Olek, Inc. v. Merrick Real Estate Group Inc.

2025 NY Slip Op 31827(U)
CourtNew York Supreme Court, New York County
DecidedMay 19, 2025
DocketIndex No. 652181/2017
StatusUnpublished

This text of 2025 NY Slip Op 31827(U) (Olek, Inc. v. Merrick Real Estate Group Inc.) is published on Counsel Stack Legal Research, covering New York Supreme Court, New York County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Olek, Inc. v. Merrick Real Estate Group Inc., 2025 NY Slip Op 31827(U) (N.Y. Super. Ct. 2025).

Opinion

Olek, Inc. v Merrick Real Estate Group Inc. 2025 NY Slip Op 31827(U) May 19, 2025 Supreme Court, New York County Docket Number: Index No. 652181/2017 Judge: Lori S. Sattler Cases posted with a "30000" identifier, i.e., 2013 NY Slip Op 30001(U), are republished from various New York State and local government sources, including the New York State Unified Court System's eCourts Service. This opinion is uncorrected and not selected for official publication. FILED: NEW YORK COUNTY CLERK 05/20/2025 04:49 PM INDEX NO. 652181/2017 NYSCEF DOC. NO. 245 RECEIVED NYSCEF: 05/20/2025

SUPREME COURT OF THE STATE OF NEW YORK NEW YORK COUNTY PRESENT: HON. LORI S. SATTLER PART 02 Justice ---------------------------------------------------------------------------------X INDEX NO. 652181/2017 OLEK, INC.,

Plaintiff,

-v- DECISION AFTER TRIAL MERRICK REAL ESTATE GROUP INC.,12 E 72ND LLC

Defendant. ---------------------------------------------------------------------------------X

Plaintiff Olek, Inc. (“Olek”) commenced this action seeking recovery for breach of

contract and foreclosure on a mechanic’s lien by filing a Summons and Complaint on April 24,

2017. Defendants Merrick Real Estate Group (“Merrick”) and 12 E 72nd LLC (“12 E 72nd”)

(collectively “Defendants”) filed an Answer on June 19, 2017 in which they interposed

counterclaims for breach of contract and willful exaggeration of a mechanic’s lien. The action

was transferred to this Court for trial on March 6, 2024. In a Decision and Order dated August 2,

2024, the Court rescheduled the trial of this action to October 15-18, 2024 (NYSCEF Doc. No.

232). Thereafter, the Court conducted settlement and pretrial conferences.

On the date of the trial, Merrick’s principal, Richard Pesce (“Pesce”), did not appear.

Through counsel, Pesce claimed that he needed to assist his daughter in Florida due to Hurricane

Milton and that he could not attend the trial for “a couple of weeks” (October 15, 2024 Trial

Transcript at 2-4). The Court denied the request of his attorney, also the attorney for Merrick’s

co-defendant 12 E 72nd, for an extension as he provided no valid excuse for his default given the

longstanding date for this trial, his ability to return to New York as Florida airports were no

longer closed at the time, and the age of this case. Merrick’s counsel conceded that “Mr. Pesce

652181/2017 OLEK, INC. vs. MERRICK REAL ESTATE GROUP INC. Page 1 of 9 Motion No. 008

1 of 9 [* 1] FILED: NEW YORK COUNTY CLERK 05/20/2025 04:49 PM INDEX NO. 652181/2017 NYSCEF DOC. NO. 245 RECEIVED NYSCEF: 05/20/2025

was a fact witness, but I think I can make out my claim with Mr. Croman as well” (October 15

Trial Transcript at 13).

A three-day bench trial was held on October 15-17, 2024. At the conclusion of

Defendants’ case, the Court dismissed the counterclaims for breach of contract and willful

exaggeration of the mechanic’s lien for the reasons set forth on the record, namely that

Defendants did not demonstrate a breach or an exaggeration of the mechanic’s lien because they

set forth no proof other than the testimony of the owner as to what their damages were or that

there was a willful exaggeration (October 17 Transcript at 18-19).

Two witnesses were called during the trial: Peter Triestman (“Triestman”), Olek’s

president and sole shareholder, and Steven Croman (“Croman”), a principal of 12 E 72nd, which

is the owner of the townhome located at 12-14 East 72nd Street (“the townhome”). Olek called

Triestman, who testified about the nature of Olek’s business, stating that it fabricates and restores

parts for historic buildings, including at Grand Central Station, the United Nations, and New

Jersey Transit Penn Station (October 15 Transcript at 20-21). They have performed work on the

Upper East Side of Manhattan on other occasions (id.).

12 E 72nd retained Merrick as construction manager for work on the townhome

(Plaintiff’s Exhibit 32, “Construction Management Agreement”). Merrick then retained Olek for

work on the townhome pursuant to a subcontract signed on October 15, 2014 (Plaintiff’s Exhibit

0, “Subcontract”). Olek was hired to fabricate the townhome’s front courtyard grills, window

grills, some railings, and three doors, including the double door main entrance to the townhome

(id. 21-22). Merrick issued six change orders to Olek during the job (Plaintiff Ex. 2-6). 12 E

72nd was not a party to the Subcontract or change orders. Olek was initially owed $122,000

under the Subcontract, which increased with additional work performed under the change orders.

652181/2017 OLEK, INC. vs. MERRICK REAL ESTATE GROUP INC. Page 2 of 9 Motion No. 008

2 of 9 [* 2] FILED: NEW YORK COUNTY CLERK 05/20/2025 04:49 PM INDEX NO. 652181/2017 NYSCEF DOC. NO. 245 RECEIVED NYSCEF: 05/20/2025

The change orders expanded the scope of the job to include things such as a pergola structure for

the roof and hinges for the doors that were fabricated amongst other things. A one-year door

warranty was prepared by Triestman on August 8, 2016 and issued to Merrick (October 15

Transcript at 38-39; Plaintiff’s Ex. 21).

Trietsman credibly testified that Olek was not paid in full (October 15 Transcript at 41).

He stated that Olek had difficulty receiving payment after the initial seven or eight payments (id.

33). Olek submitted a summary all 14 requests for payments, which showed a balance of

$81,534.48 owing as of October 21, 2016 (Plaintiff’s Ex. 23). This calculation included 2%

monthly “finance charges” on overdue balances, as provided by Section 10 of the Subcontract.

Olek filed a mechanic’s lien against the townhome on November 25, 2016 (Plaintiff’s Ex. 26).

Olek also submitted requisition orders to Merrick, which they called “applications for payment”

(Plaintiff’s Ex. 7-20). Triestman testified, and the requisitions confirm, that different portions of

the Subcontract required payment of a 10% deposit, 30% upon approval of shop drawings, 40%

upon completion of fabrication and the last 20% upon installation (October 15 Transcript at 31;

Plaintiff’s Ex. 7-20).

Triestman testified as to the work Olek performed and addressed some of the concerns

about the work raised by Croman, the principal of 12 E 72nd. The Court credits Triestman’s

testimony. He stated that, at the time Olek completed the work, all the townhome’s doors were

functioning properly (October 15 Transcript at 41). He further states that Olek installed

weatherstripping on the doors in August 2016 (id. at 74-75). Prior to that time, he stated that it

was Defendants who did not want weatherstripping, because they wanted to use the doors as a

construction entrance (id. at 40). Triestman testified that the work was performed in conformity

to the plans which had been signed off on with comments from Merrick’s architects (id. at 41).

652181/2017 OLEK, INC. vs. MERRICK REAL ESTATE GROUP INC. Page 3 of 9 Motion No. 008

3 of 9 [* 3] FILED: NEW YORK COUNTY CLERK 05/20/2025 04:49 PM INDEX NO. 652181/2017 NYSCEF DOC. NO. 245 RECEIVED NYSCEF: 05/20/2025

He stated that Merrick provided the electric “strike” for the townhome’s double front doors (id.

at 46). Olek prepared the shop drawings which were ultimately marked “final” by Merrick

(Plaintiff Ex. 22). Triestman further testified that Olek completed all the work called for by the

Subcontract and change orders by September 2016 (October 15 Transcript at 31).

On cross-examination, Triestman addressed some of 12 E 72nd’s complaints about the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Feigen v. Advance Capital Management Corp.
150 A.D.2d 281 (Appellate Division of the Supreme Court of New York, 1989)
Clark-Fitzpatrick, Inc. v. Long Island Rail Road
516 N.E.2d 190 (New York Court of Appeals, 1987)
West-Fair Electric Contractors v. Aetna Casualty & Surety Co.
661 N.E.2d 967 (New York Court of Appeals, 1995)
Cooper, Bamundo, Hecht & Longworth, LLP v. Kuczinski
14 A.D.3d 644 (Appellate Division of the Supreme Court of New York, 2005)
Superb General Contracting Co. v. City of New York
70 A.D.3d 517 (Appellate Division of the Supreme Court of New York, 2010)
Burns Electric Co. v. Walton Street Associates
136 A.D.2d 291 (Appellate Division of the Supreme Court of New York, 1988)
Ellis v. Abbey & Ellis
294 A.D.2d 168 (Appellate Division of the Supreme Court of New York, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
2025 NY Slip Op 31827(U), Counsel Stack Legal Research, https://law.counselstack.com/opinion/olek-inc-v-merrick-real-estate-group-inc-nysupctnewyork-2025.