KITCHENS, PRESIDING JUSTICE, FOR THE COURT:
¶ 1. Phillip Moore, Gloria Moore, and Katelyn Moore sued Olshan Foundation Repair of Jackson, LLC (Olshan), and Wayne Brown in Perry County Circuit Court. Olshan and Brown sought to compel arbitration pursuant to an arbitration provision within a contract between Phillip Moore and Olshan for the repair of the foundation of the Moores' home. The circuit court ordered Phillip and Gloria Moore to arbitrate their claims. But because the circuit court declined to order Katelyn Moore to the arbitral forum, Olshan and Brown now appeal. We affirm the judgment of the Perry County Circuit Court denying the motion to compel arbitration filed by Olshan and Brown as to Katelyn Moore's claims.
FACTS AND PROCEDURAL HISTORY
¶ 2. On June 10, 2013, Phillip Moore contracted
1
with Olshan for repairs to the
foundation of the home he shared with his wife, Gloria Moore, and his adult daughter, Katelyn Moore. Phillip, Gloria, and Katelyn Moore sued Olshan and Brown in the Circuit Court of Perry County on April 29, 2016, requesting
contract
damages solely for Phillip Moore and Gloria Moore, including damages related to loss of value and expenses to repair their home.
2
Katelyn Moore alleged intentional or negligent infliction of emotional distress. The only remedy she sought is found in the unnumbered prayer for relief, separate and apart from the contract damages sought by Phillip Moore and Gloria Moore.
¶ 3. After Olshan and Brown moved to compel arbitration, the circuit court held a hearing. It then entered an order granting the motion with respect to Phillip and Gloria Moore's claims while denying the motion as it pertains to Katelyn Moore's claims. Regarding Katelyn Moore's claims, the circuit court reasoned that the terms of the contract were not broad enough to include Katelyn as a third-party beneficiary of the agreement and that the arbitration agreement could not be enforced against Katelyn on the grounds of estoppel "as her claims are not based solely on the terms of the contract." The circuit court explained:
Katelyn asserts claims for intentional or negligent infliction of emotional distress and negligence which could be pursued regardless of whether or not there was a contract. Moreover, due to ambiguity in the Complaint, it is not clear to the [c]ourt if Katelyn is seeking to assert claims for breach of contract and breach of warranty. Those claims more properly belong to Phillip and Gloria.
The trial court further held that Katelyn Moore was neither a third-party beneficiary nor a direct beneficiary of the Olshan contract, because:
the terms of the contract were not expressly broad enough to include Katelyn as a third-party by name or as one of a specified class, as Katelyn was not an
owner of the property. Furthermore, Katelyn was not a direct beneficiary of the contract. The fact that Katelyn resides in the home makes her an incidental, not direct beneficiary of the construction work performed by Olshan.
See
Rein v. Benchmark Construction Company
,
865 So.2d 1134
(Miss. 2004) ;
Simmons Housing Inc. v. Shelton ex rel. Shelton
, 36 So.[3]2d 1283 (Miss. 2010).
¶ 4. Olshan and Brown appeal only the circuit court's denial of their motion to compel Katelyn Moore to arbitrate her claims.
ANALYSIS
¶ 5. A grant or denial of a motion to compel arbitration is reviewed
de novo
.
Harrison Cty. Commercial Lot, LLC v. H. Gordon Myrick, Inc.
,
107 So.3d 943
, 949 (Miss. 2013) (citing
Cmty. Bank of Miss. v. Stuckey
,
52 So.3d 1179
, 1181 (Miss. 2010) ).
¶ 6. The circuit court held that the arbitration provision in the foundation-repair contract between Phillip Moore and Olshan was valid and enforceable and that Gloria Moore was a third-party beneficiary. Phillip and Gloria Moore declined to cross-appeal the circuit court's decision that the arbitration agreement was valid and enforceable respecting their claims. Accordingly, the validity of the arbitration provision, itself, is not before the Court. The only question is whether Katelyn Moore, a nonsignatory, is bound to arbitrate her claims against Olshan.
¶ 7. Olshan contends that a federal policy favoring arbitration exists and the Federal Arbitration Act (FAA) requires "that 'we rigorously enforce agreements to arbitrate.' "
East Ford, Inc. v. Taylor
,
826 So.2d 709
, 713 (Miss. 2002) (quoting
Shearson/Am. Express, Inc. v. McMahon
,
482 U.S. 220
, 226,
107 S.Ct. 2332
, 2337,
96 L.Ed.2d 185
(1987) ). But Phillip Moore contracted specifically with Olshan for Mississippi law to govern any disputes or lawsuits arising out of their agreement. So the FAA does not apply to this case. And Mississippi courts will "not override the clear intent of the parties, or reach a result inconsistent with the plain text of the contract, simply because the policy favoring arbitration is implicated."
B.C. Rogers Poultry Inc. v. Wedgeworth
,
911 So.2d 483
, 487 (Miss. 2005) (quoting
EEOC v. Waffle House, Inc.
,
534 U.S. 279
, 294,
122 S.Ct. 754
, 764,
151 L.Ed.2d 755
(2002) ).
¶ 8. Only in the rarest of circumstances, and with caution, should we shackle a citizen to an agreement of others that strips the citizen of his or her constitutional right to a trial by jury. Miss. Const. Art. 3, § 31 ;
see
Pinnacle Trust Co., L.L.C. v. McTaggart
,
152 So.3d 1123
, 1127 (Miss. 2014) (quoting
Scruggs v. Wyatt
Free access — add to your briefcase to read the full text and ask questions with AI
KITCHENS, PRESIDING JUSTICE, FOR THE COURT:
¶ 1. Phillip Moore, Gloria Moore, and Katelyn Moore sued Olshan Foundation Repair of Jackson, LLC (Olshan), and Wayne Brown in Perry County Circuit Court. Olshan and Brown sought to compel arbitration pursuant to an arbitration provision within a contract between Phillip Moore and Olshan for the repair of the foundation of the Moores' home. The circuit court ordered Phillip and Gloria Moore to arbitrate their claims. But because the circuit court declined to order Katelyn Moore to the arbitral forum, Olshan and Brown now appeal. We affirm the judgment of the Perry County Circuit Court denying the motion to compel arbitration filed by Olshan and Brown as to Katelyn Moore's claims.
FACTS AND PROCEDURAL HISTORY
¶ 2. On June 10, 2013, Phillip Moore contracted
1
with Olshan for repairs to the
foundation of the home he shared with his wife, Gloria Moore, and his adult daughter, Katelyn Moore. Phillip, Gloria, and Katelyn Moore sued Olshan and Brown in the Circuit Court of Perry County on April 29, 2016, requesting
contract
damages solely for Phillip Moore and Gloria Moore, including damages related to loss of value and expenses to repair their home.
2
Katelyn Moore alleged intentional or negligent infliction of emotional distress. The only remedy she sought is found in the unnumbered prayer for relief, separate and apart from the contract damages sought by Phillip Moore and Gloria Moore.
¶ 3. After Olshan and Brown moved to compel arbitration, the circuit court held a hearing. It then entered an order granting the motion with respect to Phillip and Gloria Moore's claims while denying the motion as it pertains to Katelyn Moore's claims. Regarding Katelyn Moore's claims, the circuit court reasoned that the terms of the contract were not broad enough to include Katelyn as a third-party beneficiary of the agreement and that the arbitration agreement could not be enforced against Katelyn on the grounds of estoppel "as her claims are not based solely on the terms of the contract." The circuit court explained:
Katelyn asserts claims for intentional or negligent infliction of emotional distress and negligence which could be pursued regardless of whether or not there was a contract. Moreover, due to ambiguity in the Complaint, it is not clear to the [c]ourt if Katelyn is seeking to assert claims for breach of contract and breach of warranty. Those claims more properly belong to Phillip and Gloria.
The trial court further held that Katelyn Moore was neither a third-party beneficiary nor a direct beneficiary of the Olshan contract, because:
the terms of the contract were not expressly broad enough to include Katelyn as a third-party by name or as one of a specified class, as Katelyn was not an
owner of the property. Furthermore, Katelyn was not a direct beneficiary of the contract. The fact that Katelyn resides in the home makes her an incidental, not direct beneficiary of the construction work performed by Olshan.
See
Rein v. Benchmark Construction Company
,
865 So.2d 1134
(Miss. 2004) ;
Simmons Housing Inc. v. Shelton ex rel. Shelton
, 36 So.[3]2d 1283 (Miss. 2010).
¶ 4. Olshan and Brown appeal only the circuit court's denial of their motion to compel Katelyn Moore to arbitrate her claims.
ANALYSIS
¶ 5. A grant or denial of a motion to compel arbitration is reviewed
de novo
.
Harrison Cty. Commercial Lot, LLC v. H. Gordon Myrick, Inc.
,
107 So.3d 943
, 949 (Miss. 2013) (citing
Cmty. Bank of Miss. v. Stuckey
,
52 So.3d 1179
, 1181 (Miss. 2010) ).
¶ 6. The circuit court held that the arbitration provision in the foundation-repair contract between Phillip Moore and Olshan was valid and enforceable and that Gloria Moore was a third-party beneficiary. Phillip and Gloria Moore declined to cross-appeal the circuit court's decision that the arbitration agreement was valid and enforceable respecting their claims. Accordingly, the validity of the arbitration provision, itself, is not before the Court. The only question is whether Katelyn Moore, a nonsignatory, is bound to arbitrate her claims against Olshan.
¶ 7. Olshan contends that a federal policy favoring arbitration exists and the Federal Arbitration Act (FAA) requires "that 'we rigorously enforce agreements to arbitrate.' "
East Ford, Inc. v. Taylor
,
826 So.2d 709
, 713 (Miss. 2002) (quoting
Shearson/Am. Express, Inc. v. McMahon
,
482 U.S. 220
, 226,
107 S.Ct. 2332
, 2337,
96 L.Ed.2d 185
(1987) ). But Phillip Moore contracted specifically with Olshan for Mississippi law to govern any disputes or lawsuits arising out of their agreement. So the FAA does not apply to this case. And Mississippi courts will "not override the clear intent of the parties, or reach a result inconsistent with the plain text of the contract, simply because the policy favoring arbitration is implicated."
B.C. Rogers Poultry Inc. v. Wedgeworth
,
911 So.2d 483
, 487 (Miss. 2005) (quoting
EEOC v. Waffle House, Inc.
,
534 U.S. 279
, 294,
122 S.Ct. 754
, 764,
151 L.Ed.2d 755
(2002) ).
¶ 8. Only in the rarest of circumstances, and with caution, should we shackle a citizen to an agreement of others that strips the citizen of his or her constitutional right to a trial by jury. Miss. Const. Art. 3, § 31 ;
see
Pinnacle Trust Co., L.L.C. v. McTaggart
,
152 So.3d 1123
, 1127 (Miss. 2014) (quoting
Scruggs v. Wyatt
,
60 So.3d 758
, 767 (Miss. 2011) (quoting
Bridas S.A.P.I.C. v. Gov't of Turkmenistan
,
345 F.3d 347
, 354 n.3 (5th Cir. 2003) ) ) ("arbitration agreements apply to nonsignatories only 'in rare circumstances.' "). This Court has held that "[a] nonsignatory may be bound to an arbitration agreement under ordinary principles of contract and agency."
Simmons Housing, Inc. v. Shelton ex rel. Shelton
,
36 So.3d 1283
, 1286 (Miss. 2010) (internal citations omitted). "[A] signatory may enforce an arbitration agreement against a non-signatory if the non-signatory is a third-party beneficiary or if the doctrine of equitable estoppel applies."
Id.
(internal quotations omitted).
¶ 9.
Simmons
was introduced to these proceedings by Olshan in its motion to compel arbitration, albeit for a different proposition.
3
Roy and Kimberly Shelton
and their two minor children brought suit against Simmons Housing, Inc.,
et al.
, for claims concerning a defective mobile home.
Simmons
,
36 So.3d at 1285
. The circuit court compelled the parents' claims to arbitration based on two agreements they had signed in purchasing the mobile home, but refused to compel the children's claims to arbitration.
Id.
at 1285-86
. This Court held that the nonsignatory children could not be bound to arbitration because they were neither third-party beneficiaries, nor were they bound to the contract by virtue of direct-benefit estoppel.
Id.
at 1286-88
.
¶ 10. First, the
Simmons
Court analyzed whether the Sheltons' children were third-party beneficiaries and held that a person may be considered a third-party beneficiary "if: (1) the contract between the original parties was entered for that person's or entity's benefit, or the original parties at least contemplated such benefit as a direct result of performance; (2) the promisee owed a legal obligation or duty to that person or entity; and (3) the legal obligation or duty connects that person or entity with the contract."
Id.
at 1286 (citing
Burns v. Washington Savings
,
251 Miss. 789
, 796,
171 So.2d 322
, 325 (1965) ).
4
Simmons
held that "a mere incidental or consequential benefit is insufficient."
Id.
at 1287 (quoting
Adams v. Greenpoint Credit, LLC
, 943 So.2d at 703, 708 (Miss. 2006) (daughter was not bound by arbitration clause found in the contract signed by her father) ). Accordingly, this Court held that the Sheltons' children were not third-party beneficiaries to the agreements signed by their parents, because the children "were not referenced or alluded to in the contract. Additionally, their living in the mobile home did not make them direct beneficiaries."
Simmons
,
36 So.3d at 1287
. Here,
as in
Simmons
, Katelyn Moore was not mentioned in the contract. She merely lived in the home.
Simmons
held that living under the same roof was insufficient to confer third-party-beneficiary or direct-beneficiary status.
¶ 11. Here, the trial judge eminently was correct in finding that Katelyn Moore was neither a third-party beneficiary nor a direct beneficiary because:
the terms of the contract were not expressly broad enough to include Katelyn as a third-party by name or as one of a specified class, as Katelyn was not an owner of the property. Furthermore, Katelyn was not a direct beneficiary of the contract. The fact that Katelyn resides in the home makes her an incidental, not direct beneficiary of the construction work performed by Olshan.
See
Rein v. Benchmark Construction Company
,
865 So.2d 1134
(Miss. 2004) ;
Simmons Housing Inc. v. Shelton ex rel. Shelton
, 36 So.[3]2d 1283 (Miss. 2010).
¶ 12. The
Simmons
Court next analyzed whether equitable estoppel would bind the Sheltons' children to arbitration.
Simmons
,
36 So.3d at 1287
. Equitable estoppel "is an extraordinary remedy to be used with caution."
Adams
, 943 So.2d at 709. "In the arbitration context, equitable estoppel prevents a party from embracing the benefits of a contract while simultaneously trying to avoid its burdens."
Simmons
,
36 So.3d at 1287
.
¶ 13. Olshan unconvincingly argues that equitable estoppel applies because Katelyn Moore's claim of personal injury arises from the contract, so she should be bound to arbitrate. Katelyn Moore argues that she is not subject to equitable estoppel because she had no knowledge of the contract, and, therefore, she could not have benefitted knowingly from the contract. She continues that her claim for negligent and intentional infliction of emotional distress is not dependent on the contract. We agree. In
Hattiesburg Health & Rehab Center, LLC v. Brown
,
176 So.3d 17
, 18 (Miss. 2015), a nursing home resident's wife, who had signed an admission agreement that contained an arbitration provision, filed a wrongful death lawsuit against the nursing home after her husband's death. The circuit court denied the nursing home's motion to compel arbitration, and this Court affirmed.
Id.
at 18, 25
. On appeal, the nursing home argued that the decedent had been estopped from repudiating "the terms of the admission agreement because he received services from [the nursing home] and benefitted from the terms of the agreement."
Id.
at 23-24
. This Court held that the husband's estate "is not attempting to 'enforce the terms' of the admission agreement, nor is it 'asserting claims that must be determined by reference to it.' "
Id.
at 24
. The wife had "alleged claims of negligence, medical malpractice, ... deviations from the standard of care,
respondeat superior
,
res ipsa loquitur
, negligent supervision and retention and wrongful death."
Id.
at 19
. With regard to the wife's claims, this Court observed: "[s]imply put, Leo's estate's claims sound in tort and [the wife] could pursue those claims without an admission agreement at all."
Id.
Here, too, Katelyn's claims sound in tort. Katelyn neither sought enforcement of the contract nor did she assert a prayer for relief in her complaint compelling performance of the contract.
5
¶ 14. The trial court correctly found that Katelyn Moore's claim for intentional or negligent infliction of emotional distress and negligence "could be pursued regardless of whether or not there was a contract."
¶ 15. Olshan next argues that direct-benefit estoppel mandates enforcement of an arbitration provision against a nonsignatory. "Direct-benefit estoppel involves non-signatories who, during the life of the contract, have embraced the contract despite their non-signatory status, but then, during litigation, attempt to repudiate the arbitration clause in the contract."
Pinnacle Trust Co.
,
152 So.3d at 1124
(quoting
Noble Drilling Servs., Inc. v. Certex USA, Inc.
,
620 F.3d 469
, 473 (5th Cir. 2010) ). In order for direct-benefit estoppel to apply, a nonsignatory must " 'embrace' a contract containing an arbitration clause" in one of two ways.
Scruggs
,
60 So.3d at 760
. First, a nonsignatory can embrace a contract "by knowingly seeking and obtaining 'direct benefits' from that contract."
Id.
Katelyn Moore did not. Or, a nonsignatory can embrace a contract "by seeking to enforce the terms of that contract or asserting claims that must be determined by reference to that contract."
Id.
Katelyn Moore did not. In
Pinnacle Trust Co.
, nonsignatory trustees were not bound to an arbitration agreement under direct-benefit estoppel because they were neither beneficiaries, direct or residual, nor were they aware of the agreement that would bind them to arbitrate their claims.
Pinnacle Trust Co.
,
152 So.3d at 1129
. Neither was Katelyn Moore.
¶ 16. Katelyn Moore is not a direct beneficiary because she never sought to obtain any direct benefit from the foundation-repair contract. She is, as the trial court ruled, merely an incidental beneficiary.
Simmons
,
36 So.3d at 1287
. Katelyn Moore is not asserting a claim that requires reference to the contract, and no evidence has been offered to support the argument that Katelyn knowingly sought any direct benefit from the contract or that she embraced its terms. Moreover, no evidence has been offered that Katelyn Moore knew of the contract's existence, much less that it contained an arbitration provision.
¶ 17. In any event, Katelyn Moore "cannot be required to arbitrate any disputes [to] which [she] did not agree ...."
Harrison Cty. Commercial Lot, LLC
,
107 So.3d at
949 (citing
Scruggs
,
60 So.3d at
767 ). In reviewing the contract, there is no evidence of the following: (1) that the contract between Olshan and Phillip Moore was intended for Katelyn Moore's benefit; (2) that Olshan and Phillip Moore at least contemplated such benefit to Katelyn Moore as a direct result of performance; (3) that Olshan owed a contractual obligation or duty to Katelyn Moore, or
vice versa
; (4) that the terms of the contract were expressly broad enough to include Katelyn Moore either by name or by specified class; (4) that Katelyn Moore evidently was within the intent of the terms of the contract, and that Katelyn Moore would be within its benefits; (5) that Olshan had a substantial and articulate interest in the welfare of Katelyn Moore in respect to the subject of the contract; (6) that the contract references or alludes to Katelyn Moore; (7) that Katelyn Moore signed the contract; or (8) that Katelyn Moore consistently has maintained that other provisions of the same contract should be enforced to benefit her.
Simmons
,
36 So.3d at 1286-88
.
¶ 18. Importantly, in
Simmons
, the children alleged contract-related claims.
Simmons
,
36 So.3d at 1288
. The children did not seek to amend their complaint or to
withdraw it to strike the contract-related claims.
Id.
Nevertheless, this Court remanded the case to proceed on the tort claims but declared the contract-related claims to have been relinquished.
Id.
at 1289
. Here, Katelyn Moore did not assert a claim based on the contract because she does not request relief for damages under the contract.
¶ 19. Finally, Olshan cites
Terminix International, Inc. v. Rice
,
904 So.2d 1051
(Miss. 2004). In
Rice
, "a husband and wife sued Terminix for negligence, misrepresentation, fraud, breach of contract, and fraudulent inducement."
Simmons
,
36 So.3d at
1288 (citing
Rice
,
904 So.2d at
1058 ). This Court had held that "the wife was bound to the arbitration agreement under the ordinary principles of equitable estoppel."
Id.
(citing
Rice
,
904 So.2d at
1058 ). Olshan argues that Katelyn Moore's claims, "whether sounding in negligence or contract, all directly stem from Olshan's alleged failure to properly perform the foundation repair work covered by the Agreement." But in
Simmons
, this Court observed that the
Rice
Court, which had referenced the wife's claims in passing, "gave very little discussion as to why equitable estoppel applied to the facts of that case," and, according to a footnote, "afforded great weight to the fact that the wife's suit relied exclusively on the contract."
Id.
(citing
Rice
,
904 So.2d at
1057-58 n.3 ).
¶ 20. As in
Simmons
and
Brown
, Katelyn Moore is neither a third-party beneficiary to the foundation-repair contract nor is she bound by direct-benefit estoppel. Accordingly, we hold that Katelyn Moore's claims, including negligence and intentional/negligent infliction of emotional distress, are wholly independent of the terms of the contract to which she was not a party. We hold further that Olshan should not be allowed to enforce an arbitration clause respecting Katelyn Moore's claims, which are unrelated to the contract.
CONCLUSION
¶ 21. On
de novo
review, we find that the circuit court did not err in declining to compel Katelyn Moore's claims to arbitration. Accordingly, we affirm the judgment of the Perry County Circuit Court.
¶ 22.
AFFIRMED.
WALLER, C.J., RANDOLPH, P.J., KING, COLEMAN AND BEAM, JJ., CONCUR. CHAMBERLIN, J., DISSENTS WITH SEPARATE WRITTEN OPINION JOINED BY MAXWELL AND ISHEE, JJ.