O'REILLY v. Dock

929 S.W.2d 297, 1996 Mo. App. LEXIS 1591, 1996 WL 534715
CourtMissouri Court of Appeals
DecidedSeptember 23, 1996
Docket20407
StatusPublished
Cited by12 cases

This text of 929 S.W.2d 297 (O'REILLY v. Dock) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'REILLY v. Dock, 929 S.W.2d 297, 1996 Mo. App. LEXIS 1591, 1996 WL 534715 (Mo. Ct. App. 1996).

Opinion

SHRUM, Judge.

This case presents questions about the application and interpretation of statutes of limitations in a contract dispute.

Plaintiffs sought to recover damages from Defendant for his failure to build an addition to their house according to the terms of their contract. 1 The trial court found that Defendant had installed certain windows with improper flashing or no flashing, that this defect caused certain windows to leak, and that water damage resulted “which was apparent more than five years before suit was filed.” On those findings, the trial court ruled that Plaintiffs were not entitled to recover “any damage that may have occurred as a result of the leaking in the window[s] [as it] is barred by the statute of limitations_” See § 516.100 and 516.120.1. 2 Plaintiffs did not appeal from that portion of the judgment.

Additionally, the trial court found that Defendant breached the contract by not building a crawl space beneath the addition of the size specified in the plans and by not providing footings of the depth specified. It also found that Plaintiffs did not know about and could not “reasonably have ascertained those breaches.” The trial court awarded to Plaintiffs those “items of damages ... necessary ... to correct the breach of contract that [the court has] described[,]” which it determined to be $6,180.24. Defendant appeals from that portion of the judgment.

In his first point, which we find dispositive, Defendant charges that the trial court erred because the damages awarded were “both sustained and capable of ascertainment more than five ... years” before suit was filed, hence they too were barred by the five-year statute of limitations.

We reverse the judgment.

*299 FACTUAL BACKGROUND

In March, 1988, Plaintiffs contracted with Defendant for the latter to make certain renovations and changes to Plaintiffs’ home. The contract documents included certain plans and specifications prepared by Plaintiffs’ architect. In part, Defendant was to rebuild and add onto the front or north part of Plaintiffs’ house from “the roof down to the foundation.” The work was completed by September 8,1983.

The construction plans specified neither a crawl space entry point nor air vents in the foundation wall beneath the north addition, and consequently the addition was built without those features.

As part of the renovation, a large number of wooden windows were installed on the north side. Shortly after the work was done, Plaintiffs discovered water which had leaked through some windows and onto window sills inside the house. Both Plaintiffs testified that when the leaks were found, Defendant was notified. They testified that he responded by recaulking the entire window bank. According to Plaintiffs, the initial repair stopped the flow of water to the inside of the house. Nevertheless, during routine maintenance in 1986, carpenters told Plaintiffs that the window frames had rotted excessively. From 1986 onward, Plaintiffs repeatedly attempted to remedy the window leaks — without success — by painting, caulking, and replacing window sashes. Charles testified that carpenters who worked on the windows in 1987 and 1988 told him that there was “some kind of a moisture problem” around the windows. However, they were unable to tell him what was causing the problem. As Charles explained it, the carpenters had tried to find the problem but reported back to him that they could not “get under there and take a look at it.” Charles also recounted at trial that a mildew smell in the house progressively worsened until 1989 or early 1990 when they installed a dehumidifier. Plaintiffs’ use of a dehumidifier stemmed from the recommendation of a heating and air conditioning installer who told them in 1989 that they had a “severe moisture problem” in the front part of their house. Charles testified that the air conditioning man also reported his inability to assess the problem because he could not “crawl up in under there.”

By March, 1992, Plaintiffs “wanted to replace that whole bank of windows and solve that problem there in the front of the house.” To accomplish that end they hired Ronald Middleton, a residential builder. Middleton testified that on initial inspection, he found no “noticeable evidence of leaks or defects in the structure” and no “apparent problems” with Defendant’s work. However, upon removing the brick and styrofoam sheeting, he discovered extensive rot damage in the wooden rim joists and sill along the north wall area. Middleton testified that as the work progressed he concluded that the windows “were improperly flashed at the top” and that water that came in the window area traveled in the wall cavity and ended up “in and around and under the window [area].” He also testified that “[t]he thing that complicated [the window leak problem] considerably was the fact that ... there was no crawl space basically under the house.” He characterized the lack of crawl space as a “faulty construction practice.” Middleton explained the significance of the crawl space defect thusly: “[E]ven if there had ... been ... foundation vents, which there were not, to provide ventilation, the [incoming water] ... was ending up ... under the window ... [where] the joists were sitting on the ground or within four inches of the ground.... ”

Plaintiffs’ expert witness, engineer Saul A. Nuccitelli, testified that Defendant breached both a contract requirement and good building practice by building with only a four to eight inch crawl space rather than a minimum twelve inch space. He explained that the twelve inch requirement provides proper air ventilation between the ground and the woodwork and to build with less space, as Defendant did, “allows the moisture in the soil to be very close to your lumber and timber and it starts ... causing problems.” Nuccitelli testified that the area along the north wall was a little bit lower than the rest, apparently because of excavation for duct work. He found that the duct work had been insulated; consequently, the water that collected in this low area tended to keep the insulation wet. Continuing, he testified that *300 the insulation had acted “as a wick effect ... to transfer the water at the ground level on up into and around the lumber at that front portion of the north wall.”

Plaintiffs’ experts,' Nuccitelli and Middleton, agreed that window leaks were the source of the excessive water beneath Plaintiffs’ house, and but for the excessive water, the rotting would not have occurred.

DISCUSSION AND ANALYSIS

As mentioned earlier, Defendant’s first point charges that the trial court erred in awarding damages because Plaintiffs’ loss was “both sustained and capable of ascertainment more than five ... years prior to the filing of the petition and [their claim is] thus time barred by §§ 516.120 and 516.100.”

With exceptions not applicable here, §§ 516.100 and 516.120.1 mandate that all contract actions must be commenced within five years “after the causes of action shall have accrued.” To determine when a cause of action has accrued, § 516.100 provides:

“[T]he cause of action shall not be deemed to accrue when the wrong is done or the technical breach of contract or duty occurs, but

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Farmer's Alliance Mutual Insurance Company v. Daniels Plumbing
496 S.W.3d 644 (Missouri Court of Appeals, 2016)
Simon Mahanna v. U.S. Bank National Assoc.
747 F.3d 998 (Eighth Circuit, 2014)
Ashford Condominium, Inc. v. Horner & Shifrin, Inc.
328 S.W.3d 714 (Missouri Court of Appeals, 2010)
Allen v. Kuehnle
92 S.W.3d 135 (Missouri Court of Appeals, 2002)
ARCHITECHTONICS CONSTRUCTION v. Khorram
45 P.3d 1142 (Court of Appeals of Washington, 2002)
Architechtonics Construction Management, Inc. v. Khorram
45 P.3d 1142 (Court of Appeals of Washington, 2002)
Business Men's Assurance Co. of America v. Graham
984 S.W.2d 501 (Supreme Court of Missouri, 1999)
Estate of Cates v. Brown
973 S.W.2d 909 (Missouri Court of Appeals, 1998)
Community Title Co. v. U.S. Title Guaranty Co.
965 S.W.2d 245 (Missouri Court of Appeals, 1998)
Jordan v. Willens
937 S.W.2d 291 (Missouri Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
929 S.W.2d 297, 1996 Mo. App. LEXIS 1591, 1996 WL 534715, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oreilly-v-dock-moctapp-1996.