Old St. Paul Missionary Baptist Church v. First Nation Insurance Group

707 F. Supp. 2d 811, 2010 U.S. Dist. LEXIS 38058, 2010 WL 1540827
CourtDistrict Court, E.D. Arkansas
DecidedApril 16, 2010
DocketCase No. 3:07CV00043JLH
StatusPublished

This text of 707 F. Supp. 2d 811 (Old St. Paul Missionary Baptist Church v. First Nation Insurance Group) is published on Counsel Stack Legal Research, covering District Court, E.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Old St. Paul Missionary Baptist Church v. First Nation Insurance Group, 707 F. Supp. 2d 811, 2010 U.S. Dist. LEXIS 38058, 2010 WL 1540827 (E.D. Ark. 2010).

Opinion

OPINION AND ORDER

J. LEON HOLMES, District Judge.

Old St. Paul Missionary Baptist Church brings this action against First Nation Insurance Group; AA Risk Management, Inc.; AA communications, Inc.; Gwen Moyo; Graig Greene; Daniel Esparza; James Zoucha; and Cong Li. Old St. Paul has filed a motion for summary judgment, as has Daniel Esparza. For reasons discussed below, the Court treats Esparza’s motion for summary judgment as a separate response to Old St. Paul’s motion for summary judgment. For the following reasons, Old St. Paul’s motion for summary judgment is granted in part and denied in part, and Esparza’s motion for summary judgment is denied.

I.

A court should enter summary judgment if the evidence, viewed in the light most favorable to the nonmoving party, demonstrates that there is no genuine issue of material fact and that the moving party is entitled to judgment as a matter of law. Fed.R.CivP. 56(c); see also Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 250, 106 S.Ct. 2505, 2511, 91 L.Ed.2d 202 (1986); Cheshewalla v. Rand & Son Constr. Co., 415 F.3d 847, 850 (8th Cir.2005). The moving party bears the initial responsibility of demonstrating the absence of a genuine issue of material fact. Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 2553, 91 L.Ed.2d 265 (1986). If the moving party meets its burden, the nonmoving party must “come forward with ‘specific facts showing that there is a genuine issue for trial.’ ” Matsushita Elec. Indus. Co. v. Zenith Radio, 475 U.S. 574, 587, 106 S.Ct. 1348, 1356, 89 L.Ed.2d 538 (1986) (quoting *814 Fed.R.Civ.P. 56(e)) (emphasis in original). A genuine issue exists only if there is sufficient evidence to allow a jury to return a verdict for the nonmoving party. Anderson, 477 U.S. at 249, 106 S.Ct. at 2511.

II.

Old St. Paul Missionary Baptist Church is located in West Memphis, Arkansas. In 2003, it decided to build a new worship center. Blockett Woody was hired as the project manager, and Templebloc, Inc., as the general contractor. Templebloc was owned by Kenneth “Ted” Blockett. Because Woody lacked an Arkansas license, the project eventually continued with Templebloc as both contractor and project manager. Old St. Paul’s construction contract with Templebloc was valued at $2,690,659.

The project was financed in part by a construction loan from the Bank of Bartlett, which required a bond. Blockett, owner of Templebloc, obtained payment and performance bonds from First Nation Insurance Group. The bonds were signed by Blockett (on behalf of Templebloc) and Gwen Moyo (on behalf of both First Nation Insurance Group and AA Communications), and they covered the full amount of the construction contract: $2,690,659. Templebloc is listed as the contractor, Old St. Paul as the owner, and First Nation Insurance Group as the surety. According to the bonds, First Nation Insurance Group had given a general power of attorney to Gwen Moyo. Pursuant to Moyo’s instructions, the bank wired $121,079.65 1 from Old St. Paul’s construction account to her and AA Communications, Inc.

Around November and December 2006, the construction slowed, and concerns were raised over whether Templebloc was adequately paying subcontractors and vendors. Templebloc eventually walked away from the project. As a result, in December 2006 Old St. Paul’s pastor, Rev. Frederick Anthony, met with Moyo and Craig Greene, who held himself out to be a representative of AA Risk Management. They requested that Old St. Paul provide additional information, which Rev. Anthony said he did.

On January 10, 2007, there was a meeting in West Memphis regarding the construction and bond issues. Present at the meeting were Rev. Anthony, members of Old St. Paul’s building committee, Moyo (representing First Nation Insurance Group), Greene (who said he was representing AA Risk Management), Blockett (representing Templebloc), Samuel Turner (the architect), and Daniel Esparza (who said he was representing First Nation Insurance Group). Rev. Anthony recorded that meeting, and Old St. Paul submitted a copy of the recording as evidence. At the outset, Moyo characterized the purpose of the meeting as investigatory — to investigate Old St. Paul’s claim under its performance bond with First Nation Insurance Group. Moyo said she had contacted and spoken with the contractors and other entities involved in the project. Moyo questioned Rev. Anthony and the building commission as to why Old St. Paul and the bank approved payment of upwards of 95% of the contract price for work that had not been partially or substantially completed. Rev. Anthony countered that the contractor had abandoned the project, and that the performance bond obligated First Nation Insurance Group to complete the project if the contractor was in default. Rev. Anthony then questioned whether, if the contractor was properly declared to be in default, First Nation Insurance Group would abide by the terms of the performance bond. Moyo then criticized Old St. Paul for not having paid certain of its *815 contractors for completed work on a timely basis or for significant periods of time. Moyo asked Blockett why Templebloc had boarded up the building, removed equipment and personnel, and appeared to have ceased doing any work on the project. Blockett never provided a direct answer, and at one point suggested that he would not answer the question while the meeting was still being recorded. Moyo alleged that Old St. Paul had defaulted as the owner because it paid upwards of 95% on the total contract price while simultaneously asserting that the project was substantially incomplete. Moyo, Esparza, and Greene took the position that Temple-bloc had not actually abandoned the project at that time because it still had property on site. Moyo alleged that Old St. Paul had not been honest with First Nation Insurance Group as to the progress that actually had been made and the amount of payment given to contractors and subcontractors. The meeting ended with no apparent agreement as to how the parties were going to proceed in resolving the dispute.

On January 30, 2007, Old St. Paul notified both First Nation Insurance Group and Templebloc that Templebloc was in default on its contract. 2 Unable to resolve the disputes, Old St. Paul terminated Templebloc’s contract on February 9, 2007, and declared it to be in default pursuant to Paragraph 3 of the performance bond.

Pursuant to Paragraph 4 of its performance bond, Old St. Paul then attempted to contact First Nation Insurance Group. Paragraph 4 states that after Old St. Paul properly declared Templebloc to be in default, First Nation Insurance Group was to take one of the following actions:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
National Labor Relations Board v. Bolivar-Tees, Inc.
551 F.3d 722 (Eighth Circuit, 2008)
Newmark v. R K O General, Inc.
294 F. Supp. 358 (S.D. New York, 1968)
Gorman v. Gilliam
374 S.W.3d 117 (Court of Appeals of Arkansas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
707 F. Supp. 2d 811, 2010 U.S. Dist. LEXIS 38058, 2010 WL 1540827, Counsel Stack Legal Research, https://law.counselstack.com/opinion/old-st-paul-missionary-baptist-church-v-first-nation-insurance-group-ared-2010.