Old National Bank v. Lewis County

242 P. 961, 137 Wash. 436, 1926 Wash. LEXIS 582
CourtWashington Supreme Court
DecidedJanuary 25, 1926
DocketNo. 19563. Department One.
StatusPublished
Cited by11 cases

This text of 242 P. 961 (Old National Bank v. Lewis County) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Old National Bank v. Lewis County, 242 P. 961, 137 Wash. 436, 1926 Wash. LEXIS 582 (Wash. 1926).

Opinion

Fullerton, J.

The county of Lewis entered into a contract with one Graves by the terms of which the latter agreed to furnish all of the necessary labor and material, and construct a bridge for the county. The contract was in the usual form in such cases, and, *438 among other things, provided that the contractor should furnish a bond conditioned, as. the statute requires, to pay for all labor, material and supplies furnished the contractor in the prosecution of the work. Graves furnished a bond with the Maryland Casualty Company as surety, which the county officials accepted as a compliance with the statute. He entered upon the performance of the work, but, later on, defaulted in performance and abandoned the work, leaving unpaid a large indebtedness to laborers, materialmen and those furnishing supplies. These persons filed claims against the bond, and subsequently began an action to enforce their claims. The surety defended on the ground that the bond furnished was not the statutory bond, that it did not obligate the surety to answer for the contract- or’s defaults, but was conditioned to indemnify the county against loss or damage arising from the contractor’s default, and that the claimants had no right of recovery thereon. This defense the trial court sustained and dismissed the action, and its ruling was affirmed by this court. Wallace Equipment Co. v. Graves, 132 Wash. 141, 231 Pac. 458.

The contract entered into between the county and Graves provided for partial payments to Graves during the progress of the work, to be determined as to the amount from estimates made at stated times by the engineer engaged to supervise the work. On entering into the contract, Graves, as a consideration for advancements made and to be made to him by the Old National Bank, of Spokane, assigned these estimates to that bank. The first three of these were paid by the county to the bank; but, at the time of the contractor’s default, there was a fourth due in the sum of $7,183.20, which had not been paid. The bank made claim to the sum and demanded it of the county. The county refused *439 to recognize its claim, whereupon the bank brought the present action to recover the sum claimed. In its complaint it named the county as the sole defendant. The county, on its appearance in the action, moved the court to require the plaintiff to make parties defendant to the action the contractor Graves, his bondsman, and those claiming liens against the' bond, and require them to disclose what claim they had to the fund sought to be • recovered by the bank. The motion was granted by the court, and the plaintiff thereupon made them parties.

The contractor Graves did not appear in the action. The surety appeared and filed an answer disclaiming interest in the controversy. The persons having claims against the contractor also appeared and answered. At that time, the cause in this court first mentioned had been determined, and the claimants by cross-complaints sought to charge the county with liability. The county, by its answer, put in issue the claimed right of the bank to the assigned fund, and, by replies to the various cross-complaints of the claimants, put in issue its asserted liability to answer for their claims. On the issues framed, a trial was had resulting in a judgment and decree on the issues between the plaintiff, Old National Bank, and the defendants, to the effect that the plaintiff take nothing by its action, and that the county have judgment against it for its costs. With reference to the surety, no recovery was awarded against it, and it was allowed costs against the plaintiff. On the issues between the county and the claimants furnishing labor, material, and supplies to the contractor, judgment was allowed against the county for the amount of the several claims. There are other provisions in the decree relative to the collateral rights of the parties, but, as no question is made concerning them, they need not be further noticed.

*440 Both the plaintiff, Old National Bank, and the defendant county appealed. Prior to the time the appeals were perfected in this court, however, the plaintiff dismissed by its appeal, leaving the appeal standing on the part of the county only.

The statute (Rem. Oomp. Stat., § 1159) provides that, whenever the board of county commissioners of any county shall contract with any person to do work for the counity, they shall require the person with whom the contract is made to execute and deliver to the county auditor a good and sufficient bond, with two or more sureties, or with a surety company as surety, conditioned that such person shall faithfully perform all of the provisions of the contract, and shall pay all laborers, mechanics, materialmen, and persons furnishing supplies to such contractor necessary for the prosecution of the work. By another section (lb. § 1161), it is provided that the bond shall run in the name of the state of Washington, shall be in an amount equal to the contract price, and that any of the persons mentioned in the first cited section shall have a right of action on such bond, in their own names, for labor, material and supplies furnished the contractor. It is further provided that, to perfect the right of action, the person furnishing the labor, material or supplies, shall file with the board, within thirty days after the work has been accepted, a claim in a prescribed form. By § 1160, it is provided:

“If any board of county commissioners of any county, or mayor and common council of any incorporated city or town, or tribunal transacting the business of any municipal corporation shall fail to take such bond as herein required, such county, incorporated city or town, or other municipal corporation, shall be liable to the persons mentioned in section 1159, to the full extent and for the full amount of all such debts so contracted by such contractor. ’ ’

*441 It is the first contention of the county that it is not liable in this instance, because its board did take a bond from the contractor, acting in good faith and on the advice of its legal counsel, believing it was such a bond as the statute requires. But the staitute is plain and unambiguous. Its purpose and intent are to provide for the payment of laborers, materialmen and supplymen, who shall furnish labor, material or supplies used in the prosecution of a public work; and a county, to relieve itself of the obligation, must exact a bond on which these persons may have a right of action. The bond exacted in this instance was not such a bond. It was conditioned only to save the county harmless from any claim or liability arising out of the contract, and no action could be maintained thereon by any of the persons the statute was designed to protect. Indeed, this was the very question presented in the case of Wallace Equipment Co. v. Graves, above cited. It may be, as counsel for the county argue, that the county would not be liable, if it exacted a bond good at the time it was taken, but which subsequently became worthless because of the insolvency of the surety, or if the bond taken became lost or destroyed, through no fault of the county or its officers, and could not for that reason be proven; but these are not conditions presented here, and to give assent to them does not argue in favor of the non-liability of the county on the facts as here presented.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nelson v. Dunkin
419 P.2d 984 (Washington Supreme Court, 1966)
Puget Construction Co. v. Pierce County
392 P.2d 227 (Washington Supreme Court, 1964)
Cook v. Clallam County
180 P.2d 573 (Washington Supreme Court, 1947)
Caron v. Grays Harbor County
139 P.2d 626 (Washington Supreme Court, 1943)
Holmquist v. Queen City Construction Co.
27 P.2d 1066 (Washington Supreme Court, 1934)
Shaw Supply Co. v. King County
20 P.2d 8 (Washington Supreme Court, 1932)
Puget Sound Bridge & Dredging Co. v. Jahn & Bressi
268 P. 169 (Washington Supreme Court, 1928)
Byram v. Thurston County
252 P. 943 (Washington Supreme Court, 1926)
Northern Pacific Railway Co. v. Yakima County
252 P. 942 (Washington Supreme Court, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
242 P. 961, 137 Wash. 436, 1926 Wash. LEXIS 582, Counsel Stack Legal Research, https://law.counselstack.com/opinion/old-national-bank-v-lewis-county-wash-1926.