 25th day of December, 1905, and the last day of February, 1906, was compelled to and did install in said building, and was compelled to and did equip the same with, an asbestos curtain, ticket office, and brass rail therefor, manager’s office, gridiron and rigging loft, forty-eight chairs for boxes or stalls, and ceiling and wall decorations at an expense and costs, to wit, of $2013.85, and that on or about the 1st day of July, 1906, it expended on further ceiling and wall decoration the further sum of $2000.”

Upon the foregoing allegations appellant prayed judgment for the amount stated above.

Omitting the formal parts, the material portions of the agreement entered into between the parties to which reference has been made are as follows:

“The party of the first part hereby agrees to completely build', erect and equip at the cost of the party of the first part, in accordance with plans and specifications to be prepared by architect O. 1L Neuhausen, at the expense of the party of the first part, which plans and specifications, shall first be approved by the party of the second part, a theater building, which building shall be erected on that certain piece of land situate in Salt Lake City, Utah, and described [610]*610as follows, to wit: (Describing a certain piece of ground on State Street, between First and Second South Streets, Salt Lake City.) . . . The party of tbe first part further agrees that said building and entrance shall be completed and equipped in all particulars in accordance with said plans and specifications on or before the first day of October, A. D. 1905.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turner v. Turner
89 S.E.2d 245 (Supreme Court of North Carolina, 1955)
Moynihan v. Elliott
195 F.2d 363 (Fifth Circuit, 1952)
Buckman v. Hill Military Academy
189 P.2d 575 (Oregon Supreme Court, 1948)
Vitagraph, Inc. v. American Theatre Co.
291 P. 303 (Utah Supreme Court, 1930)
Sunshine Cloak & Suit Co. v. Commissioner
10 B.T.A. 971 (Board of Tax Appeals, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
128 P. 575, 41 Utah 605, 1912 Utah LEXIS 95, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orpheus-vaudeville-co-v-clayton-investment-co-utah-1912.