Oregon Natural Resource Council v. Turner

863 F. Supp. 1277, 25 Envtl. L. Rep. (Envtl. Law Inst.) 20380, 1994 U.S. Dist. LEXIS 19653, 1994 WL 532328
CourtDistrict Court, D. Oregon
DecidedJuly 6, 1994
DocketCiv. 92-6291-TC
StatusPublished
Cited by9 cases

This text of 863 F. Supp. 1277 (Oregon Natural Resource Council v. Turner) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oregon Natural Resource Council v. Turner, 863 F. Supp. 1277, 25 Envtl. L. Rep. (Envtl. Law Inst.) 20380, 1994 U.S. Dist. LEXIS 19653, 1994 WL 532328 (D. Or. 1994).

Opinion

ORDER

HOGAN, District Judge.

Magistrate Judge Thomas M. Coffin filed his Findings and Recommendation on June 1, 1994. The matter is now before me. See 28 U.S.C. § 636(b)(1)(B) and Fed.R.Civ.P. 72(b). *1279 No objections have been timely filed. This relieves me of my obligation to give the factual findings de novo review. Lorin Corp. v. Goto & Co., Ltd., 700 F.2d 1202, 1206 (8th Cir.1983). See also Britt v. Simi Valley Unified School Dist., 708 F.2d 452, 454 (9th Cir.1983). Having reviewed the legal principles de novo, I find no error.

Accordingly, I ADOPT Judge Coffins’ Findings and Recommendation. Plaintiffs petition for an award of attorney fees and expenses (#64) is denied, and the parties shall bear their own costs.

IT IS SO ORDERED.

FINDINGS AND RECOMMENDATION

COFFIN, United States Magistrate Judge.

Plaintiffs petition the court for an award of attorneys’ fees and expenses of litigation in the amount of $31,371.28. Such petition is made pursuant to 16 U.S.C. § 1540(g)(4), a section of the Endangered Species Act (ESA). For the reasons set forth below, the petition should be denied. 1

Factual Background

Plaintiffs brought this suit alleging that defendants failed to designate critical habitat for two endangered plant species (MacFarlane’s four o’clock and Bradshaw’s Desert Parsley (BDP)) and failed to develop a recovery plan for BDP. Plaintiffs concede that they did not prevail on their first two critical habitat claims, 2 but contend that they prevailed on their third claim regarding the development of a recovery plan for BDP and are entitled to fees related to such claim. Defendants “vigorously oppose” the petition for fees and costs.

The Third Claim,

On June 4,1992, plaintiffs sent their notice of intent to sue to the Secretary of Interior (Secretary), the Director of the United States Fish and Wildlife Service (USFWS), and the Regional Director for Region One of the USFWS, for violations of the ESA, 16 U.S.C. § 1533(f)(1) and. (f)(4), and 16 U.S.C. § 1533(b)(6)(C). When the notified parties failed to immediately remedy the situations giving rise to the alleged violations, plaintiffs filed suit in the District Court for the District of Oregon on August 10, 1992. In the complaint, plaintiffs asserted their eligibility under ESA § 1540(g)(4) to recover attorney’s fees. Id. at 6. After the initial service of the complaint, plaintiffs served requests for the production of documents, interrogatories, and requests for admissions.

On March 1, 1993, this Court issued a Findings and Recommendation (# 23) which was adopted in its entirety (#32). Defendants’ motion as to’plaintiffs’ claims related to the development of recovery plans for BDP was denied without prejudice to refile or to file as ’ a summary judgment motion. The Court noted that the ESA establishes a non-discretionary duty for the Secretary to develop recovery plans for species listed as endangered and that plaintiffs conceded that the ESA imposes no time limit in which the *1280 Secretary must act. The Court also noted that a complaint should not be dismissed under Rule 12(b)(6) unless it appears beyond doubt that the plaintiff can prove no set of facts in support of his claim that would entitle him to relief and invited defendants to provide further briefing with their refiled motion to dismiss. Briefing was to be on the issue of at what point, if ever, the Secretary’s nonpublishing of a recovery plan becomes a failure to perform a duty. The Court recognized the status of the nearly completed draft recovery plan and stated that the above mentioned issue had the potential of being mooted.

On March 12, 1993, defendants filed the recovery documents for BDP. The documents included drafts of the recovery plan that were circulated for comment within the agency as early as September 1991. On April 8, 1993, the' draft recovery plán was published in the Federal Register for review and comment. 58 Fed.Reg. 18225 (April 8, 1993).

On May 6, 1993, defendants filed a Motion for Summary Judgment (#34) addressing the issues of timing raised in the Findings and Recommendation, and attached a copy of the published draft recovery plan. Defendants explained that no violation of a legal duty had occurred since the Secretary had been working on drafts of the recovery plan since at least September 1991 and had, on April 8,1993, published a draft recovery plan for comment and review. Moreover, due to the publication of the draft plan, plaintiffs’ claims were now moot.

Plaintiffs filed their Opposition to Defendant’s Motion for Summary Judgment and Motion for Partial Summary Judgment on May 19, 1993 (# 43, # 44). Plaintiffs sought summary judgment on four issues. The first two issues sought summary judgment as to plaintiffs’ standing and jurisdiction of the court. Neither issue had been raised by defendants and defendants did not oppose summary judgment as to these issues, noting that “briefing these issues seems only to increase unnecessarily the costs and fees already invested in this case.” Defs’ Opp’n to Pis.’ Cross-Mot. for Partial Summ.J. (#49) at 3 n. 1. Defendants also did not oppose plaintiffs’ motion for partial summary judgment as to the fact that declaratory judgment would be an appropriate remedy if the court were to find for plaintiffs on the merits. Defendants strongly opposed plaintiffs’ motion for summary judgment on the issue of whether the Secretary of the Interior had violated a statutory duty to develop a recovery plan. Id. at 5-11.

On June 1, 1993, defendants filed, and served on opposing counsel, the Declaration of David L. McMullen (# 50) stating that a final recovery plan would be complete on or before August 6, 1993. Oral argument on the pending motions for summary judgment was held by telephone on June 21, 1993. On June 24, 1993, plaintiffs’ counsel requested by letter to the Court that the Court not rule on the pending motions because the case would become moot in light of the statement by defense counsel at oral argument that the final recovery plan would be complete by August 6,1993, information plaintiffs’ counsel had been provided at least three weeks prior to the hearing date. Defendants requested by reply letter that the Court proceed with its deliberation on the pending motions.

On August 12, 1993, defendants informed the Court and opposing counsel that completion of the final recovery plan would be delayed until August 13, 1993.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Center for Biological Diversity v. Scarlett
452 F. Supp. 2d 966 (N.D. California, 2006)
National Wildlife Federation v. Norton
386 F. Supp. 2d 553 (D. Vermont, 2005)
Vieques Conservation & Historical Trust, Inc. v. Martinez
313 F. Supp. 2d 40 (D. Puerto Rico, 2004)
Klamath Siskiyou Wildlands Center v. Babbitt
105 F. Supp. 2d 1132 (D. Oregon, 2000)
Strahan v. Linnon
967 F. Supp. 581 (D. Massachusetts, 1997)
Earth Island Institute v. Christopher
942 F. Supp. 597 (Court of International Trade, 1996)
Defenders of Wildlife v. Browner
909 F. Supp. 1342 (D. Arizona, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
863 F. Supp. 1277, 25 Envtl. L. Rep. (Envtl. Law Inst.) 20380, 1994 U.S. Dist. LEXIS 19653, 1994 WL 532328, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oregon-natural-resource-council-v-turner-ord-1994.