Orion Communications Limited v. Federal Communications Commission, Biltmore Forest Radio, Inc., Intervenors

131 F.3d 176, 327 U.S. App. D.C. 326
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 2, 1998
Docket96-1430
StatusPublished
Cited by2 cases

This text of 131 F.3d 176 (Orion Communications Limited v. Federal Communications Commission, Biltmore Forest Radio, Inc., Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orion Communications Limited v. Federal Communications Commission, Biltmore Forest Radio, Inc., Intervenors, 131 F.3d 176, 327 U.S. App. D.C. 326 (D.C. Cir. 1998).

Opinion

Opinion for the court filed by Circuit Judge GINSBURG.

GINSBURG, Circuit Judge:

Orion Communications, Ltd. appeals from an order of the Federal Communications Commission rescinding Orion’s interim authority to operate an FM station and granting that authority to a consortium of Orion’s competitors whose license applications the Commission had previously rejected. We hold that the FCC acted arbitrarily and capriciously and we reverse the Commission’s decision.

I. Background

In 1990, after a contested hearing, an Administrative Law Judge granted the application of Orion Communications, Ltd. for a license to operate a new FM station in BilL more Forest, North Carolina. See National Communications Indust., 5 FCC Red 2862 (ALJ 1990). The Federal Communications Commission thrice confirmed that grant. See National Communications Indust., 6 FCC Rcd 1978 (Review Bd.1991); National Communications Indust., 7 FCC Red 1703 (1992) (denying applications for review); Liberty Prod., 7 FCC Red 7581 (1992) (denying petition for reconsideration). In April 1993, while rejected applicants had still further appeals pending before the Commission and this court, the FCC issued to Orion a construction permit “conditioned on the final outcome of Docket 88-577,” i.e., the license proceeding, noting that “[a]ny construction pursuant to this permit prior to this docket becoming final is at the permittee’s sole risk.” After discovering that it could save money by leasing a tower rather than building its own, Orion asked the Commission to modify its construction permit. In November 1993 the Commission issued a second, modified permit, but only after extracting from Orion a promise to begin construction immediately.

Meanwhile, in December 1993 this court decided Bechtel v. FCC, 10 F.3d 875, in which we held that the Commission’s use of the “integration” criterion in comparative hearings was arbitrary and capricious, Shortly thereafter the Commission announced that it would “hold[ ] in abeyance the processing of applications and the adjudication of hearing proceedings .... while it considered] appropriate action” in light of Bechtel. Public Notice, FCC Freezes Comparative Proceedings, 9 FCC Red 1055 (Feb. 25, 1994).

In March 1994, acting upon the basis of Bechtel, we reversed the orders of the Commission granting Orion’s license application and denying the applications of its competitors, and remanded the entire matter to the FCC for reconsideration. See Biltmore Forest Broadcasting FM, Inc. v. FCC, No. 92-1645, 1994 WL 116196 (Mar. 15, 1994). The previously rejected applicants then petitioned the Commission to rescind the construction permit it had issued to Orion.

Before ruling upon that petition the Commission on June 27, 1994 issued to Orion yet a third construction permit, this time for a broadcast station in Asheville auxiliary to the primary FM station in Biltmore Forest. Orion then completed construction of its station, began to broadcast program tests, and on August 3, 1994 applied for an operating license. The next day the Commission acted to “clarify” its earlier Public Notice; it stated that “[w]here program tests have already commenced, operations may be continued so as not to deprive the public of existing service.” Public Notice, Modification of FCC Comparative Proceedings Freeze Policy, 9 FCC Red 6689 (Aug. 4, 1994). Because Orion had begun broadcasting before August 4, the Audio Services Division of the FCC later denied the request of Orion’s competitors to rescind its construction permit.

*178 The rejected applicants sought reconsideration of their petition to rescind Orion’s permit and also, acting as a nonprofit consortium under the name Biltmore Forest Radio Inc. (BFRI), themselves applied for joint interim' operating authority. The Commission reversed the Audio Services Division and rescinded Orion’s construction permit. According to the Commission, although Orion was “technically within the parameters described by the Public Notice [of August 4] for continued operation .... the Public Notice did not contemplate circumstances ... where an applicant did not commence [broadcasting program tests] until more than four months subsequent to the court Order reversing the grant of that applicant’s permit.” Orion Communications, Ltd., 10 FCC Rcd 13066 (Nov. 29, 1995). The Commission also instructed its staff to accept BFRI’s application for joint interim operating authority pending the Commission’s final grant of a license. Orion petitioned for reconsideration. The Commission denied the petition, explaining that Orion’s construction of the station and commencement of broadcasting was “clearly unreasonable” in light of this court’s having earlier reversed and remanded the Commission’s decision granting Orion’s application. See Orion Communications, Ltd., 11 FCC Red 19589 (Oct. 22, 1996). BFRI began broadcasting six months later, on June 2, 1997.

II. Analysis

We reverse a Commission decision granting or denying a broadcast license only if that decision is “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A); see DIRECTV, Inc. v. FCC, 110 F.3d 816, 826 (D.C.Cir.1997). The Commission’s decisions in this case clearly fail to meet even this deferential standard.

The Commission recognized that it had the “discretion to maintain [Orion’s] existing service upon ... remand ... in order to avoid disruption of service to the public.” See 11 FCC Red 19589 (1996). In nonetheless rescinding Orion’s authority to provide such service, the Commission abused its discretion and acted arbitrarily and capriciously in the following respects: The Commission (1) erroneously concluded that Orion had been “clearly unreasonable” in proceeding with construction and broadcast tests after this court, in remanding the ease against Orion for reconsideration in the wake of Bechtel, had vacated the Commission’s decision granting Orion’s license application; (2) created an unfounded exception to the general rule announced in its Public Notice of August 4, 1994 that a station already broadcasting could continue to do so; (3) failed to follow the standards it had set for itself in 47 C.F.R. § 73.3592(b), in that it considered neither the equities of the situation nor other aspects of the public interest; and (4) departed from its own recent precedent without providing a reasoned explanation for so doing.

A. Orion’s conduct

The Commission argues that this court’s remand of March 15, 1994, by vacating the Commission order granting Orion’s license, served automatically to revoke Orion’s construction permit and that Orion therefore acted unreasonably in continuing to build its station.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
131 F.3d 176, 327 U.S. App. D.C. 326, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orion-communications-limited-v-federal-communications-commission-biltmore-cadc-1998.