Olivier v. Olson

248 N.W. 181, 63 N.D. 316, 1933 N.D. LEXIS 185
CourtNorth Dakota Supreme Court
DecidedApril 15, 1933
DocketFile No. 6088.
StatusPublished

This text of 248 N.W. 181 (Olivier v. Olson) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Olivier v. Olson, 248 N.W. 181, 63 N.D. 316, 1933 N.D. LEXIS 185 (N.D. 1933).

Opinion

Christianson, J.

Plaintiffs brought this action to recover the sum of $498.69 claimed to be due them from the defendants on account. The defendants answered denying liability, and by way of counterclaim asserted that they had overpaid the plaintiffs by mistake in the sum of $164.16, and demanded judgment against the plaintiffs for that sum. The case was tried to a jury and resulted in a verdict in favor of the plaintiffs for the full amount demanded in their complaint and defendants have appealed.

The defendants are general building contractors. .The plaintiffs are engaged in sheet metal and roofing work. Business relations have existed between the plaintiffs and the defendants for some time. When the defendants contracted for the construction of a building it was their practice to sublet the sheet metal and roofing work, and apparently such work, in many instances, had been sublet to the plaintiffs. The present action, which is based on account, really involves a dispute arising out of two contracts. In 1929 the defendants contracted to construct a building in the city of Minot known as the Ellison Building. In conformity with their practice they asked for and obtained bids for the roofing and sheet metal work. Five different bids were submitted. The low bid was submitted by the Ray Roofing Company of St. Paul, Minnesota. This company submitted a bid of $1,5.72. The plaintiffs also submitted a bid for approximately $1,800. Later a change was made in the roof of the building, which resulted in a reduction of $420, in each of the bids submitted. The plaintiffs were awarded the sub-contract- and did the work and charged the .defendants *318 $1,344. It is undisputed' that after the bids of the sub-contractors had been submitted some discussion was had between the plaintiffs and the defendants, but there is a square conflict as to what was said. The defendants claim that the plaintiffs agreed to do the work for the amount of the low bid, namely, $1,152. The plaintiffs, on the other hand, deny that this was the agreement and claim that they agreed to install a certain skylight at cost and .also to make certain reductions in their original bid. The plaintiffs testify that the sum of $1,344 was arrived at by averaging all the five bids, that is, the amounts of the five bids were added and the total sum, divided by five, which it is said resulted in the amount that the plaintiffs charged the defendants for the work.

In March, 1929, the defendants were awarded the general contract for construction of the Ward county courthouse. They invited subcontractors to submit bids to them for the sheet metal and roofing work on such building. Several bids were submitted. The plaintiffs submitted a written bid of $4,960 for the roofing and sheet metal work, with the stipulation that if Barrett’s Twenty Year roofing were used that an additional sum of $230 should be added, making a total sum of $5,190. It is undisputed that Barrett’s Twenty Year Roofing was used, so that the amount for which they agreed to do the work according to plaintiffs’ written bid was $5,190. The bid submitted by the plaintiffs was not the low bid. Another firm submitted a bid of $4,719, or $471 lower than plaintiffs’ bid. The defendant Orheim testified that in preparing the bid for the general contract for the construction of the courthouse the defendants used the lowest bids that had been submitted to them by the different sub-bidders, including the lowest bid submitted for the sheet metal and roofing work.

After the bids of the defendants, and other bidders for the general contract for the construction of the courthouse, had been submitted to the county commissioners and while such bids were under consideration the defendant Orheim and the plaintiff Uleberg met at the offices of the defendants in Minot, and some discussion was had between them as regards the sub-contract for the sheet metal and roofing work, and concerning the- bids that had been submitted to the defendants by the plaintiffs and the other bidders for that particular sub-contract. Both the plaintiff Uleberg and the defendant Orheim testified that they met *319 pursuant to a telephone call; that the defendant Orbeim had telephoned to the plaintiffs. They agree that a conversation was had as regards the proposed sub-contract for sheet metal and roofing work, and the bids that had been received by the defendants for such work; but there is a square conflict in their testimony as to what was said and w'hat agreement was made by the parties at that time.

The plaintiff Uleberg testified:

“Q. At that time what did Mr. Orheim say to you, and what did you say to him? Was that after this proposal had been submitted? A. That was after the proposal had been submitted. Q. What did you say to Mr. Orheim, and what did Mr. Orheim say to you at that time? A. Mr. Orheim says, ‘we have a bid that is lower than yours/ Q. And what did you say ? A. Well, I said we would like to do the' work, but we didn’t want the job at a cut price. Q. What did he say ? A. He said we are going to use you, we are going to use you, and we are having quite a struggle to get the job, quite a time to get the job, and he asked that we get out and see what we could do for him in the way of helping them get the job. Q. Was there any other conversation at that time that you remember? A. No, there wasn’t anything else. Q. Did he mention any bid by a firm known as Nees Brothers ? A. lie said he had a lower bid, he didn’t mention any amounts. Q. Were any persons named in connection with it? A. No. Q. Did he show you any bids? A. No.”

The defendant Orheim testified:

“Q. What was said between you with reference to this bid? A. I told him (Uleberg), the architect had asked us for a list of sub-bidders Ave would use in case we Avas awarded the bid for the Court House. I asked him if he knew he Avas bidding quite a bit of money on the job, and he said he knew about it. Q. At that time, Mr. Orheim, you may state whether or not you had in your possession the Defendants’ Exhibit (D), from Nees Brothers? A. Tes. Q. And at thkt time did you have any talk with Mr. Uleberg Avith reference to the amount of that bid? A. Yes. Q. Well, what was said? A. I asked him hoAV it could be possible that those fellows could come up from Minnesota and beat them about ten per cent on their bid and come to Minot and expect to make any money, and he said, that bid is so cheap you can make very little or no money on it at that price. . . . Q. Now *320 what else, if anything, was said there between you and Uleberg? A. Well, after he had said that, that the bid was so cheap there was very little or no money could be made at that price, well, he said, that is a ■condition we will have to contend with, and I said, what I am interested in is do you want the work at Nees Brothers’ figure. Q. What did he say? A. Yes, we would like to do the work. Q. What did you do with respect to the sub-contract after that? A. Why, I answered him, I said, all right, we will use your name on the list of sub-bidders. Q. You may state whether or not you did use their name? A. We did, yes, sir. Q. Did you state on that list the amount of the sub-contract with it? A. No. The architect got that list, he was up in the office and checked that over, and he marked down the list of sub-bidders, and checked the sub-bidder as he marked them down.”

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
248 N.W. 181, 63 N.D. 316, 1933 N.D. LEXIS 185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/olivier-v-olson-nd-1933.