Oliver & Burr v. Noel Construction Co.

71 A. 959, 109 Md. 465, 1909 Md. LEXIS 5
CourtCourt of Appeals of Maryland
DecidedJanuary 13, 1909
StatusPublished
Cited by3 cases

This text of 71 A. 959 (Oliver & Burr v. Noel Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Oliver & Burr v. Noel Construction Co., 71 A. 959, 109 Md. 465, 1909 Md. LEXIS 5 (Md. 1909).

Opinion

Burke, J.,

delivered the opinion of the Court.

This is the plaintiff’s appeal from a judgment entered against it in the Baltimore City Court. The declaration contains the common counts only, to which the defendant pleaded the general issue pleas upon which issue was joined. Subsequently, by leave of Court, the defendant filed a plea of set' off to which a replication was filed and issue was joined.

An itemized account was filed with the narr., by which it appears that the suit was brought to recover the sum of twenty-one hundred and fifty-one dollars and twenty-one cents alleged to be due the plaintiff by the defendant on account of certain work which will be presently alluded to. It appears from the bill of particulars filed by the defendant with its plea of set off that the plaintiff is indebted to it in *467 the sum of four thousand one hundred and sixty-two dollars and seventy-five cents. The trial resulted in a verdict in favor of the defendant for nine hundred and thirty-four dollars and eighty-two cents upon which final judgment was entered. It is from this judgment that the appeal before us is taken.

The questions of law raised upon the record are simple; but there is very great conflict in the testimony. Only one hill of exceptions is brought up by the appeal, and that relates to the ruling of the Court upon certain prayers presented at the close of the whole case. With the weight of evidence and the credibility of the witnesses we have nothing to do, as those matters were exclusively for tie jury, and if the ease was fully and fairly submitted to the jury under the granted prayers the judgment must be affirmed. It is not necessary in order to dispose of the case to indulge in a minute discussion of the evidence. It will he sufficient to consider its general purport and effect. The record shows that in 3902 Edgar M. ISToel and Daniel W. Thomas entered into a contract with the United States Government for the construction of certain buildings at the Uaval Academy at Annapolis. This contract was assigned to the iNoel Construction Company, the appellee, a corporation organized to finance the work. This work was to be done in accordance with elaborate and detailed specifications furnished by the Government. The Yoel Construction Company sub-let the contract for the fire-proofing of the Cadets Quarters’ Building to the Columbian Eire-proofing Company of Pittsburg, which in turn sublet their contract to Oliver & Burr, the appellant, a New York corporation, and this last named company proceeded under that contract to do the work. The contract of the Pittsburg Company, which was sxxb-let to the appellant, was for the metal partitions on cexdain floors of the Cadets’ building. Later the Government decided to x-aise the roof of this building, and add a fourth floor. The contracts for the metal lathing axid hung ceiling wex’e made directly between the appellant and appellee. On October 9, 1903, the appellant *468 wrote to the appellee proposing “to furnish and put in place all the metal furring required by the plans and specifications of Mr. E. Flagg, architect, for the Cadet Quarters’ Building, at Annapolis, Md., including paragraphs 875 to 877 inclusive, and all other paragraphs therein referred to for the sum of seventy-five hundred ($7,500.00) dollars; subject to contract that may be mutually agreed upon.” This proposal was accepted by the appellee in a letter to' the appellant of that date. By letter of October 31, 1903, the appellant proposed to furnish and erect partitions on the top floor of this building for the sum of fifty-nine hundred dollars, and the suspended ceiling for forty-seven hundred dollars. This offer was accepted by letter of February 18, 1904. The appellant at the time these contracts were made was engaged in doing-the same character of work on the building under his contract with the Pittsburg Company, and he proceeded with the work under all the contracts.

■The contract for the work of plastering to be done in this building was sub-let by the general contractor to Barwell & Cantlin, and the manner in which their work was done presented, as will be seen, one of the important questions of fact for the consideration of the jury. As the main questions in this controversy concern the steel studding and lath partitions and the plastering, it is necessary at this point to refer to the parts of the specifications which provide for that work. A question was made during the trial as to the duty of the appellant to do certain painting for which the defendant claimed an allowance in his plea of set-off. This question was raised by the plaintiff’s eighth prayer, which was, however, abandoned in this Court, and it will not be necessary to consider’ the paragraph of the specifications providing for that work. The paragraphs of the specifications relating to metal and lath partitions and to the plastering are as follows:

“838. The partitions for toilet and bath rooms in basement of wings and in ground floor of stair towers, and partitions in roof space over Memorial Hall, extending from top of ceiling light up to skylight curb, are to be constructed of *469 iron or steel studding and metal lath for 2 in. solid plaster finish. Studding to consist of 3 in. or % in. steel channels as height or location may require, spaced 12 in. on centers and secured at bottom and top to the concrete, iron or other construction by clamps or angles, and properly braced or stiffened where so required. The partitions enclosing basement stairs in the two stair towers are to extend from ground floor up to and properly finish against bottom of stair string above.
“888. All plastering, except as hereinafter otherwise specified, is to be best three-coat work of lime mortar mixed in proper proportion to give the best results, the mortar for scratch and brown coats is to be gauged with Portland cement, using one-half of a barrel of cement to each cubic yard of mixed mortar for brick, terra cotta, block and concrete surfaces, and not less than three-qaurters of a barrel for lathed surfaces.”

The plaintiff must he held to have undertaken to do all the work contracted for upon the building in accordance with the specifications. Mr. Oliver was aware of the specifications and was no doubt familiar with their requirements, otherwise it would have been impossible for him to bid intelligently upon the work. Besides, his proposal of October 9, 1903, was to do the work in accordance with the plans and specifications. It would he most unreasonable to suppose that it was in contemplation of either party that the work could be done in disregard of the plans and specifications, because they both knew that work so done would not be accepted. Mr. Albert Oliver, the President of the appellant company, was the only witness offered in chief in support of the plaintiff’s case, and he gave testimony tending to prove that the plaintiff had done the work embraced in the account filed with the declaration, and that the defendant was indebted to the plaintiff in the full amount claimed, to wit, $2,151.21. He’testified that the whole trouble arose from the plastering done by Barwell & Oantlin; that the plaintiff had nothing to do with the plastering, and that he had warned the plasterers that they were spoiling the work.

*470

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnsamson v. Saul
D. Alaska, 2019
Rosenbloom v. Feiler
431 A.2d 102 (Court of Appeals of Maryland, 1981)
Roth v. Baltimore Trust Co.
158 A. 32 (Court of Appeals of Maryland, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
71 A. 959, 109 Md. 465, 1909 Md. LEXIS 5, Counsel Stack Legal Research, https://law.counselstack.com/opinion/oliver-burr-v-noel-construction-co-md-1909.