Omega Demolition Corporation v. Judlau Contracting, Inc

2020 IL App (2d) 190225-U
Appellate Court of Illinois·Decided September 17, 2020·No. 2-19-0225·Unpublished

Opinion

No. 2-19-0225

Order filed September 17, 2020

NOTICE: This order was filed under Supreme Court Rule 23 and may not be cited as precedent by any party except in the limited circumstances allowed under Rule 23(e)(1).

IN THE

APPELLATE COURT OF ILLINOIS

SECOND DISTRICT

OMEGA DEMOLITION CORPORATION, ) Appeal from the Circuit Court ) of Du Page County.

)

Plaintiff-Appellee and Cross-Appellant, )

)

v. ) No. 16-CH-1353 )

JUDLAU CONTRACTING, INC.; ILLINOIS ) STATE TOLL HIGHWAY AUTHORITY; ) TRAVELERS CASUALTY AND SURETY ) COMPANY OF AMERICA; ZURICH ) AMERICAN INSURANCE COMPANY; ) and LIBERTY MUTUAL INSURANCE ) COMPANY, )

)

Defendants )

)

(Judlau Contracting, Inc., Defendant-Appellant ) Honorable and Cross-Appellee). ) Bonnie M. Wheaton, ) Judge, Presiding.

JUSTICE ZENOFF delivered the judgment of the court.

Justices Schostok and Hudson concurred in the judgment.

ORDER

¶1 Held: In dispute between contractor and subcontractor on Tollway project, the trial court properly excluded as irrelevant the contractor’s estimate of what the subcontractor left incomplete on its project: the parties agreed in the subcontract that the Tollway’s word was definitive on what percentage of the project the subcontractor

had completed. The court also did not err in denying statutory interest to the subcontractor or in its calculation of damages for scrap metal that was wrongfully withheld from the subcontractor.

¶2 Plaintiff, Omega Demolition Corporation, was a subcontractor for the demolition of a bridge (Thorndale Avenue bridge) on property owned by the Illinois State Toll Highway Authority (Tollway) as part of a larger construction project in the western suburbs (the Elgin-O’Hare project). Defendant, Judlau Contracting, Inc., was the general contractor. Plaintiff filed this action against defendant and three insurance companies (the sureties). After a bench trial, the court found for plaintiff, awarding it damages from defendant for breach of contract and relief against the Tollway and the sureties. Defendant appeals, contending that the court abused its discretion in barring testimony from its project manager on the cost of completing plaintiff’s work after the Tollway barred plaintiff from the site. Plaintiff cross-appeals, contending that the court erred in denying it interest on the award and limiting its recovery for scrap left on the site. We affirm.

¶3 I. BACKGROUND

¶4 On June 28, 2018, plaintiff filed a five-count amended complaint. Count I, for an accounting, alleged as follows. In 2015, the Tollway and defendant entered into a contract for the Elgin-O’Hare project. In December 2015, plaintiff and defendant entered into a subcontract under which plaintiff would provide labor and materials to remove the Thorndale Avenue bridge. The price was $480,000. Plaintiff timely completed its work. After deducting all credits and allowances, defendant still owed plaintiff $438,280. Plaintiff duly notified the Tollway and the sureties of the outstanding balance. On or about May 23, 2017, defendant tendered $58,495.87 to some of plaintiff’s sub-subcontractors (third-tier contractors), but it had not paid plaintiff anything. Plaintiff requested an accounting of the amount due it; a mechanic’s lien on the money due it; payment from the Tollway of $379,784.13 plus interest and costs; and attorney fees.

¶5 Count II was directed against defendant for breach of contract. It repeated the allegations of count I and added the following. The subcontract entitled plaintiff to the reasonable value of scrap materials generated by its work. That value was $36,460, none of which defendant had paid plaintiff. Defendant’s repeated refusal to pay plaintiff for its labor and materials was an unreasonable delay, as was defendant’s refusal to pay for the scrap. These delays entitled plaintiff to interest under section 205/2 of the Interest Act (815 ILCS 205/2 (West 2018)). Further, under the subcontract, plaintiff should receive prejudgment interest of 5% per annum on all payments that had been unreasonably withheld. Defendant’s breaches had caused plaintiff damages in excess of $416,244.13. Count II prayed for these damages, plus interest, costs, and attorney fees.

¶6 Count III was a claim on a contractor’s bond against the sureties and is not pertinent to this appeal. Count IV was a claim against defendant for interest under the State Prompt Payment Act (30 ILCS 540/0.01 et seq. (West 2018)). Count V, pleaded in the alternative to count II, sought recovery in quantum meruit against defendant.

¶7 On November 28, 2017, defendant filed an answer and an amended counterclaim. The answer alleged in part as to count I of the amended complaint that plaintiff had completed only a portion of its obligations when the Tollway revoked plaintiff’s permission to work on the project and plaintiff ceased work. Defendant admitted that, on or about May 23, 2017, it tendered plaintiff checks totaling $58,495.87 for plaintiff to distribute to its third-tier contractors for their work; defendant had not paid any other money to plaintiff. As to count II, defendant admitted that the subcontract required plaintiff to remove and dispose of for its own account the scrap materials generated by its work on the project. Defendant denied that the scrap was worth what plaintiff claimed. Defendant denied liability on any count directed against it.

¶8 In its amended counterclaim, defendant sought a setoff and alleged as follows. In 2015, plaintiff and defendant had entered into subcontracts for both the Elgin-O’Hare project and a Cook County project centered on the Jane Addams Tollway (Jane Addams project). Plaintiff breached the Jane Addams project subcontract in various ways. A worker for plaintiff was killed on site on April 5, 2016, and a wrongful-death action was pending in Cook County. Plaintiff’s breaches had exposed defendant to potential liability of more than $50,000, plus the costs of defending claims against it. The counterclaim requested a setoff against damages defendant incurred in the Cook County case from plaintiff’s breaches of the Jane Addams project subcontract.

¶9 On December 19, 2017, plaintiff answered the counterclaim. It denied breaching the Jane Addams project subcontract and alleged that the Cook County suit had no bearing on this case.

¶ 10 Before trial, defendant clarified that it included the counterclaim to make the court aware of its exposure to liability in the Cook County case, and “the issues involving that case [were] among the reasons as to why there[] [had] not been more payment *** on this case.” Defendant would not be seeking “to adjudicate the amounts” of any setoff. The cause proceeded to trial.

¶ 11 Plaintiff first called Michael McMahon, who testified on direct examination as follows. He was plaintiff’s vice president of estimating, which involved quantifying volumes of material and setting a price for its removal. For the Thorndale Avenue project, McMahon typed up a proposal to defendant. Eventually, plaintiff received the subcontract to remove the bridge’s superstructure and substructure. The price was $480,000.

¶ 12 The subcontract (admitted by stipulation) included an attachment stating, “ ‘Subcontractors shall take title to all salvage arrived [sic] from removal work and will coordinate all removal from the jobsite at no cost to [defendant].’ ” “Salvage” was “ ‘any type of steel, whether it be rebar or

the beams from the project.’ ” 1 Another attachment contained exclusions from the subcontract, including lane closures, barricades, detours, and placing protective shielding when beams were removed.

Free access — add to your briefcase to read the full text and ask questions with AI

Omega Demolition Corporation v. Judlau Contracting, Inc, 2020 IL App (2d) 190225-U (Ill. Ct. App. 2020).

2020 IL App (2d) 190225-U (Omega Demolition Corporation v. Judlau Contracting, Inc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Razor v. Hyundai Motor America
854 N.E.2d 607 (Illinois Supreme Court, 2006)
Foutch v. O'BRYANT
459 N.E.2d 958 (Illinois Supreme Court, 1984)
In Re Application for Judgment & Sale of Delinquent Properties
656 N.E.2d 1049 (Illinois Supreme Court, 1995)
Graham v. Illinois State Toll Highway Authority
695 N.E.2d 360 (Illinois Supreme Court, 1998)
City of St. Charles v. Illinois Labor Relations Board
916 N.E.2d 881 (Appellate Court of Illinois, 2009)
Sterling Freight Lines, Inc. v. Prairie Material Sales, Inc.
674 N.E.2d 948 (Appellate Court of Illinois, 1996)
Bell v. Louisville & NashVille Railroad
478 N.E.2d 384 (Illinois Supreme Court, 1985)
People v. Montano
2017 IL App (2d) 140326 (Appellate Court of Illinois, 2017)