O'Neil Engineering Co. v. First Nat. Bank of Paris

222 S.W. 1091, 1920 Tex. App. LEXIS 691
CourtTexas Commission of Appeals
DecidedJune 16, 1920
DocketNo. 104-2940
StatusPublished
Cited by21 cases

This text of 222 S.W. 1091 (O'Neil Engineering Co. v. First Nat. Bank of Paris) is published on Counsel Stack Legal Research, covering Texas Commission of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O'Neil Engineering Co. v. First Nat. Bank of Paris, 222 S.W. 1091, 1920 Tex. App. LEXIS 691 (Tex. Super. Ct. 1920).

Opinion

SADLER, p. J.

The statement of the case as given in the opinion by the Court .of Civil Appeals is so full and complete that we adopt same as shown in 176 S. W. 74. As aptly stated by Associate Justice Hodges:

“The only errors assigned are those which question the court’s legal conclusions from the foregoing facts. To summarize: These facts show conflicting claims to a special fund authorized by law to be disbursed under the order of the board of permanent road commissioners for justice precinct No. 1 of Lamar county. The appellant [defendant in error] claims that fund — or rather so much of it as may be necessary to satisfy its debt against the engineering company — by virtue of parol assignments made before any of the money due upon the contract with the board had been earned by the engineering company. The surety company [Fidelity & Deposit Company of Maryland, and Title Guaranty Insurance Company, acting together] claims this fund upon three different -written assignments. The first is referred to as the application agreement made at the time the contract of suretyship was entered into and as a part of the consideration of that contract; the second is another written assignment, dated February 26, 1913; and the third still another agreement made on the 8th day of August, 1913, at the time it took over, or agreed to take over, the contract of the engineering company with the board. The surety company also insists upon its right of subrogation to all of the claims, securities, and,' demands owned or held by the board against the engineering company at the time the latter defaulted in the performance of its contract. [1092]*1092The question then is, Which of these opposing claims should he given the preference?”

The trial court held that the sureties on the bond of the O’Neil Engineering Company given to the board of road commissioners to insure performance of the road contract were entitled to the fund involved. On appeal, the Court of Civil Appeals held that the bank had a prior right in the fund to the extent of its debt against the engineering company. To this judgment writ of error was granted.

Opinion.

After a very careful consideration of the able presentation by counsel of the questions involved, we have concluded that the Court of Civil Appeals, erred in the disposition made of this case.

[1, 2] In reaching this conclusion, we have recognized the difficulty involved. At the time the contract was entered into between the O’Neil Engineering Company and the board of road commissioners, it was therein specially stipulated that a bond should be given as required by law, guaranteeing performance by the engineering company of the contract, in which it obligated itself, in accordance with the plans and specifications furnished, to ■ construct the roads contemplated. It was further stipulated 'as a protection to the board that 15 per cent, of each monthly estimate of the work completed should be retained by it until all of the work had been completed, in accordance with the contract. It was stipulated that between the 1st and 10th of each month, the engineer who was acting for the board should make an estimate of the amount of work which had been completed during the previous month; that he should deduct therefrom fifteen per cent, and such other amounts as might be proper to be retained by the board until the completion of the contract; that the remaining portion of the estimate should be paid over to the engineering company for the work which it had completed during the previous month. The contractor could not require payment of this amount before the fourth Monday in the month in which the estimate had been approved. 7

It may not be amiss to discuss the relationship existing between the board of road commissioners and the engineering company under the contract. The board provided for its protection against default on the part of the engineering company. The retention of 15 per cent, of the monthly estimates and such other deductions as its engineer might make, together with the bond guaranteeing performance, were provided as sufficient to recoup the board for any dereliction by the engineering company. We think that it is clear that this construction of the contract is in consonance with its terms and with the intention on the part of the board. As a ■guaranty of faithful performance — as an indemnity for its protection — it looked to the retained percentages and deductions by its engineer and the bond required. The engineering company accepted for itself, with the consent and permission of the board, such an amount of each monthly estimate as remained after the deductions had been made by the engineer in charge. This amount nay, for convenience, be treated as 85 per cent, of each monthly estimate.

At the end of each month, after the work began, the engineering company, it then being in performance of the contract, was entitled to receive 85 per cent, of each estimate, without any retained claim thereto by the board. This board did not put any restraint upon this 85 per cent, to protect against any future dereliction, failure, or incapacity on the part of the engineering company in the performance of the contract. In the absence of fraud or mistake, when the board approved the estimate submitted by the engineer for any month, the amount of such estimate, the contract then being in performance by the engineering company, was set apart from the general fund to meet the obligation to the contractor at its maturity.

What was the position of the surety or bondsman who sought to indemnify the board against loss or guarantee the faithful execution of the contract by the principal? They were charged with knowledge of all of the terms, stipulations, and legal consequences of the contract upon which they became guarantors. If we treat the contract, which we think proper to do, as being incorporated in and forming a part of the bond, then the surety company occupied exactly the same position in relation to it as that of the principals themselves. The surety company had no greater right in the contract or under it than had the board. It accepted the surety-ship with knowledge that a certain per cent, of each monthly estimate for work completed during that month was to become due and payable to and subject to the possession of its principal in the bond without restraint.

An examination of the application for suretyship made by the contractor to the surety companies further confirms the position here taken. The assignment contained in the application had relation to the condition which existed, not at the time of making the contract, but at the time of the breach and failure of performance on the part of the principal. As long as the eon- . tractor was carrying out his obligation in performing the terms of his contract, the surety company had no right to arrest or hold for its protection, either under the application assignment or by equitable subro-gation, any part of the estimate approved by the board, ordered paid, and subject to the demand of the contract. It entered into its suretyship relying for protection upon the [1093]*1093retained percentage and its faitli in tie contractor. It reserved no rights against any earned and approved amounts subject to tie demand of the contractor prior to breach by liim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

OTC Petroleum Corp. v. Brock Exploration Corp.
835 S.W.2d 792 (Court of Appeals of Texas, 1992)
Argonaut Ins. Co. v. ABC Steel Products Co., Inc.
582 S.W.2d 883 (Court of Appeals of Texas, 1979)
Corpus Christi Bank & Trust v. Smith
512 S.W.2d 761 (Court of Appeals of Texas, 1974)
Brown-McKee, Inc. v. City of Andrews
501 S.W.2d 714 (Court of Appeals of Texas, 1973)
Trinity Universal Insurance Co. v. Bellmead State Bank of Waco
396 S.W.2d 163 (Court of Appeals of Texas, 1965)
Travelers Indemnity Company v. Snyder National Bank
361 S.W.2d 926 (Court of Appeals of Texas, 1962)
LeBlanc, Inc. v. First National Bank of Bay City
320 S.W.2d 886 (Court of Appeals of Texas, 1959)
Scarborough v. Victoria Bank & Trust Co.
250 S.W.2d 918 (Court of Appeals of Texas, 1952)
Citizens National Bank at Brownwood v. Ross Construction Co.
206 S.W.2d 593 (Texas Supreme Court, 1947)
Ross Const. Co. v. Citizens Nat. Bank at Brownwood
201 S.W.2d 244 (Court of Appeals of Texas, 1947)
Friedman v. American Surety Co. of New York
154 S.W.2d 659 (Court of Appeals of Texas, 1941)
Employers' Casualty Co. v. City of Wolfe City
35 S.W.2d 694 (Texas Supreme Court, 1931)
Employers' Casualty Co. v. Wolfe City
35 S.W.2d 694 (Texas Supreme Court, 1931)
Employers Casualty Co. v. County of Rockwall
35 S.W.2d 690 (Texas Supreme Court, 1931)
Hewitt v. Buchanan
4 S.W.2d 169 (Court of Appeals of Texas, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
222 S.W. 1091, 1920 Tex. App. LEXIS 691, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oneil-engineering-co-v-first-nat-bank-of-paris-texcommnapp-1920.