O'Reilly v. City of Cambridge

279 F. 961, 1922 U.S. App. LEXIS 1648
Court of Appeals for the Sixth Circuit·Decided April 14, 1922·No. No. 3586·Published·Cited by 1 cases

Opinion

DENISON, Circuit Judge

(after stating the facts as above). [1] As to the maintenance bond, we must determine whether it was necessary and what effect follows its absence. We have no doubt of its necessity. Its requirement was not so far a part of the subject-matter oi the contract that the failure to include a call for it in the formal written contract would eliminate it, either because it was á part of the preliminary negotiations which were merged into the contract or because it varied or modified the contract. The obligations of the contract to be performed began with the commencement of the work and ended with the finishing of the work and the payment therefor, and tfe construction bond which the contract provides for is incidental to and secures the completion of the work. The guaranty and maintenance bond looked to a future period. Such retention of a percentage as the printed form of the contract provides for, beyond the completion o:, the contract, for the purpose of securing maintenance, refers to a p irt of the work not let to this contractor. By the original notice it was expressly provided that upon the completion of the work the con-ti actor should give—as to this work—a guaranty and maintenance bmd for five years. This condition was a part of the same paper which contained O’Reilly’s bid and the specifications and the blank contract. Ey such bid, O’Reilly accepted this condition. All of the bidders did the same. The giving of such bond would be a distinct burden on the bidder and a benefit to the city. Since the subsequently executed contract constituted no waiver of this condition, we must conclude that its acceptance created a valid and continuing contract between the parties.

[2] It does not follow that the contract is unenforceable. The conditions called only for the giving of the bond after the contract was completely executed by the contractor and before tire final estimate was paid, and then only if the city required it. The applicability of the provision to such “workmanship” as was involved in plaintiffs’ contract might well be so doubtful as to leave the final requirement optioiral with the city. Up to the time of commencing this suit there had been ro such requirement. On the other hand, the city and the engineer had c eclined to make the final estimate, and the time when the bond could te demanded had not been reached. The city could not consistently I ave accepted such a bond if it had been tendered, and the tender was plainly not necessary until .the point of payment was reached. We think, however, that, in order to carry out the substance of the agreement on this subject, the proceedings in this case should be so shaped that the substantial benefit and security of. the bond will be preserved to the city. The judgment in this case, if eventually rendered for the plaintiffs, will be upon the theory that the city had waived the final estimate and the formal general acceptance by and satisfaction of the engineer. In' that situation the plaintiffs should have pleaded their.' willingness to give the required bond in connection with the case and before the rendering of any judgment therein. The sufficiency of any bond which is. offered can be determined by the court, as can likewise the precise time and manner of its production in order to insure that payment shall not be compelled until the bond is given. Plaintiffs [965] should amend their pleadings in order to cover such a proffer. The verdict of the jury, if for the plaintiffs, will stand for the engineer’s estimate. The judgment will stand for payment. The bond will appropriately be an intermediate condition. Since the contemplated five-year period will probably have expired before the further trial, and since the question whether the workmanship and materials were in accord with the contract, will be decided by the jury upon such trial, it does not seem that the furnishing of the bond will turn out to be very important.

[3] The evidence as to how the wooden pipe item came to be included in the contract, when O’Reilly had not bid upon it, is very incomplete. Since the case was dismissed upon this ground, and this action was analogous, though not necessarily equivalent, to directing a verdict for the defendant, we must take the tendency of the evidence-most strongly in plaintiffs’ favor, and assume any state of fact which might fairly be inferred from the evidence and which would tend to support plaintiffs’ right of action. Giving to the city officials the ordinary presumption of good faith, it is quite consistent with the evidence and is probable enough, as such things go, and we therefore for the purpose of this opinion may rightly assume, that O’Reilly was the lowest bidder upon the items named in his bid, after giving due regard to the quantity estimates, that other bidders were the lowest upon many other parts of the work, that no hid upon the wooden pipe item was at a lower price than that for which it was awarded to O’Reilly, and that the city, in effect,. said to O’Reilly:

“You have the best bid upon the reservoir work and the iron pipe to and from, but it would be for the advantage of the city to have you lay also the wooden pipe, which is a part of the same class of work, rather than to make a separate job of it by some one else, and if you will do that work at the lowest price which has been bid for it, we will add that item to your contract,”

—and that O’Reilly accepted this proposition. Of course, the evidence upon the new trial may develop the situation differently in some material particular than that which we thus assume; but this cannot be now foreseen.

We find no satisfactory reason for thinking that the wooden pipe item of the contract would be invalid under the circumstances so to be assumed. The statute involved is section 4328 of the Ohio General, Code, reading as follows:

“ * * * The director of public service shall make a written contract with the lowest and best bidder after advertisement for not loss than two or more than four consecutive weeks in a newspaper of general circulation within the city.”

Free access — add to your briefcase to read the full text and ask questions with AI

O'Reilly v. City of Cambridge, 279 F. 961, 1922 U.S. App. LEXIS 1648 (6th Cir. 1922).

279 F. 961 (O'Reilly v. City of Cambridge) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Interstate Power Co. v. Forest City
281 N.W. 207 (Supreme Court of Iowa, 1938)