Orient Mid-East Lines, Inc. v. Cooperative for American Relief Everywhere, Inc.

410 F.2d 1006
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 6, 1969
DocketNos. 21833-21836
StatusPublished
Cited by9 cases

This text of 410 F.2d 1006 (Orient Mid-East Lines, Inc. v. Cooperative for American Relief Everywhere, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Orient Mid-East Lines, Inc. v. Cooperative for American Relief Everywhere, Inc., 410 F.2d 1006 (D.C. Cir. 1969).

Opinion

TAMM, Circuit Judge:

Appellant petitions this court seeking recovery of “second freights” 1 which it alleges are owed it by the appellees under [1008]*1008shipping contracts.2 Briefly, appellant is a ship operator who, at times relevant to this litigation, operated two ships loaded with relief cargoes which had been donated by some of the appellees for delivery overseas.3 In the winter months of 1964 the appellant’s two ships were loaded with their cargoes at various Great Lakes ports. Both ships proceeded through the Great Lakes, arriving at the lakeward entrance to the Seaway shortly after the Seaway had closed its 1964 navigation season due to the cold weather. Unable to reach their destination, appellant’s ships were forced to spend the winter at a Toronto berth (J.A. 81a, 86a). When appellant’s ships could proceed no further due to the closing of the Seaway, it claimed that the voyage was terminated due to elements beyond its control and that “all freights were earned” (J.A. 50a). Further, it asked for storage fees for keeping the goods throughout the winter and, as previously mentioned, demanded second freights for the completion of the originally scheduled voyage once the Seaway was cleared. Appellant also sought and recovered freight payments (as well as interest thereon for delay in payment) which were due to it prior to the ice closure and these claims are not in issue in this litigation.

This case was tried in our district court without a jury and the trial judge issued an opinion and a supplemental opinion finding in favor of the appellees on all claims (284 F.Supp. 34 (1968)). More specifically, the district court held that appellant did not exercise “reasoned judgment” in failing to heed repeated warnings of the possibility of ice closure of the Seaway and that therefore it was not entitled to recover second freights or storage fees from the appellees (284 F.Supp. 34, at 44, 46). We affirm.

The dispositive issues in this litigation are largely factual. Appellant argues that the exculpatory clauses in the bills of lading exempt it from liability even if it. was negligent in its contract performance (see note 2, supra). The district court found, however, that these clauses did not afford appellant a carte blanche in fulfilling its contract obligations in any way it pleased. To the contrary, it found that, notwithstanding the exculpatory language, appellant was contractually bound to exercise reasonable judgment and that it had not done so in this instance. The district court explicitly held that: (284 F.Supp. 34, 43)

there is a common standard of conduct prescribed if a carrier is to be afforded the protection of the exculpatory provisions. The Court finds that standard to be that to afford itself the protection of the exculpatory clauses of the bills of lading the carrier must exercise reasonable judgment under the circumstances existing and reasonably foreseeable at the time the judgment is made. In other words the exculpatory [1009]*1009clauses do not confer a license to disregard the likely or the obvious.

We agree with the trial court’s characterization of the standard of care required of appellant and we are of the view that it did not adhere to that standard.4

The District Court’s conclusion as set out above was bottomed largely upon the fact that the Seaway had issued several warnings regarding the possibility of an early close of the Seaway. This conclusion was derived from an analysis and evaluation of all the testimony adduced during the trial. The trial judge found it significant, and we agree, that on November 2, 1964, the Seaway issued a notice (J.A. 43a-44a), as a warning to all carriers, stating that the formal closing date of the Seaway was November 30, 1964, and that “weather and ice conditions could force the Seaway to be closed earlier * * *” (J.A. 44a). In addition, on November 25, 1964, a similar notice was issued to appellant (J.A. 46a-48a). Thereafter, the Seaway Authority sent telegrams to the Shipping Federation of Canada and the Dominion Marine Association (J.A. 284a-290a) warning of a possible early closure and listing a comparison of water temperatures which reflected the fact that 1964 was running considerably colder than 1963. Finally, various witnesses testified at the trial as to the warnings issued to appellant. Among those who testified was Captain John Butt (Senior Ship Inspector of the Seaway Authority), who testified that he called appellant’s general agent (Mr. Pen-días) personally to warn him of the impending freeze. The trial judge evaluated all the evidence before him, including the credibility of all the witnesses who testified. We find on the basis of the trial transcript and the district court opinion that his findings are free from reversible error. Miller v. Avirom, 127 U.S.App.D.C. 367, 384 F.2d 319 (1967); Elm Corp. v. E. M. Rosenthal Jewelry Co., 82 U.S.App.D.C. 196, 161 F.2d 902 (1947). In this regard, appellant argues that the trial judge erred in his evaluation of the evidence, and especially the credibility of Captain Butt. We must point out again that it is not the function of this court to evaluate the credibility of the witnesses in determining whose version of the factual setting is correct. Johns-Manville Corp. v. Ladd, 117 U.S.App.D.C. 262, 263, 328 F.2d 563, 564 (1964); Merry Manufacturing Co. v. Burns Tool Co., 335 F.2d 239 (5th Cir. 1964). Our scope of review is delineated clearly by Rule 52(a), Fed.R.Civ.P.5 Thus, upon inspection of the entire record below we find no reversible error in the trial judge’s well written opinion.

We have reviewed all of appellant’s other contentions and find them without merit. Briefly, it seems clear that the Seaway Authority had no duty to advise appellant of any definite closure date and that appellant could not rely on such duty without any affirmative obligation on its part to exercise reasonable care in guiding its ships through the Seaway. The Maritime Administration’s decision with respect to another ship caught in the Seaway is, of course, not binding upon us and may well be precluded under the doctrine of res inter alios acta. Finally, since we find that appellant was contractually required to but did not exercise reasoned judgment, we do not find controlling the district court’s distinction between “a clause granting an exemption to the carrier from liability * * * and a situation where a carrier asserts an affirmative claim of liability against another * * * ” (284 F.Supp. 34, 46). We feel that this distinction neither absolves nor indicts [1010]*1010appellant per se; rather, it is not necessary to a finding of liability on the part of appellant. The district court’s disposition of this cause of action is therefore

Affirmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
410 F.2d 1006, Counsel Stack Legal Research, https://law.counselstack.com/opinion/orient-mid-east-lines-inc-v-cooperative-for-american-relief-everywhere-cadc-1969.