Olivieri Moderen Boating v. McLeod, 97-4189 (1998)

CourtSuperior Court of Rhode Island
DecidedJune 3, 1998
DocketC.A. No. 97-4189
StatusPublished

This text of Olivieri Moderen Boating v. McLeod, 97-4189 (1998) (Olivieri Moderen Boating v. McLeod, 97-4189 (1998)) is published on Counsel Stack Legal Research, covering Superior Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Olivieri Moderen Boating v. McLeod, 97-4189 (1998), (R.I. Ct. App. 1998).

Opinion

DECISION
This action involves an appeal by Carmine Olivieri from a decision of the Administrative Adjudication Division of the Department of Environmental Management (DEM). Olivieri seeks reversal of DEM's July 29, 1997 decision finding that he violated the Freshwater Wetlands Act.

The subject site, located in West Greenwich, contains a swamp/pond complex, a stream which is less than ten feet wide on average, a perimeter wetland, and two riverbank wetlands. A cartpath which runs through the site is an undeveloped earthen roadway approximately eight feet wide on average. At a certain point this path becomes Rhode Island dam # 468.

To the east of the cartpath lies a large pond; to the west is a swamp, greater than three acres in area. A concrete structure carries flow from the pond beneath the cartpath to the swamp. After a westerly bend in the cartpath, there is a crossing stream. Dena Gonsalves, a senior natural resource specialist in the Enforcement Section of the Division of Freshwater Wetlands, indicated that over a number of years water from the pond flowed through the cartpath, a term that Gonsalves used interchangeably with "dam," to the swamp on the other side of the cartpath.

On September 1993, a Notice of Intent to Enforce (NOI) was issued to Boston Neck Realty Corp., at that time the owner of the site. (On August 25, 1994, the property was conveyed to Modern Boating, Inc., of which Olivieri is president.) The NOI was issued because Gonsalves, in an earlier site inspection, had determined that the stream channel had been excavated in order to remove a beaver dam, leaving debris along the sides of the stream channel.

During a site inspection in April of 1994, Gonsalves again noticed that the stream had been recently excavated to remove a beaver dam. Soil had again been placed along the sides of the channel. The dimensions of the channel were approximately four feet deep by three feet wide. A site inspection by Gonsalves in July revealed further excavation of the stream crossing, with debris along the sides of the channel, making it very steep and in need of stabilization.

On August 3, 1994, the Division of Freshwater Wetlands received a letter of authorization from John R. Assalone, president of Boston Neck Realty, Corp., designating Olivieri to act on its behalf in the discussions with the Division. On August 14, 1994, Gonsalves met with Olivieri at the site to discuss restoration. She told Olivieri that the slopes of the channel needed to be graded back, seeded, and mulched with a mat of loose hay. Olivieri insisted that he had to be able to drive a vehicle across the path.

Subsequent to the August 11th meeting, Olivieri received permission from DEM to fill two feet of the four foot depth of the stream in order to gain access across the water course but still allow water from the pond to flow through the cartpath to the swamp.

On or about August 29, 1994, Gonsalves again visited the site and found that the restoration had not been done in conformance with DEM's directives; rather, the stream channel had been filled to the top of the cartpath, well beyond the designated two-foot level.

On November 21, 1994, Gonsalves, Harold Ellis, the enforcement supervisor for the Division, and Olivieri met the property. The fill within the stream channel was then one foot below the top of the cartpath, probably as a result of erosion or water flowing across the surface, but water still flowed across the partially filled ditch/stream. Gonsalves and Ellis determined that since the channel appeared relatively stable and still allowed water to escape the pond, thereby acting as an emergency overflow for the dam, adequate restoration had been accomplished. Olivieri then stated that he desired to do some additional work. Because rain had damaged the road, he wanted to prevent any water from flowing across the cartpath in the area of the stream crossing. Ellis, however, informed Olivieri several times that in order to do that work, a permit from the Wetlands Division would be required. Ellis reiterated that admonition in a December 2, 1994 letter to Olivieri, expressly addressing and contradicting Olivieri's contention that the contemplated work was "maintenance" of the dam and not exempt from permit requirements:

"Contrary to what you expressed in the field, the proposed activity of raising the grade of the cartpath to stop the overflow of water is not maintenance activity in our Rules and Regulations. As such, any further work proposed in and/or adjacent to the restoration area shall require a Permit from this Division . . . . Please also note that approval is required from this Division to manipulate the water level in the Pond."

A site visit on December 14, 1994 revealed that the premises were essentially in the same condition as that approved in the November on-site meeting, and therefore the property appeared to be in compliance with the NOI. A different picture was presented on September 29, 1995, when Sean Carney, a natural resource specialist, visited the site in response to a telephone complaint received by DEM. Carney observed a large backhoe excavating a portion of the pond area near the concrete culvert outlet structure. Carney also noticed that clearing and filling in both the pond and swamp area, had occurred and that material had been placed in the stream channel. Further along the cartpath Carney noticed filling, clearing, and grading within the swamp and perimeter wetland area. A Cease and Desist Order was issued to Olivieri on that day.

Compared to her last visit on December 14, 1994, Gonsalves noted that the stream crossing area had been filled to the top of the cartpath and that there was additional work along the sides of the cartpath as well as to the north and northwest area of the stream crossing. Fill had been deposited in the stream channel and into the pond, thereby raising and widening the cartpath/dam. Other filling and grading had been done, and large fill piles had been stored at the end of the cartpath in the swamp and perimeter wetland.

A month later, November 6, 1995, Carney returned to the site and discovered that Olivieri had ignored the Cease and Desist Order. Further alterations had occurred, and additional fill had been placed in the perimeter wetland at the end of the cartpath. Carney recommended that a Notice of Violation and Order (NOV) be issued. An NOV was subsequently prepared and issued on November 21, 1995, and penalties were assessed for each violation.

Before issuing the NOV, Ellis took into account his own knowledge of the site, Carney's reports, aeriel photographs, Gonsalves' reports, along with all of the Division's files on the matter. He also reviewed provisions in the Rules and Regulations Governing the Administration and Enforcement of the Freshwater Wetlands Act ("Wetlands Regulations") relating to exempt activities and determined that the alterations at the site exceeded the limitations set forth in the regulations. He also determined that no application had been submitted for the alterations.

The NOV alleged that Olivieri altered or permitted alterations of freshwater wetlands in five instances without having first obtained DEM approval, ordered restoration of the wetlands, and imposed a Five Thousand Dollar administrative penalty. After a full adjudicatory hearing, the hearing officer determined that Olivieri had violated the Freshwater Wetlands Act by:

1. Filling into a 100-foot Riverbank Wetland and into a Swamp/Pond Complex, resulting in the unauthorized alteration of approximately 160 square feet of wetland;

2. Filling into a Stream, resulting in the unauthorized alteration of wetland by restricting flow in the Stream and causing impoundment of water in the adjacent Pond;

3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Udall v. Tallman
380 U.S. 1 (Supreme Court, 1965)
Environmental Scientific Corp. v. Durfee
621 A.2d 200 (Supreme Court of Rhode Island, 1993)
Milardo v. Coastal Resources Management Council
434 A.2d 266 (Supreme Court of Rhode Island, 1981)
Newport Shipyard, Inc. v. Rhode Island Commission for Human Rights
484 A.2d 893 (Supreme Court of Rhode Island, 1984)
Berberian v. Department of Employment Security, Board of Review
414 A.2d 480 (Supreme Court of Rhode Island, 1980)
Carmody v. Rhode Island Conflict of Interest Commission
509 A.2d 453 (Supreme Court of Rhode Island, 1986)
Citizens Savings Bank v. Bell
605 F. Supp. 1033 (D. Rhode Island, 1985)
Costa v. Registrar of Motor Vehicles
543 A.2d 1307 (Supreme Court of Rhode Island, 1988)
Barrington School Committee v. Rhode Island State Labor Relations Board
608 A.2d 1126 (Supreme Court of Rhode Island, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Olivieri Moderen Boating v. McLeod, 97-4189 (1998), Counsel Stack Legal Research, https://law.counselstack.com/opinion/olivieri-moderen-boating-v-mcleod-97-4189-1998-risuperct-1998.