O'Neill v. Seglin Construction Co.

158 Misc. 742, 286 N.Y.S. 849, 1935 N.Y. Misc. LEXIS 1732
CourtNew York Supreme Court
DecidedSeptember 20, 1935
StatusPublished
Cited by1 cases

This text of 158 Misc. 742 (O'Neill v. Seglin Construction Co.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Neill v. Seglin Construction Co., 158 Misc. 742, 286 N.Y.S. 849, 1935 N.Y. Misc. LEXIS 1732 (N.Y. Super. Ct. 1935).

Opinion

Cotillo, J.

The plaintiff, a bricklayer and a member in good standing of the Bricklayers, Masons and Plasterers International Union of America, having performed work, labor and services in the erection and completion of a new building at the Kings Park State Hospital, Kings Park, Long Island, filed a notice of lien for the value of such work, labor and services. Thereafter this suit was instituted against the defendants Seglin Construction Company, Inc., hereinafter called Seglin, and the Standard Accident Insurance Company, hereinafter called Standard, and various individual defendants, all bricklayers and members of the above union who have also filed liens for wages, to foreclose the lien as filed. Seglin was the contractor for the erection of the above-named building, and Standard the company which bonded the lien.

It is undisputed that Seglin contracted with the State of New York for the erection and completion of a public improvement at Kings Park State Hospital and employed the individual bricklayer lienors to do the brick work on the project. At the time the work was in progress there was a dispute between the union and the Mason Builders Association as to the wage scale to be fixed and paid to members of the union. An agreement to submit the controversy to arbitration was agreed upon. Seglin, on May 11, 1933, entered into an agreement with the union’s New York executive committee as follows:

“ Whereas, the agreed rate of $1.65 per hour for Bricklayers within the territory of the Subordinate Unions terminated on May 1st, 1933; and the determination of an agreed rate of wages for Bricklayers on and after that date is now the subject of Arbitration between the Subordinate Unions and the Mason Builders Association of New York;
It is hereby agreed that the Subordinate Unions will furnish to and the Contractor will hire only Bricklayers who are members of the Bricklayers’, Masons’ & Plasterers’ International Union, of America, to man any job which the Contractor may undertake to do within the territorial jurisdiction of the Subordinate Unions; the Contractor will pay the members of the Subordinate Union manning its said job wages at the rate of $1.25 per hour for eight hours per day, until the decision of the arbitrators in the pending arbitration proceedings between the Subordinate Unions and the Mason Builders Association of New York, and on and after the making of the award by the arbitrators the Contractor will pay to the [744]*744members of said Subordinate Union manning its said job, wages at the rate fixed in said award.”

The instrument then concluded with a paragraph which charged the contractor, Seglin Construction Company, Inc., with the duty of holding in escrow the difference between the wages actually paid the bricklayers employed on this public project, and the amount that they would be entitled to receive if paid at the rate of one dollar and sixty-five cents per hour; in the event the award of the arbitrators provided for a rate in excess of one dollar and twenty-five cents per hour, the contractor was obligated to pay that difference from the escrow moneys.

The board of arbitrators, on August 4, 1933, determined and handed down their final decision and award fixing the rate of wages for bricklayers at one dollar and sixty-five cents an hour. The failure of Seglin to pay the difference between one dollar and twenty-five cents an hour and one dollar and sixty-five cents caused the filing of the liens and the institution of this suit.

The defendants Seglin and Standard not only deny that a valid award was made in this arbitration proceeding on August 4, 1933, but affirmatively allege that the proceeding in question terminated in another and entirely different award on July 15, 1933, and that the arbitrators thereupon became functi officio and without power to act further in the matter. The answer of these defendants also affirmatively alleges that the so-called award of August 4, 1933, was null and void on the ground that it was procured by undue means and evident partiality on the part of the arbitrators purporting to make the same and, more particularly, by misconduct on the part of these arbitrators in following the dictation of the Secretary of Labor of the United States rather than their own judgment based upon the evidence submitted to them. By way of an additional affirmative defense it is alleged that the so-called award of August 4, 1933, was null and void because the arbitrators were not sworn in the manner provided by section 1452 of the Civil Practice Act, the requirement of the statute in- this respect not having been waived by the written consent of the parties or their attorneys. It is further alleged that the Seglin Construction Company, Inc., duly revoked its agreement to be bound by the award in this arbitration prior to the rendition of the so-called award of August 4, 1933.

Finally, as more fully appears from the stipulation entered into in advance of trial, the notices of lien of the plaintiff and several of the defendant lienors were concededly filed in the office of the Comptroller of the State of New York either on November 18 or November 20, 1933, or over three months prior to the commence[745]*745ment of the present action, it having been conceded upon the trial that the summons and complaint herein were .not served upon the Seglin Construction Company, Inc., until February 23, 1934, and upon the Standard Accident Insurance Company until February 26, 1934. As a consequence these liens, as affirmatively alleged in the amended answer of the defendants Seglin Construction Company, Inc., and Standard Accident Insurance Company, have lapsed and been discharged by operation of law (Lien Law, §§ 18, 21).

The court will first consider the defendants’ contention that the liens have lapsed and have been discharged by operation of law. In determining this question the rights of the plaintiff and the defendant lienors must be kept separate. The liens of all were filed between November 18, 1933, and January 20, 1934. The individual defendants served a notice of appearance in this action on February 16, 1934, and a notice of pendency was filed on February 17,1934. Seglin was served on February 23,1934, and Standard on February 26, 1934. Sections 18 and 21 of the Lien Law, as applicable here, provide as follows:

§ 18. Duration of lien under contract for a public improvement. If the lien is for labor done or materials furnished for a public improvement, it shall not continue for a longer period than three months from the time of filing the notice of such lien, unless an action is commenced to foreclose such lien within that time, and a notice of the pendency of such action is filed with the comptroller of the state or the financial officer of the municipal corporation with whom the notice of such lien was filed, or unless an order be made by a court of record, continuing such lien, and a new docket be made stating such fact.”
“ § 21. Discharge of lien for public improvement. A lien against the amount due or to become due a contractor from the State or a municipal corporation for the construction of a public improvement may be discharged as follows: * * *
“ 2. By lapse of time as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O'Neill v. Seglin Construction Co.
248 A.D. 684 (Appellate Division of the Supreme Court of New York, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
158 Misc. 742, 286 N.Y.S. 849, 1935 N.Y. Misc. LEXIS 1732, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oneill-v-seglin-construction-co-nysupct-1935.