Opinion No. Oag 8-87, (1987)

76 Op. Att'y Gen. 29
CourtWisconsin Attorney General Reports
DecidedMarch 16, 1987
StatusPublished

This text of 76 Op. Att'y Gen. 29 (Opinion No. Oag 8-87, (1987)) is published on Counsel Stack Legal Research, covering Wisconsin Attorney General Reports primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Opinion No. Oag 8-87, (1987), 76 Op. Att'y Gen. 29 (Wis. 1987).

Opinion

WILLIAM A.J. DRENGLER, Corporation Counsel Marathon County

You asked my predecessor for an opinion on the following question:

Given the history and judicial interpretation of sec. 66.29 (7), Stats., does a public entity have discretionary power to demand a full and complete list of all the subcontractors and suppliers that a bidder will contract with on a given project, and the class of work to be performed by each?

More specifically, you asked whether Marathon County can consider a bid invalid if the proposal does not contain a complete list of material suppliers and subcontractors, in four different factual settings.

As a general rule, bids for municipal contracts must substantially comply with all requirements specified in statutes, ordinances and bid advertisements. 10 McQuillin MunicipalCorporations § 29.65 (3d ed. 1981). Moreover, a municipality can generally decline a bid for failure of literal compliance with specifications as advertised. Id. You explain that Marathon County currently requires a list of subcontractors through its County Project Manual, and specifies that failure to comply is grounds to reject the bid as invalid. Your question, then, is whether section 66.29 (7), Stats., effectively overrides the general rule and limits municipal authority to reject certain bids. The statute provides in relevant part:

BIDDER'S CERTIFICATE. On all contracts the bidder shall . . . submit a list of the subcontractors he proposes to contract with, and the class of work to be performed by each, provided that to qualify for such listing such subcontractor must first submit his bid in writing, to the general contractor at least 48 hours prior to the time of the bid closing, which list shall not be added to nor altered without the written consent of the municipality. A proposal of a bidder shall not be invalid if any subcontractor *Page 30 and the class of work to be performed by such subcontractor has been omitted from a proposal; such omission shall be considered as inadvertent, or that the bidder will perform the work himself.

This language seems to require the kind of bid specifications that Marathon County now issues, but at the same time directs that a bid "shall not be invalid" for failure to comply with the requirement. Conceivably, the last sentence of the section actually prohibits a municipality from rejecting a bid solely because of an incomplete subcontractor list.

However, the legislative history of section 66.29 (7) leads me to conclude that the Legislature never intended such a severe restriction on municipal authority to reject bids. Rather, the debate over amendments to this section has been whether bidders must submit subcontractor lists as a statutory mandate, or only if municipalities so require. Before 1955, the statute unequivocally required that contractors include in bid proposals "a full and complete list of all the proposed subcontractors and the class of work to be performed by each . . . ." Sec. 66.29 (7), Stats. (1953). A 1955 amendment removed the mandatory subcontractor list, and instead provided that municipalities could require such a list at their own discretion. Ch. 406, sec. 2, Laws of 1955. Even under the amended statute, though, a municipality could reject a bid that failed to comply with its subcontractor listing requirement. See Druml Co. v. Knapp,6 Wis.2d 418, 94 N.W.2d 615 (1959).

A 1959 amendment ultimately produced the current language, but began as an effort to reinstate the mandatory subcontractor lists. The original bill, 1959 Assembly Bill 574, simply restored the pre-1955 language. Subcontractors advanced this change, complaining that general contractors subjected subcontractors to "bid-peddling" when the bid specification did not require a subcontractor list. See letter from Peter Woboril, Wisconsin Council of Painting and Decorating Contractors of America, to Assemblyman Glenn Henry, Labor Committee, April 17, 1959; in 1959 A.B. 574 drafting file. General contractors opposed the amendment, as did the League of Wisconsin Municipalities, which argued that an inadvertent omission of a subcontractor from a bid might subject a municipality to "nuisance litigation." Id. Municipalities, in other words, worried that a mandatory subcontractor list reduced their *Page 31 flexibility and exposed bid decisions to challenge on technical grounds.

Hoping to eliminate "bid-peddling" but also meet the municipalities' concerns, the subcontractors offered an amendment providing that a bid proposal "shall not be deemed invalid if the bidder establishes to the satisfaction of the municipality that any subcontractor . . . has been inadvertently omitted from a proposal." Id. 1959 A.B. 574, Amendment 1. This amendment, which the assembly adopted, is the source of the current provision that a bid "shall not be invalid" because of an omitted subcontractor, and the context shows that one purpose was to protect municipal discretion. The bidder was required to submit a subcontractor list, but the municipality could overlook inadvertent omissions from the list without fear that an unsuccessful bidder would challenge the accepted bid as invalid. Similarly, the municipality could reject a bid because the list was incomplete, subject only to the bidder's "inadvertent omission" defense.

The senate amended the assembly bill by introducing the language now in the statute, but nothing in the legislative history shows an intent to alter the basic thrust of the subcontractors' proposal: reinstate the mandatory subcontractor list, but protect municipalities from litigation over that requirement. The senate version, in fact, tightened the control on general contractors, limiting the subcontractor list to those who submit bids in writing at least forty-eight hours before bid closing. The amendment also fully protected a municipal decision to accept a bid, specifying that a bid "shall not be invalid" if a qualified subcontractor is omitted; such omissions are deemed inadvertent (or evidence that the bidder plans to perform the work) rather than subject to proof as in the assembly version. Standing alone, that same language seems to prohibit any rejection of a bid based on omitted subcontractors. However, such a reading effectively nullifies the subcontractor list requirement, and removes traditional municipal authority to reject proposals that violate bid specifications. The history of section 66.29 (7) shows no hint that the Legislature perceived municipal rejection of bids as a problem, or that it intended to place significant restrictions on municipal power to enforce bidding requirements.

In my view, section 66.29 (7) simply provides that omission of a subcontractor from a proposal does not render the proposal statutorily invalid. When a municipality receives a bid containing an *Page 32 incomplete subcontractor list, it must consider the bid. The municipality can either accept the bid or notify the general contractor that it intends to reject the bid for failure to comply with bid specifications. If the contractor can produce evidence that it acquired timely written bids, then the omission is presumptively inadvertent. Likewise, if the contractor indicates an intention and an ability to perform the work itself, the bid may not be rejected on that basis.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Druml Co. v. Knapp
94 N.W.2d 615 (Wisconsin Supreme Court, 1959)
Boehck Construction Equipment Corp. v. Voigt
115 N.W.2d 627 (Wisconsin Supreme Court, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
76 Op. Att'y Gen. 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/opinion-no-oag-8-87-1987-wisag-1987.