Olivares, Emilio v. Alfonso Mares, and Multi-Building, Inc.

390 S.W.3d 608, 2012 WL 5951335, 2012 Tex. App. LEXIS 9812
CourtCourt of Appeals of Texas
DecidedNovember 27, 2012
Docket05-10-01486-CV
StatusPublished
Cited by3 cases

This text of 390 S.W.3d 608 (Olivares, Emilio v. Alfonso Mares, and Multi-Building, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Olivares, Emilio v. Alfonso Mares, and Multi-Building, Inc., 390 S.W.3d 608, 2012 WL 5951335, 2012 Tex. App. LEXIS 9812 (Tex. Ct. App. 2012).

Opinion

OPINION

Opinion by

Justice LANG.

Appellant Emilio Olivares filed suit against appellees Alfonso Mares 1 and Mul-ti-Building, Inc. (“Multi-Building”) based on injuries suffered by Olivares while working on the construction of an apartment complex (the “project”). Following a jury trial, the trial court rendered judgment that Olivares recover $61,225 from Multi-Building and $146,940 from Mares, plus interest and a percentage of court costs.

In four issues on appeal, Olivares asserts the trial court reversibly erred by (1) excluding from evidence a written subcontract (the “subcontract”) between Multi-Building and the project’s general contractor, Limestone Construction SW Bluffs, L.C. (“Limestone”); (2) “forcing” a jury submission on a premises condition liability theory when Olivares was seeking only a negligent activity submission; (3) failing to include Multi-Building in the negligent activity question submitted to the jury; and (4) reducing the jury’s award of past lost income on Multi-Building’s motion for judgment notwithstanding the verdict when there was some evidence to support the amount awarded by the jury. Additionally, Multi-Building asserts two “cross-points” in which it contends that if the trial court’s reduction of the jury’s award of past lost wages was error, (1) the trial court erred by not granting judgment notwithstanding the verdict “that [Olivares] take nothing on his claims against Multi-Building” and (2) the evidence was legally and factually insufficient to support an award of past lost wages to Olivares. We decide Olivares’s four issues against him. *611 Further, we decide against Multi-Building on its two “cross-points.” The trial court’s judgment is affirmed.

I. FACTUAL AND PROCEDURAL BACKGROUND

In his live petition at the time of trial, Olivares stated that at the time he was injured, he was a “worker for one or more of [defendants.” 2 Olivares asserted that while on the job site of the project (the “premises”) during the course and scope of his employment, he was directed by his supervisor to obtain a joist 3 for installation. Olivares stated that in doing so, he “was required to step atop of each joist of the second floor, stepping on each one, in order to traverse across the second floor of the apartment complex.” According to Olivares, “[t]his method and manner of traversing the second floor was of common knowledge to all employees of [Mares] as well as [Multi-Building].” Olivares contended that as he was stepping on a joist that “had not been properly braced, banded or properly secured,” the joist “toppled over,” causing him to fall on his side. He stated that as a result of his fall, he “suffered extensive medical injuries to his back, chest, arms, and body in general.” Olivares asserted claims for, inter alia, negligence and premises liability.

In his negligence claim, Olivares contended in part that the incident in question “occurred at the job site being managed and controlled by [defendants.” According to Olivares, “[defendants were careless in their management of the job site and failed to maintain a safe working environment for their employees/servants/agents, including [Olivares].” Specifically, Olivares stated

[Multi-Building] was contracted by [Limestone] to provide “labor and services” for the installation of joists and trusses. The contractual provisions between [Limestone], as the general contractor and [Multi-Building], as the subcontractor, provided not only that [Multi-Building] would provide labor and services for the installation of joists and trusses but also comply with all safety regulations, provide safety railings, provide OSHA approved equipment, provide a Safety Coordinator, and to comply with all other OSHA rules and regulations on all aspects of the work to be performed, which [Multi-Building] failed to do. Nor did Defendant properly brace the joists and trusses as required by local governing ordinances, plans and specifications of the joist and truss manufacturers.

In his premises liability claim, Olivares stated in part

All [defendants had management and control of these premises in order to perform both general and sub-contract work. As the general contractor, [Limestone] managed and controlled the premises in order to construct a new apartment complex on behalf of [the general partner and the premises owner]. In turn, [Limestone] contracted with [Multi-Building] to install joists and trusses for the construction project.
*612 As such [Multi-Building] had control and maintained the premises where the joists and trusses were being installed.

Further, Olivares contended in part that Multi-Building proximately caused Oli-vares’s injuries by “failing to warn [Oli-vares] a dangerous condition existed, which required extra care to be taken.”

Multi-Building and Mares filed separate general denial answers and asserted various affirmative defenses. Multi-Building’s affirmative defenses included, in part, (1) Olivares’s injuries were caused, in whole or in part, by the negligence of Mares, over whom Multi-Building had “no right of or actual control”; and (2) Multi-Building owed no “legal duty” to Olivares. Further, Multi-Building asserted several cross-claims against Mares, whom Multi-Building described as “the employer of [Olivares].”

Additionally, Multi-Building filed a pretrial motion in limine in which it requested, in part, that all counsel and witnesses be instructed to refrain from making any “mention or interrogation” concerning the subcontract or any breach thereof. Multi-Building asserted in part that “Mares (and therefore [Olivares]) were not parties to the [subcontract], and the [subcontract] has no relevancy to the duties and responsibilities of Multi-Building to Mares and/or Olivares.” Also, Multi-Building contended the subcontract “would be cumulative and would confuse the jury and unfairly prejudice [Multi-Building].” During argument on Multi-Building’s motion in limine, counsel for Olivares asserted the subcontract showed Multi-Building “contractually bound themselves to provide a safe place to work” and “contractually bound themselves to not sublet the work.” Thus, according to counsel for Olivares, the subcontract showed Multi-Building “had a duty to provide a safe place to work.” After some discussion, the trial court asked whether Olivares had pleaded “third party beneficiary” as to the subcontract, and counsel for Olivares stated he had not. The trial court granted Multi-Building’s motion in limine as to the subcontract.

During trial, Samuel Mark LeComte, an owner of Multi-Building, testified in part that Multi-Building hired Mares as a subcontractor to perform work on the project. LeComte stated there was no written contract between Multi-Building and Mares pertaining to the project. Additionally, LeComte testified Multi-Building was not Olivares’s employer.

Thomas Littrell, an expert designated by Olivares, testified in part that in his opinion, the party “responsible for overseeing safety at the jobsite” was Multi-Building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
390 S.W.3d 608, 2012 WL 5951335, 2012 Tex. App. LEXIS 9812, Counsel Stack Legal Research, https://law.counselstack.com/opinion/olivares-emilio-v-alfonso-mares-and-multi-building-inc-texapp-2012.