Ophir Silver Mining Co. v. Carpenter

4 Nev. 534
CourtNevada Supreme Court
DecidedJuly 1, 1868
StatusPublished
Cited by39 cases

This text of 4 Nev. 534 (Ophir Silver Mining Co. v. Carpenter) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ophir Silver Mining Co. v. Carpenter, 4 Nev. 534 (Neb. 1868).

Opinion

By the Court,

Lewis, C. J.

This action is founded upon an alleged unlawful diversion of water, whereby it is claimed the plaintiff was damaged in the sum of three thousand dollars, for which judgment is asked against the defendants. An injunction is also prayed for to restrain any future diversion.

[542]*542The defendants claim tbe right to divert the full quantity of water taken by them, by reason of an appropriation prior in point of time to any claim or appropriation by the plaintiff. And thus this controversy may be determined upon its merits by the resolution of the question which of the parties made the first appropriation of the water diverted by the defendants.

We have carefully examined the voluminous record in the case for the purpose of determining this main question, and as our conclusions are in favor of the plaintiff, the consideration of any minor questions is rendered unnecessary.

We concede for the purposes of the present discussion (although it is a fact by no means beyond doubt) that the grantors of the defendants made claim to and intended to appropriate the full volume of water now claimed by them long prior to the time when the plaintiff’s grantors appropriated what is claimed by it, and place our decision entirely upon the failure on the part of those from whom defendants derive their title to prosecute their claim to consummation with that diligence which is necessary when it is attempted to make the final act of appropriation relate to the time when the first step was taken or the first act done to make it. ' We propose to rely solely upon the undisputed facts and uncontra-dicted evidence to support the conclusion at which we have arrived, the substance of which may be thus stated:

In the spring of the year 1858, J. H. Rose, the grantor of defendants, desiring to convey water to the village of Dayton, from the Carson River, constructed for that purpose a ditch, about four and a half miles in length, and of dimensions varying at different points. At its immediate head it was sixteen feet wide. For a distance of one-fourth of a mile below it averaged seven and one-half feet wide on top, and two and one-half feet deep. Its general size below that point was three and one-half feet wide at the top, two and one-half feet on the bottom, and two and one-half feet deep. The ditch was thus constructed in the year 1858. In the following year water was run through it to Dayton. And it remained pretty much in this condition until the fall of the year 1862, at which time Rose entered into a contract with Shanklin and McConnell for its enlargement to its present capacity. Work was immedi[543]*543ately commenced under that contract, and the present ditch completed early in 1865. Under this contract an entirely new survey was made, and the water was taken from the river at a point one-quarter of a mile above the head of the old ditch, and on the oppo- ■ site side of the river. The size of this new ditch, which is called the Shanklin and McConnell ditch, is thirteen feet in width at the top, nine feet on the bottom, and four feet deep. Its flumes are six feet by three, with a fall of one-fifth of an inch to the rod. The volume of water which can be run through it is ten times greater than could have been run through the old Rose ditch — its capacity being fifty-seven cubic feet per second, while the old ditch was capable of discharging only about four and a half feet.

The grantors of the plaintiff made no claim to any water until the month of July, a. d. 1859. In that year they diverted the water from the river at a point some distance below the head of the Rose ditch, used some quantity of it that year, and in the fall of 1860 completed their ditch to its present capacity; and have ever since used the water thus diverted for motive power.

The defendants claim that the ditch as constructed or enlarged by Shanklin and McConnell is in accordance with the original design of Rose, from whom they acquire their right; that such design was manifested by the fact that his first ditch was of as great capacity for a quarter of a mile from its head as the present ditch, and hence that their right to the entire volume of water which the present ditch will carry must relate to the time when Rose did the first act towards appropriating it, which was in the spring of the year 1858.

The plaintiff concedes that the defendants, as the first appropriators, have the right, first, to divert through their ditch so much of the water of the river as would have run through the old ditch. It is then claimed that the plaintiff is entitled to sufficient water to fill its ditch, counsel arguing on its behalf that the grantors of defendants had no right to increase the capacity of the old ditch to its prejudice. Where the right to the use of running water is based upon appropriation, and not upon an ownership in the soil, it is the generally recognized rule here that priority of appropriation gives the superior right. When any work is necessary to be done to [544]*544complete the appropriation, the law gives the claimant a reasonable time within which to do it, and although the appropriation is not deemed complete until the actual diversion or use of the water, still if such work be prosecuted with reasonable diligence, the right relates to the time when the first step was taken to secure it. If,' however, the work be not prosecuted with diligence, the right does not so relate, but generally dates from the time when the work is completed or the appropriation is fully perfected.

As we have already stated, we concede the fact, for the present, that Rose designed, when he constructed his ditch in the year 1858, to enlarge it to the capacity of the present ditch, and if he has shown that the design thus conceived was prosecuted with a reasonable degree of diligence until its completion, then the defendants’ right to that quantity of water now claimed by them will relate back to the spring of 1858, and thus ante-date the plaintiff’s right eighteen months or two years, thereby giving them the superior right. But in our opinion the evidence shows an utter failure on the part of Rose to prosecute his original design with that diligence which the law requires. The manner in which this work was prosecuted we gather from the testimony of Rose himself. In the year 1858 the ditch was constructed, and a great deal of work was necessarily done. In the succeeding year also a considerable amount of work was done in cleaning out the ditch and enlarging it in some places. Some time in the summer of this year the ditch was completed to such an extent that a small quantity of water was run through it to Dayton. It is very doubtful whether any work was done this year towards a systematic enlargement of the ditch for the purpose of increasing its general capacity. Rose himself thus describes the work done: I was trying to get more water through; so wherever earth or rock slid in from the sides of the ditch, all the men hired by the day were instructed to dig or throw it out, and to throw out all the loose dirt or gravel that was not worked out by the water running through.” However this may be, it is certain that in the succeeding year, that is in 1860, nothing whatever was done towards enlargement. Indeed the only thing done during the entire year was the employment of two men, who were engaged for a few days in throwing out rock from the ditch. This is all the work that [545]*545was done between the fall of 1859 and the month of May, A. D. 1861, a period of more than eighteen months. As counsel for appellant very aptly remarked,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Office of the State Eng'r v. Gray
2021 NMCA 066 (New Mexico Court of Appeals, 2021)
Rand Props., Llc Vs. Filippini
484 P.3d 275 (Nevada Supreme Court, 2021)
United States v. Orr Water Ditch Company
256 F.3d 935 (Ninth Circuit, 2001)
United States v. Orr Water Ditch Co.
256 F.3d 935 (Ninth Circuit, 2001)
Kroeger v. King
746 P.2d 630 (Nevada Supreme Court, 1987)
United States v. Alpine Land & Reservoir Co.
503 F. Supp. 877 (D. Nevada, 1980)
Bailey v. State
594 P.2d 734 (Nevada Supreme Court, 1979)
Sloat v. Turner
563 P.2d 86 (Nevada Supreme Court, 1977)
Carbon Canal Co. v. Sanpete Water Users Ass'n
425 P.2d 405 (Utah Supreme Court, 1967)
Taussig v. Moffat Tunnel Water & Development Co.
106 P.2d 363 (Supreme Court of Colorado, 1940)
Steptoe Live Stock Co. v. Gulley
295 P. 772 (Nevada Supreme Court, 1931)
R. E. Taylor Syndicate v. James
243 S.W. 1105 (Court of Appeals of Texas, 1922)
Crosman v. Southern Pacific Co.
173 P. 223 (Nevada Supreme Court, 1918)
United States v. North American Oil Consolidated
242 F. 723 (S.D. California, 1917)
Grant Realty Co. v. Ham, Yearsley & Ryrie
165 P. 495 (Washington Supreme Court, 1917)
United States v. McCutchen
234 F. 702 (S.D. California, 1915)
Rio Puerco Irrigation Co. v. Jastro
141 P. 874 (New Mexico Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
4 Nev. 534, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ophir-silver-mining-co-v-carpenter-nev-1868.