Opladen v. Town of Islip

172 Misc. 726, 16 N.Y.S.2d 13, 1939 N.Y. Misc. LEXIS 2484
CourtNew York Supreme Court
DecidedOctober 30, 1939
StatusPublished
Cited by2 cases

This text of 172 Misc. 726 (Opladen v. Town of Islip) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Opladen v. Town of Islip, 172 Misc. 726, 16 N.Y.S.2d 13, 1939 N.Y. Misc. LEXIS 2484 (N.Y. Super. Ct. 1939).

Opinion

Hallinan, J.

This is a proceeding, pursuant to section 197 of the Highway Law, for the appointment of three commissioners to ascertain and determine petitioner’s damages resulting from a change of grade to the highway known as South Country road or Middle [727]*727road, in the town of Islip, extending from Sayville to Bayport, 'Suffolk county, N. Y.

Petitioner’s verified claim for damages was filed with the town clerk on June 16,1937. By respondent’s answer, verified January 4, 1938, the material allegations of the petition, verified November 35, 1937, were denied. Said answer also contains three affirmative defenses. The first alleges “ that at the time of the repairing, grading and macadamizing * * * and for some time prior thereto, the said South Country Road or Middle Road was not a town highway.” The second alleges that at the times referred to in the petition the highway in question was not macadamized from curb to curb, as required by section 197 of the Highway Law, so as to enable petitioner to recover damages. The third alleges “ that at the time of the repairing, grading and macadamizing * * * South Country Road or Middle Road was a county highway.” Thereafter the town moved for judgment on the pleadings. This motion was denied by Special Term (Matter of Opladen, N. Y. L. J. Oct. 20, 1938, p. 1221) and no appeal from the order thereon was ever taken.

According to the memoranda submitted by the respective parties after the trial of the issues raised' by the pleadings herein, the following questions are presented: .

(1) The effect of the order denying judgment on the pleadings.

(2) Whether petitioner’s claim was filed within the time limited by section 197 of the Highway Law, that is, “ within sixty days after such change of grade is effected.”

(3) Whether, notwithstanding an affirmative answer to issue No. “(2),” the petition must nevertheless be dismissed by reason of an alleged changed status of South Country road or Middle road, from a town to a county highway.

(1) The court is of the opinion that the decision of the Special Term denying the town’s motion for judgment on the pleadings, established, as the law of the case, the sufficiency of petitioner’s notice of claim and petition, and nothing else. In its memorandum the learned Special Term referred specifically to the timeliness of the filing of petitioner’s claim for damages on the 16th of June, 1937, in relation to the allegation in the notice and petition that the work was completed on the 25th of May, 1937. In other words, assuming that the work was completed within the meaning of section 197 of the Highway Law, on the 25th of May, 1937, as pleaded, the filing of a notice of claim on June 36, 3937, was timely; but the issues of fact raised by the denials, in the answer, of petitioner’s allegations as to the completion date, etc., still remained for determination at the trial.

[728]*728(2) Plans for. the " Proposed Reconstruction of Brown’s ."Creek Bridge, Sayville, Suffolk County, New York, .Town .of Islip,” were approved on September 8,,-1936, by the superintendent of. highways.

At a meeting of .the town board of Islip, held on October 13,1936; the following resolution was-duly adopted:

“Resolved that bids-for the construction of .the approaches at Brown’s Creek, - Bayport, be' awarded to the lowest bidder - that complied with the bid requirements, i. e., E.- L,- North for the -sum of $17,924.50.” .

■ .Pursuant to such resolution;- a contract was entered into by the respondent with E. L. North, of Islip, on-October 13, 1936, for the construction of said approaches at a total-cost .of $-17,924.50. Page 3 of said contract contains the breakdown of the cost into-.the following seventeen units: , ■

9 Clearing & Grubbing
Earth Excavation
Unclassified Excavation
Borrow
Preparing Fine Grade
Trimming Shoulders
yitrified.CIay Pipe-12” Diam.
Reinf. Cone. Pipe-Class 1 A ’-12" Diam.
Portland Cement.
Class ‘ C ’ Concrete
Metal Reinf. for.Cone. Pavement
Mise. Iron & Steel
‘Concrete Guide Posts
'Cement Cone. Pav’t-1:2:3-l/2 Mix
Concrete Sidewalks
Concrete Curb
Breaking Up Concrete Only.”

According to the testimony, the fill or earth was dredged from the creek and placed over the right of way during November and December, 1936, where it remained until the 17th of March, 1937, when cement or concrete for the highway was poured and allowed tó set' until the 27th of March, 1937, at which time traffic was resumed; but the work balled for by the contract in question was not completed until the 19th of May, 1937, and it was not until the'25th óf May, 1937, that the town board adopted a resolution"" approving the work done * * * and that the final payment-due on the contract be paid.”' The contractor was paid in five different installments' as follows, based on as many " estimates ” of the'work completed, submitted by him: • ■ '

[729]*729Date of. Estimate Date of Cheek Amount
January 7, 1937 January 11,1937 $2,448 72
February 23, 1937 February 24, 1937 ' 2,115 00
March 23, 1937 . March 24, 1937 • 7,418 88
April 19, 1937 April 20, 1937 , ■ 3,247 20
May 19, 1937 May 28, 1937 2,694 70
Total $17,924 50

On page 6 of the brief dated July 6, 1939, submitted on behalf of the town, it is contended that only the sum of approximately $2,600 (the fifth payment) out of a total contract price aggregating some $17,000 “ was paid after the highway had been opened to traffic, to wit, March 27, 1937.” This is obviously an error, for, in addition to the final payment of $2,694.70 pursuant to the final estimate of May 19, 1937, the sum of $3,247.20 was paid on April 20, 1937, pursuant'to the estimate of April 19, 1937. Thus, a total of $5,941.90, Of about thirty per cent of the full cost of the job, was paid after March 27,1937, the date when traffic was resumed.

The work embraced by the fourth and fifth estimates consisted of excavating, preparing fine grade, trimming shoulders, putting in concrete curbing, laying concrete sidewalks, putting in catch basins and guide posts, and breaking up old concrete.

The town urges that whatever damages occurred by reason of the change in grade, were suffered by the petitidner between December, 1936, when the work was started, and March 27, 1937, when traffic was resumed on the highway, and that whatever work was done subsequent to that event has no bearing on the time when change of grade is effected.”

With this contention the court is not in accord. The work performed by the contractor was the uninterrupted performance of a contract

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heezen v. Aurora County
157 N.W.2d 26 (South Dakota Supreme Court, 1968)
Cataldo v. Town of Hempstead
25 Misc. 2d 489 (New York Supreme Court, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
172 Misc. 726, 16 N.Y.S.2d 13, 1939 N.Y. Misc. LEXIS 2484, Counsel Stack Legal Research, https://law.counselstack.com/opinion/opladen-v-town-of-islip-nysupct-1939.