Oneida Township v. Eaton County Drain Commissioner

499 N.W.2d 390, 198 Mich. App. 523
CourtMichigan Court of Appeals
DecidedMarch 2, 1993
DocketDocket No. 132895
StatusPublished
Cited by3 cases

This text of 499 N.W.2d 390 (Oneida Township v. Eaton County Drain Commissioner) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oneida Township v. Eaton County Drain Commissioner, 499 N.W.2d 390, 198 Mich. App. 523 (Mich. Ct. App. 1993).

Opinion

Per Curiam.

Defendant, the Eaton County Drain Commissioner, appeals as of right an order of the Eaton Circuit Court that granted summary disposition to the plaintiff township and intervening plaintiffs, persons owning property within a drainage district potentially subject to a special assessment, pursuant to MCR 2.116(C)(8). We reverse and remand for further proceedings.

New material facts are disputed on appeal. In early 1986, officials of Oneida Township contacted defendant regarding the possible improvement of the Reed Drain to accommodate future development in the township. A petition for improvement was prepared, and defendant appointed a board of determination. In June 1986, the board of determination filed a notice of determination of necessity. Defendant directed an engineering firm to prepare preliminary plans for the project, which resulted in a plan whose estimated cost to complete exceeded $1 million. Details of the plan were made known to the township at a meeting held in the spring of 1987.

The township and the landowners in the drainage district were concerned about the expense of the project. In response, the engineering firm developed six alternative plans. The firm prepared construction drawings, conducted soil boring, and performed other tests. Defendant selected one of the alternatives and began to obtain the necessary rights of way. Defendant then solicited bids for the project and awarded a contract in January 1990. [526]*526The following month, defendant filed an order of apportionment. Several property owners filed appeals with the Eaton County Probate Court, and a board of review was appointed. Before the board could meet, plaintiffs obtained a temporary restraining order from the circuit court that restrained the board from meeting and enjoined defendant from beginning construction. According to plaintiffs, the proposed drain would have conferred no benefit that was not provided by the existing drain, was not the drain that they had originally sought, and had not been constructed in a timely manner.

The parties stipulated the entry of a permanent injunction against construction of the drain, but reserved the question how the costs incurred up to that point would be allocated. The stipulation effectively killed the project. Defendant thereafter moved to allow apportionment of the costs.1 On July 9, 1990, plaintiff Robert Soltow, a landowner, filed a motion to dismiss, arguing that because the project had never been completed, no benefits had inured to plaintiffs’ lands and, therefore, costs could not be assessed. According to plaintiffs, MCL 280.306; MSA 11.1306, the provision of the Drain Code that permits the recovery of expenses for uncompleted projects, was unconstitutional in light of our Supreme Court’s decision in Dixon Road Group v Novi, 426 Mich 390; 395 NW2d 211 (1986).2 The trial court did not believe that § 306 [527]*527was unconstitutional, but held that no assessment could be levied until a benefit from the project had been conferred on the property to be assessed. Plaintiffs’ motion was granted, and defendant now appeals.

MCL 280.306; MSA 11.1306 provides, in relevant part:

Whenever revolving fund moneys have been expended or a drainage district has become obligated to pay expenses for engineering, legal and administrative services, by action of the drain commissioner or drainage board and no improvement has been completed . . . the drain commissioner . . . may report such fact to the board of supervisors. If no improvement has been completed within 5 years subsequent to the . . . entry of the first order of determination . . . the drain commissioner . . . shall report such fact to the board of supervisors. If the sum involved is too small to justify spreading the same over the designated district . . . such board of supervisors may order the sum to be spread against the property of the original petitioners according to such percentage as the commissioners shall deem just and equitable, based on the same beneñt theory as if the improvement had been completed. If the sum involved is large enough to, in the opinion of the board of supervisors, create undue hardship on the original petitioners, the board of supervisors may order the same spread over such designated district and the commissioner shall apportion the cost thereof to the parties benefited in the district as provided in chapter 7

In Dixon, supra, our Supreme Court held that a [528]*528special assessment must be supported by a showing of an increase in the market value of the assessed property in a reasonable proportion to the cost incurred. The courts will intervene where there is a substantial or unreasonable disproportionality between the amount assessed and value accruing to the land as a result of the improvement. Id., pp 401-403. In the present case, the trial court held that because the drain was never completed, there could be no showing of any increase in market value that resulted from the improvement — a logical conclusion.

On appeal, defendant argues only that land has been benefited because the preliminary engineering work and other actions taken before the project was halted remain on hand and would reduce the cost of any future improvements.4 Defendant fails to explain how this "benefit” has increased the market value of the land in the manner envisioned by Dixon, the basis for the trial court’s opinion. In any event, we disagree with defendant’s characterization of the preliminary work as a benefit that would justify an assessment. "Benefits in the remote future, dependent upon [some future improvement], cannot be made the basis for present assessments of benefits.” Dix-Ferndale Taxpayers’ Ass’n v Detroit, 258 Mich 390, 395; 242 NW 732 (1932).5_

[529]*529Although we disagree with defendant’s argument, we believe that a central issue has been overlooked in this case. We do not believe that Dixon is applicable to this case.

The Dixon opinion failed to identify the statutory basis for the special assessments at issue in that case. It is apparent, however, that § 306 was not at issue. Section 306 specifically provides a method for the recovery of expenses in instances where an improvement is not completed, and, hence, no "benefit” in the usual sense of the word is obtained. If the rule of Dixon were applied to a § 306 situation, then we would have no difficulty in concluding that a special assessment for the costs of an uncompleted improvement would be constitutionally unsound for the reason that no increase in market value proportional to the assessment can be shown. We would hesitate to conclude, however, that the Supreme Court intended to invalidate a statute not before it. Statutes enjoy a presumption of constitutionality. Hall v Calhoun Co Bd of Supervisors, 373 Mich 642, 649; 130 NW2d 414 (1964); Mooahesh v Treasury Dep't 195 Mich App 551, 563; 492 NW2d 246 (1992). Whether §306 works an unconstitutional taking without due process of law, Dixon, supra, pp 402-403, is a question of first impression.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Asia Anderson v. Jennifer L Tracy Rn
Michigan Court of Appeals, 2018
Michigan's Adventure, Inc. v. Dalton Township
802 N.W.2d 353 (Michigan Court of Appeals, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
499 N.W.2d 390, 198 Mich. App. 523, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oneida-township-v-eaton-county-drain-commissioner-michctapp-1993.