Orman v. Crystal River Railway Co.

5 Colo. App. 493
Colorado Court of Appeals·Decided January 15, 1895·Published

Opinion

Bissell, P. J.,

delivered the opinion of the court.

Orman & Crook contracted with The Crystal River Railroad Company, in September, 1892, to construct certain parts of the road. When the work was done, there remained due a little upwards of thirty thousand dollars out of the total contract price of some two hundred and sixty-eight thousand dollars which the company had agreed to pay. The company failed to pay, and on the 4th of October, 1898, the contractors filed a lien statement with the clerk and recorder of the counties through which the road ran. On the 9th of March, 1894, they brought this suit to enforce the lien. They named the railroad company and divers other parties as defendants, alleging, as to the company, the contract and its breach, and as to the other defendants, that they had or claimed some interest as lien claimants against the railroad company. These other defendants — The Morey Mercantile Company and Jones & Seeley — likewise brought suits in the Pitkin county district court to enforce the liens which they had initiated. After these three different suits were begun, the court made an order consolidating the cases. The railroad company demurred to Orman & Crook’s complaint, on the ground that Orman & Crook had not shown they were lien claimants having the right of foreclosure. There were a good many irregularities in the proceedings below, and some which inhere in the judgment; but by stipulation the litigants have relieved us of the necessity to dispose of these matters, and the right to determine the sufficiency of the complaint is left open. It is not essential to our conclusion, nor to its apprehension, to do more than state what the allegations are with reference to two or three of the essential facts. The plaintiffs alleged that pursuant to the contract, [495] they constructed the grade and roadbed between two dates, the 3d of September, 1892, and the 15th of August, 1893. They farther stated that, according to the terms of the contract, the sum which they sought to recover became due and payable on the 15th day of August, 1893, and thereafter remained unpaid. In another portion of the pleading, they averred they begun the work and commenced to furnish the materials in September and October, 1892, and thereafter continuously prosecuted the work of constructing the road and roadbed until the 15th day of August, 1893. These are the only particulars which must be stated. In other respects the pleading is probably sufficient to compel an issue of fact, and to entitle the plaintiffs to a trial. Notwithstanding these facts, the contractors did not file their statement of lien until October, nor institute their suit for foreclosure until the following March. Unless, under these circumstances, the plaintiffs have the right to foreclose their lien, they were not entitled to anything but a money judgment against the company for whatever sum they might prove to be due. For many years there have been lien statutes in this state. It is conceded that, under the statutes in force prior to 1893, what the contractors did was enough to give them a lien, if otherwise they could prove their case, and under those acts they commenced their suit in apt time to entitle them to proceed to judgment. The appellee, however, insists that the lien law which was approved April 3, 1893, and went into effect on the 2d day ofi July, 1893, was not observed by the contractors. The act of 1893 differs from the former statute in respect to the time in which the liens must be filed, and to the time for the commencement of the suit to enforce it. Under the complaint, we must assume the lien was filed in apt time, even under the act of 1893, because that pleading charges the work to have been continuously prosecuted up to the 15th of August, and to have been finished on that day, when the money earned became due. This matter then will not be considered. The troublesome question springs from the [496] date when the suit was begun. Under the former statute, foreclosure proceedings could be instituted at any time within six months after the lien was filed, but under the act of 1898, certain other things must precede the commencement of the suit, and the action itself must be begun within four months after the completion of the work. There is one other consideration which must be noticed before proceeding to state the general proposition on which the case turns. The act of 1893 contained a proviso that the repeal of the antecedent acts should not be construed to affect any existing right as to remedy or otherwise, or to abate any suit which might have been instituted to enforce a lien acquired under the preceding enactments.

Free access — add to your briefcase to read the full text and ask questions with AI

Orman v. Crystal River Railway Co., 5 Colo. App. 493 (Colo. Ct. App. 1895).

5 Colo. App. 493 (Orman v. Crystal River Railway Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Withenbury v. United States
72 U.S. 819 (Supreme Court, 1867)
Nichol v. Dunn
25 Ark. 129 (Supreme Court of Arkansas, 1867)
Henry v. Travelers' Insurance
16 Colo. 179 (Supreme Court of Colorado, 1891)
Templeton v. Horne
82 Ill. 491 (Illinois Supreme Court, 1876)
Barton v. Steinmitz
37 Ill. App. 141 (Appellate Court of Illinois, 1890)
Hagerman v. Moore
2 Colo. App. 83 (Colorado Court of Appeals, 1892)
Kiefer v. Kiefer
4 Colo. App. 506 (Colorado Court of Appeals, 1894)
Weaver v. Sells
10 Kan. 609 (Supreme Court of Kansas, 1873)
John S. Hanes & Co. v. Wadey
41 N.W. 222 (Michigan Supreme Court, 1889)
Tell v. Woodruff
47 N.W. 262 (Supreme Court of Minnesota, 1890)
Bardwell v. Mann
48 N.W. 1120 (Supreme Court of Minnesota, 1891)