One North of Boston LLC v. Dhiren Thakkar.

Massachusetts Appeals Court·Decided July 11, 2025·No. 24-P-0756·Unpublished

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

24-P-756

ONE NORTH OF BOSTON LLC

vs.

DHIREN THAKKAR.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

The plaintiff (landlord) brought this action to evict the

defendant (tenant) from an apartment for nonpayment of rent.

The tenant filed counterclaims for breach of the warranty of

habitability and the covenant of quiet enjoyment. After a jury-

waived trial in the Housing Court, the judge found in favor of

the landlord for unpaid rent and in favor of the tenant on his

counterclaims. The landlord appeals, arguing the judge erred in

ruling that the landlord breached the warranty of habitability

and the covenant of quiet enjoyment. We affirm.

Background. We summarize the judge's findings of fact

relevant to this appeal, supplemented with undisputed facts from

the record. See Allison v. Eriksson, 479 Mass. 626, 627 (2018).

The parties signed a one year lease which began on October 14, 2022, and ended on October 13, 2023. The rent was $2,670, due at the first of each month.

Upon moving in, the tenant noticed water damage on the kitchen flooring, and that the "3-layer flooring by the washing machine" was completely rotted and the top layer was "puckering up." Approximately two weeks after moving in, the tenant sent an e-mail message to the landlord's management with his signed "Notice of Condition," which noted the damage on the floor and that "at least one [of the hardwood floors] is completely rotted." A leasing agent thereafter contacted the tenant, and, after a series of communications, a work order was "opened up" in February 2023. Someone came to look at the floor sometime after that, but the damage was not fixed.1 On June 26, 2023, the tenant sent a demand letter to the landlord requesting that the floor be repaired. In the letter,

In November 2022, the tenant showed the landlord's 1 maintenance team that the hot water heater was leaking brown liquid; the team patched it rather than replace it. In February 2023, the tenant's hot water heater stopped working. On Sunday, February 19, 2023, the tenant notified the landlord via an online service request. The heater was removed and replaced two days later, on Tuesday, February 21, 2023. Although the tenant raised this issue in his counterclaims, and the judge concluded that it was a breach of the warranty of habitability, the damages awarded to the tenant were based on the landlord's delay in repairing the kitchen floor, because they were greater than the damages warranted by the brief delay in repairing the hot water heater.

the tenant detailed an incident in which his sock got caught in the rotted flooring. The day after the tenant mailed the letter, Caitlin Bishop (Bishop), the landlord's senior property manager, sent an e-mail message to the tenant discussing the work that needed to be done in the apartment. Bishop suggested the flooring work could be completed on June 30, 2023, but the tenant was not available on that date, so they discussed rescheduling. On July 6, 2023, the landlord sent a letter to the tenant advising him the repair of the floors would take place on July 19, 2023. After this communication, the tenant began speaking directly with Bishop's regional manager.

In July 2023, before the floor had been repaired, the tenant contacted the city of Chelsea's inspectional services department (ISD). ISD conducted an investigation on July 21, 2023, and found violations for, among other things, the damage to the flooring. On August 1, 2023, Bishop sent another letter to the tenant advising him that a full floor replacement would be completed on August 9, 2023. She also explained that because the entire kitchen floor would be replaced, the tenant's property would be moved into his bedroom during the repair. The tenant objected to moving his possessions and also refused to consent to having his property moved to an off-site storage unit. The tenant eventually proposed a repair date of August

16, 2023, and the repair was completed on that date. ISD conducted a reinspection on August 17, 2023, and found the violation for the damaged flooring had been corrected.

The tenant did not pay rent in July 2023. The landlord served a notice to quit to the tenant on July 7, 2023. The landlord commenced this summary process action on August 14, 2023.

On the basis of these facts, the judge concluded that the landlord had proven damages in the amount of $13,350 for unpaid rent. However, the judge also concluded the tenant proved his counterclaims for a breach of the warranty of habitability and a breach of the covenant of quiet enjoyment. The judge found "no credible evidence supporting any other counterclaim or defense of the [t]enant." The judge concluded that the tenant was entitled to $8,010 in damages -- three times his monthly rent. Subtracting this amount from the $13,350 to which the landlord was entitled, the judge determined that the landlord was entitled to $5,340, plus interest and costs. Finally, the judge ordered that if the tenant paid this amount within seven days, judgment for possession would enter for the tenant. The tenant made payment within the seven-day period.

Final judgment entered on January 16, 2024. On the same day, the landlord submitted a "Motion for Clarification and/or

Reconsideration" of the judge's order. On February 16, 2024, the judge issued a memorandum and order denying the landlord's motion. The landlord appeals.2 Discussion. The landlord argues that the judge erred in concluding that he materially breached the implied warranty of habitability and the covenant of quiet enjoyment. "On review of a jury-waived proceeding, we accept the judge's findings of fact unless they are clearly erroneous. . . . We review the judge's rulings on questions of law de novo" (citation omitted). South Boston Elderly Residences, Inc. v. Moynahan, 91 Mass. App. Ct. 455, 462 (2017).

1. Breach of warranty of habitability. "The existence of a material breach [of the warranty of habitability] will be a question of fact to be determined in the circumstances of each case." Boston Hous. Auth. v. Hemingway, 363 Mass. 184, 200

2 The landlord entered his notice of appeal on January 29, 2024. The judge denied the motion for reconsideration on February 16, 2024, and the landlord did not file a subsequent notice of appeal. Because the landlord did not file a new notice of appeal after the denial of the motion for reconsideration, he did not comply with Mass. R. A. P. 4 (a), as appearing in 481 Mass. 1606 (2019). However, we may nevertheless decide the appeal where the concerns underlying rule 4 (a) are not implicated; that is, "no action on the appeal had yet been taken before the motion for reconsideration was decided." Roch v. Mollica, 481 Mass. 164, 165 n.2 (2019). The appeal has been briefed by both parties and neither party has raised this issue. We therefore choose to exercise our discretion to decide the appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

One North of Boston LLC v. Dhiren Thakkar., (Mass. Ct. App. 2025).

One North of Boston LLC v. Dhiren Thakkar. (One North of Boston LLC v. Dhiren Thakkar.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Rahman v. Federal Management Co.
505 N.E.2d 548 (Massachusetts Appeals Court, 1987)
Boston Housing Authority v. Hemingway
293 N.E.2d 831 (Massachusetts Supreme Judicial Court, 1973)
Doe v. New Bedford Housing Authority
630 N.E.2d 248 (Massachusetts Supreme Judicial Court, 1994)
Allison v. Eriksson
98 N.E.3d 143 (Massachusetts Supreme Judicial Court, 2018)
Roch v. Mollica
113 N.E.3d 820 (Massachusetts Supreme Judicial Court, 2019)
Cruz Management Co. v. Thomas
417 Mass. 782 (Massachusetts Supreme Judicial Court, 1994)
Al-Ziab v. Mourgis
424 Mass. 847 (Massachusetts Supreme Judicial Court, 1997)
Andover Housing Authority v. Shkolnik
820 N.E.2d 815 (Massachusetts Supreme Judicial Court, 2005)
Jablonski v. Casey
835 N.E.2d 615 (Massachusetts Appeals Court, 2005)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)